Change orders and contracts

How to handle differing site conditions claims

When you find conditions that differ from the contract documents or from what is normally expected, stop disturbing them, give written notice right away, document everything, and submit a priced request for money and time. Notice comes first, because late notice can forfeit the claim.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

To handle a differing site conditions claim, stop work on the affected area if you can do so safely, give the owner written notice before you disturb the condition further, document it with photos, measurements, and logs, let the owner inspect, and then submit a priced request for added cost and time. Read your contract's differing site conditions clause first, because it sets the notice timing and what counts as a qualifying condition. A real condition with poor notice often loses. A modest condition with clean notice and records often gets paid.

Differing site conditions are the classic hidden risk: rock where the borings showed clay, groundwater the geotech report did not mention, an abandoned tank, concealed rot behind plaster, or a buried foundation from an old building. The clause exists so contractors do not have to price every possible surprise into every bid. It only works if you follow it.

Type I and Type II differing site conditions

Many contracts follow the federal model. FAR 52.236-2 recognizes two categories, usually called Type I and Type II.

The two categories in the federal clause
TypeWhat it coversExample
Type ISubsurface or latent physical conditions that differ materially from those indicated in the contractBorings show sandy clay to 12 feet; excavation hits rock at 6 feet
Type IIUnknown physical conditions of an unusual nature that differ materially from those ordinarily encountered in this kind of workAn undocumented concrete vault under a parking lot with no indication in the documents

Type I claims compare the site to what the contract documents indicated, so the boring logs, survey, and drawings are the key evidence. Type II claims compare the site to what a reasonable contractor would expect for this kind of work in this area, which is harder to prove. Private contracts may use similar language, a narrower version, or none at all, and some try to disclaim the owner's soils data entirely. Know which you signed. Related term: concealed conditions.

Step-by-step: handling a differing site condition

1. Stop disturbing the condition

The federal clause requires written notice before the conditions are disturbed. Many private clauses say the same or give a short window. Move the crew to other work if you can, keep the area safe, and leave the condition visible for the owner to see.

2. Give prompt written notice

Send notice to the person the contract names, by the method it requires. Describe what you found, where, when, how it differs from the documents or normal expectation, and that you consider it a differing site condition. Under FAR 52.236-2, no adjustment is allowed unless the required written notice was given (the contracting officer may extend the time), and no request is allowed after final payment. A phone call to the owner's rep is a courtesy, not notice.

3. Document before, during, and after

Take dated photos and video with a scale reference, record depths and locations against the survey, keep test results, and note crew and equipment standing by. Put all of it in the daily log. If you can, have the owner's rep or engineer sign a field observation.

4. Let the owner investigate and direct

The federal clause requires the contracting officer to investigate promptly. Ask the owner for written direction on how to proceed. If they direct a solution (over-excavate, dewater, redesign the footing), that direction is also a change and should be documented.

5. Track costs separately

Open a separate cost code for the condition and charge every hour, rental, haul ticket, and material to it. Mixed costs are the fastest way to lose a valid claim on the numbers.

6. Submit a priced request for money and time

Price the added work with backup, and include schedule impact if the condition affected the critical path. Use the change order process if the owner agrees; use the claims clause and a formal notice of claim if they do not.

Worked example: rock on a utility trench

Here is an illustration. A site contractor is installing 900 linear feet of storm drain on a public project. The geotech report and boring logs show silty clay to 10 feet. At station 4+00, the excavator hits rock at 5 feet. The super stops the trench, moves the crew to the next run, photographs the rock face, and calls the PM. The PM sends written notice that afternoon citing the borings and the contract's differing site conditions clause. The owner's engineer visits the next morning and directs the contractor to bring in a hydraulic hammer.

Example claim summary (illustrative numbers)
Cost itemAmount
Hammer rental, 8 days$11,200
Added operator and labor hours$14,600
Haul-off of rock spoils and import of bedding$9,800
Crew standby while awaiting direction (4 hours)$1,900
Overhead and profit per contract$5,625
Total requested$43,125
Time requested6 working days

Because the contractor gave notice before disturbing the rock, kept costs on a separate code, and tied the claim to the boring logs, the owner's engineer accepts entitlement quickly. The parties negotiate the overhead figure and settle with a change order. Without notice, the same contractor would be arguing about whether the rock was ever there.

Notice the details that made this claim easy to accept. The PM quoted the exact boring log depth, the photos showed a tape measure against the rock face, and the cost code captured the hammer rental from the first hour. None of that took legal skill. It took a crew and a PM who knew the drill before the excavator ever hit rock.

Mistakes to avoid

  • Digging through it first, telling the owner later. Once the condition is gone, so is the best evidence.
  • Ignoring the site investigation clause. Many contracts, including FAR 52.236-3 on federal work, have the contractor acknowledge it investigated the site and the conditions that can be reasonably determined from an inspection and the contract documents. Claims for things a site visit would have shown are weak.
  • Not reading the geotech report at bid time. You cannot prove a difference from documents you never read.
  • Forgetting the time impact. The extra cost is often smaller than the delay. Ask for both.
  • Waiting for final payment. Many clauses bar requests after final payment. Raise it while the work is open.

Templates, terms, and tools

The construction daily report template and construction change order template cover the paperwork. Read how to document construction delays for claims for the schedule side, and see the site survey and delay claim entries. Smart Business Automator keeps photos, daily logs, notices, and cost codes on the same job record, and can summarize daily logs so a claim package comes together faster. See construction workflow automation.

Frequently asked questions

What is a Type I differing site condition?

A subsurface or latent physical condition that differs materially from what the contract documents indicated, such as rock where the borings showed soil. It is usually the easier type to prove because you compare the site to the documents.

What is a Type II differing site condition?

An unknown physical condition of an unusual nature that differs materially from what is ordinarily encountered in that kind of work. It does not depend on what the documents showed, but proving it is unusual takes more evidence.

What if my contract has no differing site conditions clause?

The contractor may carry the risk of unexpected conditions, unless another clause or state law shifts it. Price that risk, add clarifications to your bid, or ask for a clause before signing.

How fast do I need to give notice?

It depends on the contract. The federal clause requires written notice before the condition is disturbed. Private contracts vary. Give notice the same day whenever you can.

Can I get time as well as money?

Usually yes, if the condition delayed the critical path and the contract allows it. Request both in the same submission and support the time with schedule analysis.

Sources

  1. Acquisition.gov: FAR 52.236-2 Differing Site Conditions
  2. Acquisition.gov: FAR 52.236-3 Site Investigation and Conditions Affecting the Work
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.