What is construction management at risk?

Construction management at risk (CMAR or CM at risk) is a project delivery method where the owner hires a construction manager during design for preconstruction services, then that CM builds the project, usually under a guaranteed maximum price, and carries the risk of cost overruns above it.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

In CM at risk, the builder shows up early. The owner hires an architect for design and, separately, a construction manager who provides precon services: estimating, constructability reviews, scheduling, and early trade input. Once the design is far enough along, the CM commits to a guaranteed maximum price (GMP) and becomes the contractor, holding the trade subcontracts.

The "at risk" part means the CM is on the hook for costs above the GMP, subject to the contract's change rules. That is the main difference from construction manager agent, where the CM advises the owner and does not hold the trade contracts or the cost risk.

How CMAR works on a real job

Say a school district plans a $22 million middle school. It selects a CM through a qualifications-based process. In precon, the CM prices schematic design, flags that the gym roof structure is driving cost, and suggests a different framing system. At 90 percent construction documents, the CM bids the trade packages and builds the GMP.

Example GMP build-up
ComponentAmount
Trade subcontracts (bid)$17,850,000
General conditions$1,320,000
CM contingency$540,000
Insurance and bonds$310,000
CM fee$780,000
Guaranteed maximum price$20,800,000

If the final cost of the work plus fee comes in at $20.3 million, the savings are handled however the contract says: returned to the owner, or split between owner and CM. If it comes in at $21.1 million with no owner changes, the CM absorbs the $300,000. That is why CMs fight hard over what was and was not in the documents when the GMP was signed, and why the GMP amendment needs a clear list of the drawings it was priced from.

Pros and cons

  • Pros for owners: builder input during design, earlier cost certainty, the ability to start early packages before design is done (fast-track construction), and a single contractor accountable for delivery.
  • Cons for owners: the GMP is negotiated, not hard bid, so price transparency depends on open books and audits.
  • For CMs: a fee on cost-of-the-work, but real risk if scope is unclear when the GMP is set.
  • For trade contractors: often still a competitive bid, but with more coordination meetings and open-book reporting.

Common disputes in CMAR

  1. What counts as a scope change versus design development that the CM should have priced into the GMP.
  2. Use of CM contingency versus owner contingency.
  3. Whether certain costs are reimbursable as cost of the work or covered by the fee or general conditions.
  4. Shared savings calculations at closeout.

Related terms

See GMP contract, design-bid-build, design-build, delivery method, and open book pricing. Public owners often have specific statutes allowing CMAR; check state and local public works bidding basics.

Frequently asked questions

What does CMAR stand for?

Construction management at risk, sometimes written CM at risk or CM/GC.

Is CM at risk the same as design-build?

No. In design-build, one entity holds both design and construction. In CMAR, the owner holds separate contracts with the architect and the CM.

Who holds the subcontracts in CMAR?

The CM at risk holds the trade subcontracts, just like a general contractor.

How is a CM at risk selected?

Often by qualifications, or a mix of qualifications and fee, rather than lowest total price. Public owners must follow their own procurement rules.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.