Estimating

What is labor burden in construction?

Labor burden is the cost a contractor pays for each worker beyond the hourly wage, such as payroll taxes, workers' comp, insurance, and benefits. It is usually expressed as a percentage added to base pay.

A foreperson with a clipboard briefs four workers wearing hardhats, safety glasses and high visibility vests.
A focused crew briefing connects the day’s work with its hazards and controls. AI-generated illustration.

Labor burden is everything an employee costs you that does not show up as their hourly wage. Employer payroll taxes, unemployment insurance, workers' compensation premiums, health coverage, retirement contributions, paid time off, and in some shops vehicles, phones, and safety gear. Add it all up, divide by base wages, and you get a burden percentage. A carpenter paid $30 an hour does not cost $30 an hour. The real number is higher, and that real number is what belongs in your estimate and your job costing.

Some contractors call it payroll burden or the burden rate. The idea is the same: the gap between what lands on the paycheck and what leaves the company bank account.

What goes into labor burden

A few pieces are fixed by federal law. The rest depend on your state, your insurance carrier, and the benefits you choose to offer.

Common labor burden components
ComponentHow it is set
Social Security (employer share)6.2 percent of wages, up to the annual wage base ($184,500 for 2026 earnings, per the IRS)
Medicare (employer share)1.45 percent of all covered wages, with no cap
Federal unemployment (FUTA)6.0 percent of the first $7,000 per employee, reduced by up to a 5.4 percent credit for state unemployment tax paid
State unemployment (SUTA)Rate assigned by your state, often based on your layoff history
Workers' compensationRate per $100 of payroll by job class, adjusted by your experience mod
General liability (if payroll-rated)Set by your carrier; many construction policies rate on payroll
Benefits and paid time offYour company's health, retirement, holiday, vacation, and sick pay policies

Paid time off is the one most people forget. If a laborer gets two weeks of vacation and six holidays, you are paying for hours that never touch a job. Those dollars have to be spread over the hours that do.

How to calculate it, with an example

Work it per employee or per job class, on an annual basis. Say a framing lead earns $32 an hour and is paid for 2,080 hours, which is $66,560 in wages. Of those, 80 hours are vacation and 48 are holidays, so only 1,952 hours are billable to jobs.

  1. Total the annual employer costs for that person. In this made-up example: $5,092 in Social Security and Medicare (7.65 percent), $420 in federal and state unemployment, $6,000 in workers' comp, $7,200 in health insurance, and $2,000 in retirement match, for $20,712.
  2. Add the paid but non-working wages: 128 hours at $32 is $4,096.
  3. Total burden is $24,808. Divide by the wages for hours actually worked ($32 times 1,952, or $62,464).
  4. The burden rate is about 39.7 percent. The true cost of a field hour is roughly $44.70, not $32.

Your own percentage will be different. Workers' comp alone varies a lot between an office estimator and a roofer, which is why burden should be calculated by trade or class, not as one company-wide number. The guide on how to calculate labor burden for construction workers walks through a full worksheet.

Common mistakes

  • Bidding at base wage. An estimator who prices 400 hours at $32 instead of $44.70 has left about $5,000 on the table before the first stud goes up.
  • Using last year's rate forever. Wage bases, unemployment rates, insurance renewals, and benefit costs change. Recheck burden at least once a year.
  • One rate for everyone. A blended number undercharges high-risk trades and overcharges low-risk ones.
  • Mixing burden with overhead. Burden follows the worker. Office rent and the owner's truck are overhead. Keep them separate so job costs stay honest.
  • Forgetting overtime. Payroll taxes rise with overtime pay, but fixed costs like health insurance do not, so the burden percentage on an overtime hour behaves differently.

Related terms

Labor burden feeds the labor rate and burden rate you use in estimating, and it shows up again in markup decisions and direct costs on the job cost report. Smart Business Automator lets you load burdened rates by employee class so job costing and WIP views show what labor really costs, not just what was on the paycheck. See job costing and WIP automation.

Frequently asked questions

What is a typical labor burden percentage in construction?

It depends heavily on trade, state, insurance history, and benefits. Calculate your own by class rather than borrowing a rule of thumb, because workers' comp and benefits swing the number more than anything else.

Is labor burden the same as overhead?

No. Labor burden is the extra cost tied to each employee's hours. Overhead covers company costs that are not tied to a specific worker or job, like office rent and accounting.

Do subcontractors have labor burden?

Yes, for their own employees. When you hire a sub, their burden is already inside their price, so you do not add burden to subcontract costs.

Should labor burden be charged on T&M work?

Usually yes. Time and materials rates should be built from the burdened cost of labor plus markup. Check the contract, since some define exactly what the hourly rate must include.

Sources

  1. IRS: Topic no. 751, Social Security and Medicare withholding rates
  2. IRS: Topic no. 759, Form 940, Employer's Annual Federal Unemployment (FUTA) Tax Return
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment