Prompt payment

Mississippi prompt payment act and retainage rules

Mississippi sets interest on late owner payments (45 days on public work, 30 on private), a 15 day deadline for primes to pay subs on both, and 5 percent retainage on public building contracts that halves at 50 percent complete.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

In Mississippi, a public owner that pays a progress or final payment more than 45 calendar days late owes interest of 1 percent per month. A private owner owes the same 1 percent once a payment is 30 calendar days late. On both kinds of jobs, the prime has 15 days after it gets paid to pay its subs and suppliers, or it owes a penalty of 0.5 percent per day, capped at 15 percent of the balance. Public building contracts carry 5 percent retainage, cut in half once the job is 50 percent complete on contracts of $250,000 or more. No statute reviewed here caps retainage on private jobs.

Mississippi payment and retainage rules at a glance
RulePublic workPrivate work
Owner progress paymentsDue per the contract; 1 percent per month interest if unpaid 45 calendar days after due (31-5-25)Due per the contract; 1 percent per month interest from the due date if unpaid 30 calendar days after due (87-7-3)
Final paymentDue at the first of completion, beneficial use, or certification; interest after 45 daysDue at the first of completion, beneficial use, or certification; interest after 30 days
Surety consentRequired in writing before final paymentRequired in writing before final payment
Prime to sub15 days after receipt; 0.5 percent per day penalty, capped at 15 percent (31-5-27)15 days after receipt; same penalty and cap (87-7-5); single-family homes excluded
Retainage5 percent; on contracts of $250,000 or more and on all subcontracts, half returned at 50 percent complete, then 2.5 percent (31-5-33)No statutory cap found; set by contract
ExcludedRetainage section does not cover Mississippi Transportation Commission road and bridge contractsPenalty section does not cover single-family dwellings

Public construction payment in Mississippi

Mississippi's public prompt payment act, Miss. Code 31-5-25, does not set its own due date for progress payments. The contract does. What the statute adds is interest: if a partial, progress, or interim payment is still unpaid 45 calendar days after it came due, it bears 1 percent per month until paid. Final payment comes due at the first of four events: completion or substantial completion under the contract, the owner's beneficial use or occupancy (with an exception for renovation work where the owner keeps using the building), certification by the architect or engineer, or certification by the contracting authority. Interest starts if it is not paid within 45 days of that event.

Two practical points. Final payment cannot go out until the contractor's surety consents in writing and that consent is delivered to the contracting authority. And the prime must certify monthly to the architect or engineer what it paid subs from the prior pay request. Get the consent of surety request to the bonding agent early in closeout.

Public retainage under Miss. Code 31-5-33

  • Scope: contracts by the state, its agencies, or political subdivisions to build, repair, alter, or demolish buildings, structures, or facilities. Mississippi Transportation Commission road and bridge contracts are excluded.
  • Rate: 5 percent of progress payments based on estimated percent complete. A prime cannot hold a higher percentage from a sub than the owner holds from the prime.
  • Reduction: on contracts of $250,000 or more, and on any subcontract, once the work is at least 50 percent complete, on schedule, and satisfactory to the architect or engineer, half of the retainage held to date is returned, and future retainage drops to 2.5 percent.
  • Security: retainage is money or other security agreed by the parties, held until final completion and acceptance.
  • Release: tied to final completion and acceptance; the statute sets no separate day count, so interest exposure runs through the final payment rules in 31-5-25.

Take a $1,800,000 county courthouse renovation. By the 50 percent mark, about $45,000 is held. Once the architect confirms the job is on schedule and satisfactory, $22,500 comes back to the prime for distribution to subs and suppliers, and each later payment holds 2.5 percent instead of 5. The statute text does not spell out a reduction for prime contracts under $250,000.

Private construction payment in Mississippi

Mississippi does have private prompt pay rules, in Title 87. Under Miss. Code 87-7-3, progress payments are due when the contract says, and anything unpaid 30 calendar days after the due date earns 1 percent per month from the due date. Final payment uses the same first-to-occur triggers as public work, minus the contracting authority certification, and also requires written surety consent before it is made.

Miss. Code 87-7-5 requires a prime, on receipt of any owner payment, to pay each sub and supplier in proportion to its completed work, and to split a partial payment pro rata. Missing the 15 day window without reasonable cause costs 0.5 percent per day, up to 15 percent of the balance. Single-family dwellings are excluded. A neighboring rule, 87-7-7, makes it a misdemeanor for a contractor to cash a joint check without the co-payee's endorsement or written authorization, with a fine of up to $500 per violation and restitution.

Pay-if-paid and practical steps

The 15 day rules run from the prime's receipt of payment, which fits pay-when-paid timing. None of the sections reviewed here say whether a pay-if-paid clause is enforceable, so that question turns on the subcontract wording and case law. Get advice before relying on one.

See the Mississippi mechanics lien guide for lien deadlines, Mississippi prevailing wage for public pay rules, and the Mississippi contractor license guide for licensing. Smart Business Automator tracks due dates, retainage, and sub payments by job through construction accounts receivable automation.

Frequently asked questions

What is the retainage rate on Mississippi public projects?

5 percent under Miss. Code 31-5-33. On contracts of $250,000 or more and on any subcontract, half of the retainage held is returned at 50 percent complete if the work is on schedule and satisfactory, and future retainage drops to 2.5 percent.

How long does a Mississippi contractor have to pay subcontractors?

15 days after receiving payment, on both public (31-5-27) and private (87-7-5) work. Late payment without reasonable cause carries a penalty of 0.5 percent per day, capped at 15 percent of the outstanding balance.

Does Mississippi have a private prompt payment law?

Yes. Miss. Code 87-7-3 adds 1 percent per month interest on owner payments more than 30 calendar days late, and 87-7-5 sets the 15 day sub payment rule, except on single-family dwellings.

Why is my final payment held for surety consent?

Both 31-5-25 and 87-7-3 say final payment cannot be made until the contractor's surety consents in writing and that consent is delivered. Request it from your bonding company as soon as completion is in sight.

Does the public retainage statute apply to highway jobs?

No. Miss. Code 31-5-33 excludes contracts let by the Mississippi Transportation Commission for roads and bridges, which follow the contract and agency specifications.

Sources

  1. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 31-5-25, payments on public construction contracts
  2. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 31-5-27, payment of subcontractors on public work
  3. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 31-5-33, public retainage
  4. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 87-7-3, payments to contractors on private work
  5. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 87-7-5, payment of subcontractors on private work
  6. FindLaw (Mississippi Code text, current as of January 1, 2025): Miss. Code 87-7-7, joint check endorsement

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment