Materials and procurement

How to track shipments for construction projects

Track every critical shipment from order acknowledgment to the job site: confirm the ship date, get the carrier and tracking or PRO number, check status on a set schedule, plan the unload, inspect before signing, and write any damage on the delivery receipt.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

To track shipments on a construction project, keep one shipment list per job with the PO, supplier, promised ship date, carrier, tracking or PRO number, and the date the item is needed on site. Get the order acknowledged in writing, follow up on a fixed schedule as the ship date gets closer, confirm the carrier and delivery window two days out, and have someone ready to unload and inspect. If anything is damaged or short, write it on the delivery receipt before anyone signs. That last step decides whether you can recover the cost later.

This guide focuses on shipments in transit: the stretch between "the supplier says it is ordered" and "it is on the ground." For receiving and site storage, see how to track materials and deliveries on job sites.

Which shipments need active tracking

You cannot chase every box of screws. Track actively anything that is long lead time, on the critical path, expensive, custom, or hard to replace. Typical examples:

  • Switchgear, panelboards, transformers, and generators.
  • Rooftop units, chillers, air handlers, and other major HVAC equipment.
  • Structural steel, joists, and deck.
  • Storefront, curtain wall, and custom doors and hardware.
  • Elevators, specialty equipment, and anything shipped from overseas.

Step by step: tracking construction shipments

1. Start the list at buyout

When you issue the purchase order, add a line to the shipment list with the need-by date from the schedule. Work backward: if the switchgear must be set by May 15, and the supplier quotes 20 weeks after approved submittals, you know when submittals must be approved. Tie this to your submittal schedule.

2. Get a written order acknowledgment

A verbal "it is in production" is not a date. Ask for an order acknowledgment that confirms quantities, model numbers, and a ship date. Check it against the PO. Errors caught here cost an email. Errors caught at delivery cost weeks.

3. Follow up on a schedule, tighter as the date gets close

A simple expediting rhythm works: monthly while the item is far out, every two weeks inside two months, weekly inside a month, and daily the week it ships. Each call asks the same thing: is the ship date still good, and if not, what is the new date and why?

4. Capture the carrier, tracking, and bill of lading

When it ships, get the carrier name, the tracking or PRO number, the bill of lading, the number of pieces and weight, and whether it is coming by parcel, less-than-truckload, full truckload, or flatbed. Freight that goes through terminals can sit a day or two between legs, so the carrier's tracking page is often more accurate than the supplier's estimate.

5. Confirm the delivery window and unload plan

Two days out, confirm the delivery date and time window, the truck type, and whether it needs a liftgate, forklift, or crane. Tell the driver about gate hours, site access, and where to stage. Your site logistics plan should already show the laydown area.

6. Inspect before signing

Count pieces against the bill of lading and look for visible damage: crushed crates, tipped equipment, wet packaging, broken shock indicators. Write every exception on the delivery receipt, with the driver present, and take photos. Open crates promptly to check for concealed damage.

7. File freight claims fast

For interstate truck shipments, federal law (49 U.S.C. 14706) makes carriers liable for actual loss or injury to the property and says a carrier cannot give you less than 9 months to file a claim or less than 2 years to sue after it denies the claim in writing. Carriers and contracts can set terms beyond those minimums, and shipments by sea, air, or parcel follow different rules, so check the bill of lading. Do not wait for the minimum. File with photos, the annotated delivery receipt, and the invoice for the damaged item, and order a replacement at the same time.

Worked example: switchgear for a medical office building

Say an electrical contractor on a medical office building orders switchgear in January with a quoted lead time of 22 weeks after approved submittals. Submittals are approved February 10, so the target ship date is mid-July. Permanent power is scheduled for early August.

Example: shipment log entries for the switchgear
DateStatus updateAction
Feb 12Order acknowledged, ship date July 14Logged, monthly follow-up set
May 20Supplier moves ship date to July 28GC and owner notified, schedule impact reviewed
June 18Ship date confirmed July 28, flatbed, crane neededCrane booked for July 31
July 28Shipped, PRO number and bill of lading receivedDaily tracking on carrier site
July 31Delivered, one section with a dented door panelException written on receipt, photos, claim filed

The two-week slip in May came with enough warning to resequence work and notify the owner in writing, which protects the contractor if the delay becomes a claim. The dent was documented on the receipt, so the claim was not a he-said, she-said with the carrier.

Tracking overseas and multi-leg shipments

Imported items such as specialty fixtures, stone, tile, or custom equipment move through more hands: a factory, an ocean or air carrier, a port, customs clearance, and a domestic trucker. Each handoff is a chance for a delay. Ask the supplier who arranges each leg and who is responsible for customs clearance and duties, since that affects both cost and who you call when something stalls. Get the vessel or flight details and the expected port arrival date, then add time for customs and the domestic leg before you promise anything to the schedule.

For these items, keep a second need-by date that is earlier than the real one. Port and customs delays are common enough that a few weeks of cushion is cheaper than a crew standing around waiting for tile.

Mistakes to avoid

  • Trusting the original lead time and never calling again until the week it is due.
  • Tracking shipments in one person's email inbox, where nobody else can see them.
  • Signing a clean delivery receipt and finding damage the next day.
  • Not giving written notice of supplier delays that affect the schedule. See how to document construction delays for claims.
  • No unload plan, so a truck waits hours or leaves and redelivers for a fee.

Templates, terms, and tools

Use the material delivery log template for arrivals and the submittal log template to keep approvals on pace. Related reading: how to manage construction procurement and how to manage supplier relationships in construction.

Smart Business Automator includes shipment tracking tied to each job and purchase order, with risk alerts when a ship date moves past the need-by date. See construction workflow automation.

Frequently asked questions

What is a PRO number?

A PRO number is the tracking number a freight carrier assigns to a less-than-truckload or truckload shipment. Use it on the carrier's website to check status, and reference it on any freight claim.

How long do I have to file a freight damage claim?

For interstate motor carrier shipments, federal law prevents carriers from setting less than 9 months to file a claim. Your bill of lading may give more time, and other modes follow different rules. File as soon as damage is found.

Who is responsible for tracking shipments, the GC or the sub?

Usually the party that issued the purchase order tracks it. The GC should still keep a project-wide list of critical shipments from all subs, since a late sub delivery can hold up the whole schedule.

What should I do if a shipment arrives damaged?

Write the damage on the delivery receipt with the driver present, take photos, keep the packaging, notify the supplier and carrier the same day, and file a written claim with supporting documents.

Sources

  1. Cornell Law School Legal Information Institute: 49 U.S. Code 14706, Liability of carriers under receipts and bills of lading
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.