What is a cost-plus-fixed-fee contract?

A cost-plus-fixed-fee (CPFF) contract reimburses the contractor's allowable costs and pays a fee set as a fixed dollar amount at the start, so the fee does not rise or fall with actual cost.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Under a cost-plus-fixed-fee contract, the owner pays the contractor's actual project costs (labor, materials, subcontracts, equipment, and other reimbursable items the contract allows) plus a fee agreed in dollars up front. If costs run higher than estimated, the contractor gets the costs reimbursed but the fee stays the same. If costs come in lower, the fee also stays the same. It is one flavor of cost-plus contract; others pay a percentage fee or add a guaranteed maximum price.

How CPFF works on a real job

Say an owner hires a GC to renovate an occupied hospital wing where the scope will shift as walls are opened. The estimated cost is $1,800,000 and the parties agree on a fixed fee of $144,000. Two scenarios:

ScenarioActual costFeeTotal paidFee as % of cost
Costs come in under$1,700,000$144,000$1,844,0008.5%
Costs run over$2,000,000$144,000$2,144,0007.2%

Compare that with cost plus a percentage: at 8 percent, the overrun case would pay a $160,000 fee. The fixed fee removes the contractor's reward for spending more, which is why owners prefer it over a percentage fee. The fee can still change when the scope changes. A real added scope (a new floor, an added system) normally adjusts the fee through a change order, while cost growth on the same scope does not.

CPFF on federal contracts

The Federal Acquisition Regulation defines CPFF at FAR 16.306 as a cost-reimbursement contract that pays a negotiated fee fixed at inception. The fee does not vary with actual cost but may be adjusted for changes in the work. FAR 16.306 also describes a completion form (a defined end product) and a term form (a level of effort over a period). FAR 15.404-4 sets statutory fee caps on CPFF contracts: 15 percent of estimated cost (excluding fee) for experimental, developmental, or research work, 10 percent for other CPFF contracts, and for architect-engineer services on public works, 6 percent of the estimated cost of construction for the design work. Federal cost-reimbursement contracts also bring cost accounting and audit requirements.

On private work there is no statutory fee cap, so the fee is whatever the parties negotiate. Owners often benchmark it against what a fixed-price bidder would carry for overhead and profit, and contractors should make sure it covers home office support the contract does not reimburse.

Common disputes

  1. What counts as reimbursable cost. Home office staff, small tools, equipment rates, and warranty work are frequent arguments. Define them in the contract.
  2. Scope change vs cost growth. Contractors argue for a fee increase; owners say it is the same scope costing more. Document the change at the time.
  3. Audit access. Owners usually have the right to audit costs. Messy records mean disallowed costs.
  4. Self-performed labor rates. Burden, overhead, and markup inside labor rates can double count with the fee if not spelled out.

Related terms

See GMP contract, fee, reimbursable expenses, and time and materials. The guide cost-plus vs fixed-price contracts for contractors helps you decide which to offer. Smart Business Automator tracks job costs by code with the backup attached, which makes cost-plus billing and audits easier.

Frequently asked questions

What is the difference between cost-plus-fixed-fee and cost-plus-percentage?

In CPFF the fee is a set dollar amount. In cost-plus-percentage the fee is a percentage of actual cost, so it grows when costs grow. FAR 16.102 says the cost-plus-a-percentage-of-cost system shall not be used on federal contracts.

Can the fixed fee change?

Yes, when the scope of work changes. Under FAR 16.306 the fee may be adjusted for changes in the work, but not for cost overruns on the same scope.

What is the maximum fee on a federal CPFF contract?

Under FAR 15.404-4, generally 10 percent of estimated cost excluding fee, 15 percent for experimental, developmental, or research work, with a separate 6 percent limit for architect-engineer design services on public works.

Is CPFF good for contractors?

It removes most cost risk, but caps upside and brings audit scrutiny. It fits uncertain scopes where a fixed price would need a huge contingency.

Sources

  1. Acquisition.gov: FAR 16.306 Cost-plus-fixed-fee contracts
  2. Acquisition.gov: FAR 15.404-4 Profit
  3. Acquisition.gov: FAR 16.102 Policies
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment