Scheduling

How to handle weather delays in the schedule

Build normal weather for the season into the schedule up front, log every weather day against the activities it stopped, give written notice on time, and ask for a time extension when weather beyond the normal amount delays critical work.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

To handle weather delays in a construction schedule, plan for the weather you can expect in that location and season before the job starts, either as lost days on a weather calendar or as weather activities in the schedule. During the job, record each weather day in the daily log, note which activities stopped, and check whether those activities were on the critical path. Give written notice within the contract's deadline, and request a time extension for weather that was worse than normal and pushed the finish date. Normal rain is usually your risk. Unusual weather often is not.

Most contracts treat weather this way. On federal fixed-price construction, FAR 52.249-10 lists unusually severe weather among the causes of excusable delay, and it requires the contractor to notify the contracting officer in writing of the causes of delay within 10 days from the beginning of the delay, unless the contracting officer extends the time. The key word is unusually. Ordinary weather for the season is expected to be in your plan.

Step 1: Plan normal weather into the schedule

Look up historical weather for the site. NOAA's National Centers for Environmental Information publishes U.S. Climate Normals, 30-year averages for 1991 to 2020 from thousands of stations, including statistics such as days with precipitation and days below freezing. Use them to estimate how many work days per month you will lose on weather-sensitive activities like earthwork, concrete, roofing, and exterior finishes.

  • Weather calendar: assign weather-sensitive activities to a calendar with fewer working days in wet or cold months. Interior work stays on the normal calendar.
  • Weather allowance activities: add an explicit weather float activity before key milestones like dry-in. It is visible and easy to track.
  • Sequence for the season: plan to get the building dried in before the wet or cold months so interior trades can keep working.
  • Read the contract: some public contracts include a table of anticipated adverse weather days per month. That table, not your own estimate, then sets the baseline for what counts as unusual.

Step 2: Log weather the same way every day

The daily log is the evidence. Record conditions at start, midday, and end of shift, rainfall or temperature if known, site conditions like mud or standing water, and which crews were sent home or moved indoors. Most important, record which scheduled activities could not proceed. A note that just says rain does not tell anyone whether the critical path stopped. See how to write a construction daily log.

Count drying days too. The day after a heavy storm, the site may still be too wet for grading even under clear skies. If the contract or the owner accepts drying days as weather impact, the log has to show why work could not proceed.

Step 3: Measure the impact on the critical path

Weather days alone do not earn time. The delay has to push the finish. U.S. Army Corps of Engineers Engineering and Construction Bulletin 2008-23 spells this out for its contracts: a weather time extension is only awarded if the weather was unusually severe and affected progress of activities on the longest path. The delay is added to the schedule as a fragnet tied into the logic, the schedule is recalculated, and the extension is based on the new early finish. The bulletin also says it does not matter whether the contractor was ahead or behind schedule when the weather hit.

That is a good method to follow on any job. If rain stopped the roofer while roofing had 12 days of float, the finish did not move. If it stopped the steel erection that was driving dry-in, it did. Critical path method explained for contractors walks through the math.

Worked example: counting unusual weather days

Here is an example on a public building job whose contract lists anticipated adverse weather days by month. In March the table shows 5 anticipated days. The superintendent's daily logs show 9 days in March when rain or ground conditions stopped work on the critical activity, site utilities ahead of the building pad.

Example: March weather tally against the contract table
ItemDays
Anticipated adverse weather days in contract table, March5
Actual days weather stopped critical work, per daily logs9
Days beyond the anticipated amount4
Calculated finish date movement after adding a 4-day weather fragnet4 working days

The contractor sends written notice of the delay within the contract's deadline after the unusual weather begins, then submits the time request with the March logs, the weather fragnet, and the recalculated schedule. The first 5 days are the contractor's risk because they were expected. The other 4 days support an extension. On most contracts, weather extensions add time but not money, so the main value is protection from liquidated damages.

Step 4: Keep the schedule and the subs current

After a weather event, update the schedule and the three-week look-ahead right away. Move weather-sensitive work, pull interior work forward where possible, and tell subs who are affected. If the delay pushes outdoor work into a colder or wetter month, note that too. The Corps bulletin says that pushing weather-dependent critical work into months with more anticipated bad weather can justify more time, and pushing it into drier months can mean less.

Weather on private and residential jobs

Private contracts and home improvement agreements are often silent on weather or say only that delays beyond the contractor's control extend the time. That leaves room for argument. Put a short weather clause in your own contract: how weather days are counted, how the client is notified, and that the completion date moves by the days lost on work that controls the finish. Then send a short written update after each weather event. A homeowner who got a text on the day of the storm rarely disputes the new date later.

Mistakes to avoid

  1. Scheduling exterior work with no weather allowance, then claiming every rain day.
  2. Logging weather without naming the activities it stopped.
  3. Missing the notice deadline in the contract.
  4. Asking for time when the stopped work had float.
  5. Forgetting drying days and site cleanup after storms.
  6. Not passing weather time through to subs, or not asking subs for their own weather logs.

Templates, terms, and tools

Use the construction daily report template with a weather section on every page. Related terms: weather delay, excusable delay, force majeure, and notice of claim. For seasonal planning, see how to plan for weather on construction projects.

Smart Business Automator can summarize a week of daily logs for the PM, pulling out weather stoppages and the work they affected, which makes the monthly weather tally faster to build. See construction workflow automation.

Frequently asked questions

Do contractors get paid for weather delays?

Usually not. Most contracts treat weather as an excusable but non-compensable delay: you get time, not money. Read your contract, because some private contracts handle it differently.

What counts as unusually severe weather?

Weather worse than what is normal for that location and time of year. Some public contracts define normal with a table of anticipated adverse weather days per month. Others leave it to historical data, such as NOAA climate normals.

How fast do I have to give notice of a weather delay?

Check the contract. On federal fixed-price construction, FAR 52.249-10 requires written notice of the causes of delay within 10 days from the beginning of the delay unless the contracting officer extends the time. Private contracts set their own deadlines.

Can I claim a weather day if the crew worked half a day?

It depends on how the contract defines a weather delay day. Record the hours lost and the activities affected either way, so the log supports whatever rule the contract uses.

Sources

  1. Acquisition.gov: FAR 52.249-10 Default (Fixed-Price Construction)
  2. U.S. Army Corps of Engineers (via WBDG): Engineering and Construction Bulletin 2008-23, Adverse Weather Policy for Construction Contracts
  3. NOAA National Centers for Environmental Information: U.S. Climate Normals