Project delivery

What is an award in construction?

In construction bidding, the award is the owner's formal decision to give the contract to a specific bidder. On public work it follows rules about responsiveness, responsibility, and price.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

An award (or contract award) is the point at which the owner selects a bidder and offers it the contract. It comes after bids or proposals are opened and evaluated, and before the contract is signed and a notice to proceed is issued. On private work an award can be as informal as a phone call followed by a letter of intent. On public work it is a formal act with written notice.

The word has a second meaning in disputes: an arbitration award is the arbitrator's decision. This entry covers the bidding meaning. For the other, see arbitration.

How an award works on public and private jobs

On federal sealed bid work, FAR 14.408-1 says the contracting officer makes the award by written or electronic notice, within the time for acceptance stated in the bid or an extension, to the responsible bidder whose bid, conforming to the invitation, will be most advantageous to the government, considering only price and the price-related factors in the invitation. Many state and local agencies follow a similar pattern under their own procurement laws: lowest responsive bidder that is also a responsible bidder.

On negotiated or best value procurement jobs, the award goes to the proposal that offers the best overall value under the stated evaluation factors, which may not be the lowest price. On private work, the owner can award to anyone it likes, for any reason, unless it promised otherwise in the bid documents.

Example: from bid opening to award

A school district opens bids for a $2.4 million roof replacement. The apparent low bidder is $2,215,000. Staff checks that the bid form is complete, the bid bond is attached, all addenda were acknowledged, and the bidder holds the required license. The second bidder points out that the low bidder did not list a required subcontractor. Staff reviews the bid documents, decides whether the omission makes the bid nonresponsive, and sends a recommendation to the board. The board votes to award. A written notice of award goes out with instructions to return signed contracts, a performance bond and payment bond, and insurance certificates within a set number of days.

What happens after award

  1. The contractor signs the agreement and delivers bonds and insurance.
  2. The owner signs and issues a notice to proceed.
  3. The contractor holds a buyout of subcontracts and purchase orders, ideally within the first few weeks.
  4. Estimating hands the job to operations. See how to hand off a job from estimating to operations.

Common mistakes and disputes

  • Starting work on a verbal award. Without a signed contract or a clear letter of intent, the contractor may not get paid for early work if the award falls through.
  • Missing the post-award deadline. Failing to deliver bonds and insurance on time can let the owner award to the next bidder and claim the bid bond.
  • Bid protests. Public owners face protests from losing bidders. Protest procedures and deadlines are set by each agency and are usually short.
  • Holding subs to prices without telling them. Subs whose numbers you carried should hear about the award promptly; prices often expire.

Related terms

See invitation to bid, bid tabulation, sealed bid, and executed contract. For public work, read how to bid public construction projects. Smart Business Automator carries the estimate, bid, and scope into the new project at award so operations does not start from scratch. See estimate to project handoff automation.

Frequently asked questions

What is the difference between award and notice to proceed?

The award selects the contractor and offers the contract. The notice to proceed, issued after the contract is signed, authorizes work to start and often starts the contract time.

Does the lowest bidder always win the award?

On many sealed bid public jobs, the award goes to the lowest responsive and responsible bidder. On best value procurements and private jobs, the owner can choose a higher price for better value or other reasons stated in the solicitation.

How is an award made on a federal sealed bid job?

FAR 14.408-1 calls for written or electronic notice to the responsible bidder whose conforming bid is most advantageous to the government, considering only price and price-related factors, within the bid acceptance period.

Can an owner cancel an award?

Sometimes, depending on the bid documents, the procurement law that applies, and whether a contract has been signed. Public owners often reserve the right to reject all bids.

Sources

  1. Acquisition.gov: FAR 14.408-1, General (award of sealed bid contracts)
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment