Project delivery

What is the construction documents phase?

The construction documents (CD) phase is the last major design phase, where the architect and engineers turn the approved design into the detailed drawings and specifications used for permitting, bidding, and building.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

On a typical design-bid-build project, design moves through schematic design, design development, and then construction documents. In the CD phase the decisions are already made: room layouts, structural system, major equipment, exterior materials. The job now is to document every one of those decisions in enough detail that a contractor can price it, a building department can approve it, and a crew can build it. The output is the drawing set and the project manual of specifications.

What the CD phase produces

  • Drawings: architectural plans, sections, elevations, and details; structural, mechanical, electrical, plumbing, and fire protection drawings; civil and landscape sheets where needed.
  • Specifications: the written requirements for products, execution, and quality, usually organized by MasterFormat divisions.
  • Permit set: a version submitted to the authority having jurisdiction for plan review.
  • Bid set: the set issued to contractors with bidding instructions, forms, and later any addenda.

How it looks from the contractor's side

Say a school district is renovating a gym. The architect issues a 50 percent CD set for a cost check, then a 95 percent set, then the 100 percent bid set. A GC hired early for preconstruction prices each one. At 50 percent, the estimate carries allowances for things not yet drawn, like the bleacher system. At 95 percent, the estimator finds the mechanical drawings show a new rooftop unit but the structural set has no new framing to support it. That goes back to the design team as a comment instead of becoming an RFI and a change order six months later.

On a hard-bid job, contractors only see the final bid set. Every gap and conflict in the CDs then shows up during bidding as questions, or during construction as RFIs.

Common problems and disputes

  1. Incomplete documents. CDs rushed to hit a bid date leave items "by others" or "to be coordinated," which become change orders.
  2. Conflicts between drawings and specs. The contract's order of precedence clause decides which governs, so know it before you bid.
  3. Discipline coordination gaps. Architectural, structural, and MEP sets that were never overlaid produce clashes in the field.
  4. Design-build blur. On design-build projects, the contractor may own CD completeness, so gaps become the contractor's cost, not the owner's.

A practical habit for estimators: when a new CD set arrives, compare it to the last one sheet by sheet before pricing anything. Clouded revisions help, but designers do not always cloud every change. A quick overlay of the plumbing plan or the door schedule often turns up a change worth thousands that nobody flagged.

Related terms

See contract documents, constructability review, and design-bid-build. The guides how to read construction plans for estimating and how to write bid clarifications and exclusions help you price from CDs without inheriting the design team's gaps.

Frequently asked questions

What comes before the construction documents phase?

Usually schematic design and design development. Design development fixes the major systems and sizes; the CD phase documents them in full detail.

Are construction documents the same as contract documents?

Not exactly. The construction documents are the drawings and specs. The contract documents usually include those plus the agreement, general conditions, supplementary conditions, addenda, and modifications.

Who produces the construction documents?

The architect and its engineering consultants on design-bid-build work. On design-build projects, the design-builder's design team does.

Can contractors comment during the CD phase?

Yes, when they are hired early under CM at risk, design-build, or a preconstruction agreement. That is one of the main benefits of early contractor involvement.