Legal

Indiana prompt payment act and retainage rules

On Indiana public works, the owner holds either up to 6% of completed work until the job is 50% complete or up to 3% until substantial completion, the contractor can have retainage placed in escrow, and payment is due within 61 days after substantial completion. Late public payments carry a 1% per month penalty.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Indiana's prompt payment and retainage rules are written for public works. State projects follow IC 4-13.6-7 and local projects follow IC 36-1-12-14, and the two use the same formula: the owner may hold up to 6% of the value of satisfactorily completed work until the job is 50% complete and nothing after that, or up to 3% until substantial completion. Retainage can sit in an escrow account, and it must be paid out within 61 days after substantial completion. Separately, IC 5-17-5-1 charges state agencies and political subdivisions a penalty of 1% per month when they pay a public works contract late.

Indiana public works payment rules at a glance
RuleState projects (IC 4-13.6-7)Local projects (IC 36-1-12-14)
When retainage rules applyEstimated cost of $1,000,000 or moreContracts over $200,000 (board may apply them to smaller ones); highways, roads, streets, alleys and bridges excluded
Retainage optionsUp to 6% until 50% complete, then none; or up to 3% until substantial completionSame
Minor unfinished items200% of each item's value held after substantial completionSame
EscrowBank, savings and loan, the state, or a state instrumentality; agent chosen by mutual agreementHeld by the board or in escrow with a bank, savings and loan, or the state, at the contractor's discretion
Release deadlineFinal settlement within 61 days after substantial completionPaid within 61 days after substantial completion
Interest on retainageEscrow income goes with the principalBoard does not owe interest on retainage it holds itself; escrow income goes with the principal
Late payment penalty1% per month (IC 5-17-5-1)1% per month (IC 5-17-5-1)
Prime to subContract must address sub retainage and payment; claims can be withheldSame

Retainage on state public works

When a state public works project is estimated at $1,000,000 or more, IC 4-13.6-7-2 requires the contract to include retainage provisions at three levels: from the state to the contractor, from the contractor to its subs, and for paying subs and suppliers. The state can hold back enough from the contractor to cover unpaid subs and suppliers.

Section 3 gives the state two choices. It can hold up to 6% of the value of satisfactorily completed work until the job is 50% complete and then stop withholding, or hold up to 3% until substantial completion. Once the work is substantially complete, it holds 200% of the value of any minor items still open, as set by the architect or engineer, until they are done. Under section 8, final settlement is due no later than 61 days after substantial completion if the contractor has materially fulfilled the contract, minus those punch items and any sub or supplier claims on file.

Retainage on local public works

Cities, counties, school corporations and other political subdivisions follow IC 36-1-12-14 on public works contracts over $200,000, excluding highways, roads, streets, alleys, bridges and related structures. A board may also apply the provisions to smaller contracts. The percentages match the state rules: 6% to the halfway point, or 3% to substantial completion, plus 200% of open punch items.

The difference is where the money sits. At the contractor's discretion, retainage can be held by the board or placed in escrow with a bank, savings and loan, or the state, with the escrow agent picked by mutual agreement. A board holding retainage itself does not have to pay interest on it. In escrow, the agent invests the money, takes a reasonable fee from the income, and releases income in proportion to principal. Payment of all principal and income is due within 61 days after substantial completion.

Late payment penalty: 1% per month

IC 5-17-5-1 makes every state agency and political subdivision that fails to pay a written public works contract on time liable for a penalty of 1% per month on the amount due. If the contract does not set a payment date, payment is timely if the check or warrant goes out within 35 days of receiving the goods or services or a properly completed claim, whichever applies. When a local legislative body or board must approve the claim, the 35 days run from the first regularly scheduled meeting held at least 10 days after the claim arrives.

Subcontractors and private jobs

The public works statutes require the contract to cover retainage from subs and payment of subs, and they let the owner withhold money to cover sub and supplier claims. The sections covered here do not set a fixed number of days for a prime to pay a sub after it is paid, and they do not address pay-if-paid clauses, so the subcontract terms matter. Read the payment article before you sign.

Private work is outside these statutes. Payment timing and retainage on a private Indiana job come from the contract, and the main tool for unpaid work is an Indiana mechanics lien. Also check Indiana contractor licensing and our prompt payment act primer. Smart Business Automator tracks retainage held and billed on every job and subcontract; see construction accounts receivable automation.

Frequently asked questions

How much retainage can an Indiana public owner hold?

Up to 6% of the value of satisfactorily completed work until the project is 50% complete and nothing after, or up to 3% until substantial completion. After substantial completion, 200% of the value of open minor items may be held.

When must Indiana public works retainage be released?

Within 61 days after substantial completion, subject to amounts held for unfinished minor items and for subcontractor or supplier claims.

Can Indiana retainage be placed in escrow?

Yes. On local public works the contractor can choose escrow with a bank, savings and loan, or the state. State projects allow escrow with a bank, savings and loan, the state, or a state instrumentality, with the agent chosen by mutual agreement.

What is the penalty for late payment by an Indiana public owner?

IC 5-17-5-1 sets a penalty of 1% per month on amounts due when a state agency or political subdivision fails to pay a public works contract on time.

Do Indiana's retainage rules apply to road work?

The local public works retainage section excludes highways, roads, streets, alleys, bridges and appurtenant structures. Check the contract for those jobs.

Sources

  1. FindLaw: Indiana Code 4-13.6-7-2, state public works retainage provisions and escrow
  2. FindLaw: Indiana Code 4-13.6-7-3, state public works retainage percentages
  3. FindLaw: Indiana Code 4-13.6-7-8, final settlement within 61 days
  4. FindLaw: Indiana Code 36-1-12-14, local public works retainage and escrow
  5. FindLaw: Indiana Code 5-17-5-1, penalty for late payment
  6. Indiana General Assembly: Indiana Code

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment