What is a no-damages-for-delay clause in construction?

A no-damages-for-delay clause says that if the job is delayed, the contractor's only remedy is a time extension. No extra money for idle crews, extended overhead, or escalated costs, even when the owner caused the delay.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A no-damages-for-delay clause is contract language that takes money off the table when a project runs late. If a delay happens, the contractor can ask for more days, but it cannot recover the cost of those days. The clause shows up in prime contracts written by owners and, very often, in subcontracts where the general contractor passes the same risk down through a flow-down clause.

On paper it protects the owner's budget. In practice it shifts the cost of the owner's own late decisions, late permits, and slow approvals onto the people building the job.

How the clause works on a real job

Say a mechanical sub has a $620,000 subcontract on a school addition. The owner takes six weeks to approve a revised duct layout after an RFI. The sub's crew is pulled off, remobilized later, and the job runs into winter. Its real costs: a second mobilization, a foreman kept on site, temporary heat, and labor inefficiency. Call it $48,000.

Without the clause, the sub prices that as a delay claim and seeks a change order. With an enforceable no-damages-for-delay clause, the sub gets six weeks added to its schedule and nothing else. The extension at least protects it from liquidated damages, but the $48,000 comes out of its margin.

Where these clauses are limited or void

Enforceability depends heavily on the state. Some legislatures have stepped in. Washington, for example, makes a construction contract clause that waives a contractor's, subcontractor's, or supplier's right to damages for unreasonable delay caused by the contractee void and unenforceable as against public policy (RCW 4.24.360). That statute still allows clauses that require notice of delays, set up arbitration or another settlement process, or provide for reasonable liquidated damages.

Other states enforce the clauses as written but courts carve out exceptions. Common exceptions argued in court include delays the parties never contemplated, delays so long they amount to abandonment, delays caused by the owner's bad faith or active interference, and delays caused by the owner's breach of a basic contract duty. Whether any of these apply is a fact fight, and the rules differ for public and private work in some states. Check your state's statute and get legal advice before relying on one.

Common mistakes and disputes

  1. Signing without reading the delay section. The clause is often buried in general conditions or a rider, not the main agreement.
  2. Assuming the clause is void, then skipping notice. Even where the clause is unenforceable, the notice requirements usually are not, and a late notice of claim can sink the claim on its own.
  3. Not separating owner delay from your own slow work. Courts look harder at claims where the contractor's own delays overlap.
  4. Agreeing to a subcontract clause that is broader than the GC's own prime contract. If the owner has to pay the GC for delay but the GC owes the sub nothing, the sub is carrying the GC's risk for free.
  5. Failing to price the risk at bid time when the clause cannot be negotiated out.

Related terms

This clause sits alongside excusable delay, force majeure, extended general conditions, and the broader claim process. For a list of other risky clauses to flag before signing, see construction contract clauses that hurt subcontractors.

Frequently asked questions

Does a no-damages-for-delay clause stop me from getting more time?

Usually not. Most of these clauses keep the time extension as the remedy and only bar money. That extension still matters because it protects you from liquidated damages.

Is a no-damages-for-delay clause enforceable?

It depends on the state and on the facts. Some states, such as Washington under RCW 4.24.360, void these clauses for delays caused by the contractee. Others enforce them with court-made exceptions. Get legal advice for your state.

Should a subcontractor sign one?

Read the prime contract first. If the GC can recover delay costs from the owner but your subcontract bars you from recovering anything, ask for matching terms or a pass-through of any recovery the GC gets.

Do I still need to send notice of a delay if the clause is void?

Yes. Notice provisions are generally enforced separately, and Washington's statute expressly preserves clauses requiring notice of delays. Send written notice on time either way.

Sources

  1. Washington State Legislature: RCW 4.24.360, Construction contracts, damages for delay
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment