Prompt payment

Wisconsin prompt payment act and retainage rules

On Wisconsin state and local government work, the owner has 30 days to pay, the prime has 7 days after it is paid to pay its subs, and late money earns 12 percent a year compounded monthly. Retainage is capped at 5 percent until the job is half done. Private jobs have no prompt pay statute.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Wisconsin splits its public prompt payment act into two nearly identical sections: Wis. Stat. § 16.528 for state agencies and § 66.0135 for local governments such as cities, villages, towns, counties and special districts. Under both, a payment is timely if it goes out within 30 days after a properly completed invoice or receipt and acceptance of the work, whichever is later. After that, interest runs from day 31. A principal contractor must pay its subs within 7 days after it receives any payment from the agency. Retainage on public work is governed by § 66.0901(9). There is no matching statute for private construction.

Wisconsin construction payment rules at a glance
RulePublic workPrivate work
Owner pays prime30 days after a properly completed invoice or receipt and acceptance, whichever is later (§ 16.528(2), § 66.0135(2))No prompt pay statute; contract governs
Interest on late owner paymentFrom day 31 at the § 71.82(1)(a) rate (12 percent per year), compounded monthlyContract terms
Prime pays subs7 days after the prime receives any payment from the agency; interest from day 8; same rule for lower tiersNo statutory deadline; owner payments are trust funds under § 779.02(5)
Retainage capUp to 5 percent until 50 percent complete; up to 10 percent total if progress is unsatisfactory (§ 66.0901(9))None in statute
Retainage releaseMay be paid at substantial completion; no fixed day countPer contract
Attorney feesLocal government: court awards reasonable fees to the prevailing party in a suit for interest (§ 66.0135(6))Per contract

When a Wisconsin public owner must pay

The two statutes run the same clock. Payment is timely if it is mailed, delivered or transferred by the later of the date printed on a properly completed invoice or 30 days after the agency receives that invoice or receives and accepts the work. If the agency misses that, it owes interest on the balance from the 31st day at the rate in § 71.82(1)(a), which is 12 percent per year, compounded monthly.

Invoice errors cut both ways. A local agency that gets an improperly completed invoice must tell the sender why within 10 working days (§ 66.0135(7)). If the local agency skips that notice, the 30-day clock runs from the flawed invoice anyway. Section 16.528 works the same way for state agencies that do not follow the invoice procedure in § 16.53(2).

  • Federal money: the state statute does not apply to the part of a contract paid with federal funds. The local version excludes the portion for which federal payment has not been received.
  • Good faith disputes: no interest is owed on an amount in good faith dispute if the agency sends notice of the dispute before the payment becomes late, by first-class mail, personal delivery, or the method in the contract.
  • Contract terms: a local contract can set different deadlines only if the deviation appeared in the original bid or proposal. A state services contract can set its own payment timing and consequences.

The 7-day rule for subcontractors

Section 16.528(2m) and § 66.0135(3) require a principal contractor to pay subs for satisfactory work no later than 7 days after the prime receives any payment from the agency. Interest starts on the 8th day at the same 12 percent rate, compounded monthly. Subs that get paid must pay their own lower-tier subs on the same terms. The good faith dispute exception applies here too, so a GC that disputes a sub's work should send written notice before day 7.

Example: a GC on a $480,000 village library addition gets the village's progress payment on September 10. The masonry sub's share is $38,000. Payment must go out by September 17. If it goes out October 17 instead, the sub can claim about a month of interest at 12 percent a year on $38,000, roughly $380.

Retainage on Wisconsin public work

Section 66.0901(9) covers contracts of $1,000 or more for public works, buildings, supplies or materials let by a municipality, a term the statute defines to include the state, school districts, sewer districts and technical college districts. The Department of Transportation is carved out of this subsection, so highway work follows WisDOT's own contract terms.

  • Up to 50 percent complete: retainage may not exceed 5 percent of each estimate.
  • At 50 percent: further partial payments are made in full, and amounts already retained stay held. No more may be retained unless the architect or engineer certifies the job is not proceeding satisfactorily.
  • If progress is unsatisfactory: additional amounts may be retained, but total retainage may not exceed 10 percent of the value of work completed.
  • Substantial completion: retained amounts may be paid. If weather or material shortages leave work unfinished, the owner can hold enough to cover that work, or release all retainage in exchange for a bond or other collateral.
  • Stored materials: estimates may include fabricated or manufactured materials the contractor has paid for that are delivered or properly stored.

The statute says retainage "may be paid" at substantial completion but sets no day count. Push for a release date in the contract and get the closeout package moving early.

Private jobs and pay-if-paid

No Wisconsin statute sets payment deadlines or retainage limits for private construction. What private work does have is § 779.02(5): money an owner pays a prime or sub for improvements is a trust fund for the people who supplied labor and materials until they are paid. Spending it elsewhere is theft by contractor, and officers or agents responsible for the misuse can be personally liable. The statutes reviewed here do not mention pay-if-paid clauses by name; Husch Blackwell's July 2020 survey lists them as not permissible in Wisconsin. Get counsel's read before relying on one. Lien deadlines are covered in the Wisconsin mechanics lien guide.

Smart Business Automator records when each owner payment lands and when each sub was paid, so the 7-day window is visible on every job. See construction accounts receivable automation.

Frequently asked questions

How long does a Wisconsin government owner have to pay a contractor?

Thirty days after receiving a properly completed invoice or receiving and accepting the work, whichever is later, under Wis. Stat. § 16.528 (state agencies) and § 66.0135 (local governments). Interest starts on day 31.

What is the interest rate on late public payments in Wisconsin?

Both statutes use the rate in § 71.82(1)(a), which is 12 percent per year, compounded monthly.

How fast must a Wisconsin prime contractor pay subs on public work?

Within 7 days after the prime receives any payment from the agency. Interest runs from the 8th day, and lower-tier subs get the same protection.

What is the retainage limit on Wisconsin public projects?

Under § 66.0901(9), no more than 5 percent until the work is 50 percent complete, then no more unless the architect or engineer certifies unsatisfactory progress, with a 10 percent total ceiling. WisDOT is excluded from that subsection.

Does Wisconsin have a prompt payment law for private projects?

No. Private payment terms come from the contract, though money paid by an owner for improvements is held in trust under § 779.02(5) until labor and material suppliers are paid.

Sources

  1. Wisconsin Statutes § 16.528, Interest on late payments (state agencies)
  2. Wisconsin Statutes § 66.0135, Interest on late payments (local governments)
  3. Wisconsin Statutes § 66.0901, Public works contracts; retainage
  4. Wisconsin Statutes § 71.82, Interest
  5. Wisconsin Statutes § 779.02(5), Theft by contractors
  6. Husch Blackwell: Wisconsin state-by-state summary of prompt payment (July 2020)

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.