Legal

Iowa prompt payment act and retainage rules

On Iowa public improvements, Iowa Code chapter 573 caps retainage at 3%, adds interest when an approved progress payment sits unpaid 14 days (up to 30 if the contract says so), and requires contractors to pay subs within 7 days of being paid. Chapter 573 does not reach private jobs, which run on contract terms.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Iowa's prompt payment and retainage rules for public work sit in Iowa Code chapter 573. A public owner may hold no more than 3% of each monthly payment, owes interest if an approved progress payment stays unpaid 14 days after receipt (or up to 30 days if the contract allows), and must release retained funds after completion under sections 573.14 or 573.28. Contractors must pay subs within 7 days after being paid for their work. In 2025 the legislature cut the retainage cap from five percent to three percent, so older contracts and specs may still show the old number.

Iowa public improvement payment rules at a glance
RuleRequirementSection
Progress paymentsMonthly, based on the architect or engineer's estimate573.12(1)
Owner payment deadlineInterest if approved payment unpaid 14 days after receipt; contract may extend to no more than 30 days573.12(2)
Prime pays subsWithin 7 days after receiving payment for that sub's work573.12(2)(b)
Retainage cap3% of each monthly payment; same cap from prime to sub (or less if the subcontract says so)573.12(1), 573.13
Release after completionHeld 30 days after completion and final acceptance; then released, minus double any claims on file573.14(1)
Final payment interestPayment due within 40 days (contract may say up to 50) after completion, acceptance and closeout documents573.14(2)
Early release on requestAfter substantial completion; paid with next monthly payment or within 30 days, whichever is sooner573.28
Interest ratePublic funds deposit rate under 12C.6; prime plus 1% for late early-release retainage and for regents institutions573.14, 573.28
Private workNo general prompt payment or retainage statute; contract terms applyNone

Progress payments and the 14-day clock

Section 573.12 says payments on public improvement contracts are made monthly on estimates of labor performed and material delivered, as determined by the project architect or engineer. Once an architect or engineer approves a progress payment, interest starts if it remains unpaid 14 days after the request was received by the person named in the contract. The contract documents can stretch that to a longer period, but no more than 30 days, to give the owner time to inspect the work.

Interest runs from the day after that period ends until payment. The rate is the one set in section 12C.6 for a deposit of public funds for a comparable period, as of the day interest begins. When a prime receives interest, it owes each sub a proportional share.

Paying subs within 7 days

A progress or final payment for a sub's satisfactory work is due no later than 7 days after the contractor receives payment for that work. If the owner has not paid for reasons that are not the sub's fault, payment is due a reasonable time after the contractor could have been paid. Accepting payment for one sub's work does not waive the contractor's other claims on the project.

That last rule works against a strict pay-if-paid clause on Iowa public work: when the delay is not the sub's fault, the statute still points to a reasonable time for payment. Say an electrical sub bills $62,000 and the city holds the GC's pay app over an unrelated dispute with the roofer. The electrician's money should not sit indefinitely.

Retainage limits and release

The retained amount, which section 573.13 says can never be more than 3% of the contract price, is a fund for paying labor and material claims on the job. Under 573.14, the owner holds it for 30 days after completion and final acceptance. If claims are on file then, the owner keeps double the total of the claims and releases the rest. If none are on file, it releases everything.

  • Final payment: if any amount due is not paid within 40 days (or up to 50 if the contract says so) after the work is completed, accepted, and all required closeout documents are in, interest accrues.
  • 95% option (573.15A): a public owner may release retained funds at 95% completion after a 30-day claim window.
  • Early release on request (573.28): after all or part of the work is substantially complete, the contractor may request release after giving all known subs and suppliers a 10-day written notice in the statutory form.
  • Timing: approved early-release funds are paid with the next monthly payment or within 30 days, whichever comes first. If not released within 30 days of the due date, interest runs at prime plus 1% a year.
  • Holdback: the owner may keep 200% of the value of labor or materials still to be provided, and must give a written itemization or denial reason within 30 days.
  • Pass-through: contractors release retained funds to subs the same way they received them, and each sub passes them down to lower tiers.

Private jobs in Iowa

Chapter 573 is limited to public improvements, and we found no general Iowa statute setting payment deadlines or capping retainage on private construction. On a private job, the contract sets the terms, and your leverage for unpaid work is the Iowa mechanics lien process under chapter 572. Negotiate pay timing, retainage percentage, and release triggers before you sign.

Staying on top of the dates

Log the date each pay app is received, the approval date, and the day payment arrives, so you can show when the 14-day and 7-day clocks started. Track retainage by job and by sub so the 573.28 request goes out the day substantial completion is certified. Also review Iowa contractor registration and our prompt payment act primer. Smart Business Automator tracks invoices and retainage on every job; see construction accounts receivable automation.

Frequently asked questions

What is the retainage limit on Iowa public projects?

Three percent. A 2025 amendment to Iowa Code 573.12 and 573.13 reduced the cap from five percent to three percent for the owner and for contractors holding from subs.

How fast must an Iowa contractor pay subcontractors on public work?

Within 7 days after the contractor receives payment for that sub's work, or a reasonable time after it could have been paid if the delay is not the sub's fault.

When does interest start on a late Iowa public progress payment?

When an approved progress payment stays unpaid 14 days after receipt of the request, or after a longer period of up to 30 days if the contract documents specify it.

Can I get retainage released before final acceptance in Iowa?

Yes. Under Iowa Code 573.28 you may request release after substantial completion, after giving subs and suppliers a 10-day notice. The owner may hold 200% of the value of remaining work.

Does Iowa have a private prompt payment law?

Not a general one that we found. Chapter 573 covers public improvements only, so private jobs follow the contract, backed by mechanics lien rights.

Sources

  1. Iowa Legislature: Iowa Code 2026, chapter 573, labor and material on public improvements
  2. Iowa Legislature: 2025 Acts chapter 29 (S.F. 574), public improvement contracts fee retention
  3. Iowa Legislature: Iowa Code 2026, chapter 572, mechanic's liens
  4. Iowa Legislature: Iowa Code 2026, chapter 26, public construction bidding

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.