What is a notice of claim in construction?

A notice of claim is the written notice a contract requires a party to give, usually within a set number of days, before it can pursue a claim for more time or money.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A notice of claim is a short, formal letter that tells the other party an event has happened that you believe entitles you to extra time, extra money, or both. Most construction contracts make timely written notice a condition of recovery. Miss the deadline and a valid claim can be denied on that alone, no matter how strong the facts are.

The notice is not the full claim. It is the flag that preserves your rights. The detailed pricing and schedule analysis usually follow later.

How notice works on a real job

Say a framing sub on a 64-unit apartment building is told by the GC's superintendent to install extra blocking for owner-supplied cabinets that are not on the drawings. Nobody issues a change order. The subcontract requires written notice of any claim within 7 days of the event.

On day two the sub's PM emails a notice letter: what was directed, by whom, on what date, why it is outside the scope of work, and that the sub will seek an adjustment once costs are known. The crew tracks the blocking hours separately in its daily logs. Three weeks later the sub submits a priced change order request of $11,400 with the hours and material attached. Because the notice went out on time, the argument is about the price, not about whether the sub is allowed to ask.

Federal contract notice rules

Federal construction contracts set specific notice and claim rules in the FAR clauses. Some key ones:

Selected federal notice and claim rules (check the clauses in your contract)
RuleWhat it saysSource
Assert right to adjustment for a changeWithin 30 days after receiving a written change order or giving notice of a constructive change (the government may extend it)FAR 52.243-4(e)
Cost look-back limitNo adjustment for costs incurred more than 20 days before written notice of a constructive change (except defective specifications)FAR 52.243-4(d)
Claim submission deadlineWithin 6 years after accrual of the claimFAR 52.233-1
CertificationRequired for contractor claims exceeding $100,000FAR 52.233-1
Contracting officer decisionWithin 60 days for claims of $100,000 or less when requested in writing; for larger certified claims, decide or set a decision date within 60 daysFAR 52.233-1

State public owners and private contracts set their own windows, often much shorter. AIA and ConsensusDocs forms each have their own notice terms, and owners frequently tighten them in supplemental conditions. Read your contract for the exact number of days and the required method of delivery.

Common mistakes

  1. Waiting until the cost is known. Notice should go out when the event happens, with costs to follow.
  2. Relying on meeting minutes or a phone call. Most contracts require written notice to a named person or address.
  3. Sending notice to the wrong party. Subs give notice to the GC, not the owner, unless the contract says otherwise.
  4. Letting the GC sit on it. If the GC must pass your notice to the owner, ask for confirmation that it did.
  5. Forgetting continuing events. A long delay may need an initial notice and periodic updates.

Related terms

Notice of claim ties to delay claims, differing site conditions, change order requests, and early warning notices. For documentation habits that support a claim, see how to document construction delays for claims.

Frequently asked questions

What should a notice of claim include?

The date and description of the event, who directed or caused it, the contract clause you rely on, and a statement that you expect an adjustment in time, money, or both. A cost estimate is helpful but often not required at this stage.

Is an email enough for notice?

Only if the contract allows it. Many contracts name the method (certified mail, delivery to a named address, or a project platform). Follow the notice section exactly.

What happens if I miss the notice deadline?

The other side may deny the claim for lack of notice. Some courts excuse late notice if the other party knew about the issue and was not harmed, but that is a fight you do not want to depend on.

How long do federal contractors have to submit a claim?

Under FAR 52.233-1, a contractor claim must be submitted within 6 years after it accrues, and claims over $100,000 must be certified. Notice of changes has shorter windows under the changes clause.

Sources

  1. Acquisition.gov: FAR 52.233-1, Disputes
  2. Acquisition.gov: FAR 52.243-4, Changes
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.