Pricing and estimating

How to price masonry jobs

Price masonry by counting units, dividing by your crew's daily production to get crew days, and pricing materials, labor, scaffold, and equipment before adding overhead and profit. The square foot price is the result, not the starting point.

A project engineer in a hardhat and safety vest uses a rugged tablet beside steel wall framing.
Capture field information where the work happens, then route it to the people who need it. AI-generated illustration.

To price a masonry job, take off the wall area, convert it to unit counts (block, brick, or stone), add waste, and price the units plus mortar, grout, reinforcing, ties, flashing, and caps. Divide the unit count by your crew's production rate to get crew days, multiply by the crew's burdened daily cost, and add scaffold, equipment, dust control, and disposal. Then apply overhead and a profit margin. Production rate is the number that makes or breaks a masonry bid, and the only reliable source for it is your own job history.

How masonry contractors price work

  • Unit and production pricing. Units times material cost, plus crew days from production rates. This is how most commercial block and brick is estimated, and it is the basis for every other method.
  • Square foot of wall. A price per square foot for veneer or CMU, built from the method above. Easy for GCs to compare, but only safe when you know what height, openings, and pattern it assumes. See unit cost.
  • Per 1,000 brick or per block. Common in commercial bids and when bidding labor only to a GC who supplies material.
  • Linear foot. Caps, copings, sills, and steps are often priced per foot.
  • Time and materials. Repair, tuckpointing on old buildings, and chimney work with unknown conditions. Write the rates down first; see time and materials.

The math: from wall area to units and crew days

Start with net wall area: length times height, minus openings over a size you decide (many estimators deduct only larger openings, since small ones take as much time as the wall they replace). For standard 8 by 16 inch concrete block, each unit covers 128 square inches of wall face including the joint, and a square foot is 144 square inches, so you need 1.125 block per square foot. For brick and stone, use the count per square foot from the manufacturer for the size and bond you are laying. Add waste for cuts and breakage.

Crew days equal units divided by units per crew day. That production rate changes with wall height, scaffold moves, number of corners and openings, pattern work, weather, and how far the material sits from the wall. Keep separate rates for each condition you see often, and update them from actual jobs.

Worked example: a 50 foot CMU screen wall

This is an illustration with made-up costs and a made-up production rate. Use your own supplier quotes and history. Say a customer wants a freestanding split-face CMU screen wall, 50 feet long and 6 feet high, on a new concrete footing, with vertical rebar grouted at intervals and a cap. Check local rules first: walls like this often need a permit, and retaining walls may need engineering.

  1. Area and units. 50 x 6 = 300 square feet. 300 x 1.125 = 337.5, round to 338 block. Add 5 percent as an example waste factor: 355 block.
  2. Block. 355 at an example $2.75 = $976.25.
  3. Footing. 50 feet long, 2 feet wide, 1 foot deep = 100 cubic feet, or 3.7 cubic yards. Order 4 yards at an example $170 = $680.
  4. Other materials. Rebar $420, mortar and sand $310, grout $350, cap units $450. Materials total: $3,186.25.
  5. Labor. Example production: 120 block per day for a crew of two masons and a tender. 338 / 120 = 2.8, so 3 crew days, plus one day to grout, cap, and clean. 4 days x 3 people x 8 hours = 96 hours. Add 24 hours to dig, form, and pour the footing. 120 hours at an example burdened rate of $50 = $6,000.
  6. Equipment and disposal. Mixer and wet saw rental $380 (water-fed saws are part of OSHA's silica controls), dumpster and haul-off $250. Total $630.
  7. Direct cost. $3,186.25 + $6,000 + $630 = $9,816.25.
  8. Overhead. At an example 15 percent of direct cost, add $1,472.44. Cost with overhead: $11,288.69.
  9. Profit as margin. For a 12 percent margin, divide by 0.88: $12,828.05. Quote $12,830.
  10. Check. $12,830 / 300 = about $42.77 per square foot of wall, including the footing. Compare to your past screen walls.
Example CMU wall estimate summary (illustration only)
LineAmount
Block (355 units)$976.25
Footing concrete$680.00
Rebar, mortar, sand, grout, cap$1,530.00
Labor (120 hours burdened)$6,000.00
Equipment and disposal$630.00
Overhead at 15 percent$1,472.44
Profit at 12 percent margin$1,539.36
Price (rounded)$12,830.00

Labor is about 60 percent of the direct cost here. If the crew actually lays 100 block a day instead of 120, the wall takes about 3.4 days instead of 2.8. That is roughly 14 more crew hours plus a partial day of mixer rental, and close to half the profit disappears. That is why production rates deserve more attention than material prices.

Labor, overhead, and markup

For a wage reference, the Bureau of Labor Statistics reported a median of $28.02 per hour for masonry workers in May 2025. Tenders and laborers usually cost less per hour, so build a blended crew rate from your actual mix, then add payroll taxes, workers' comp, and benefits. The method is in how to calculate labor burden.

Overhead covers your yard, trucks, mixers and scaffold not charged to jobs, office staff, insurance, and estimating time. Find your rate with how to calculate construction overhead rate. Then set profit as a margin. A 12 percent markup on $11,288.69 gives $12,643.33, which is a margin of about 10.7 percent, not 12. See markup vs margin in construction.

Costs masonry bids often miss

Common masonry add-ons and how to price them
ItemHow to priceWhy it gets missed
ScaffoldRental per week plus labor to erect, move, and dismantleMoves happen several times per elevation
Cold weather protectionBlankets, heaters, enclosures, fuel, slower productionBid in summer, built in winter
Silica controlsWet saws, shrouds, vacuums, respirators, fit testingTreated as overhead instead of job cost
Mockup panelsLump sum per panelOften required by specs before work starts
Flashing, weeps, and tiesPer linear foot or per square foot of veneerSmall items with real labor
Cleaning and sealingPer square footLeft for the end and done for free
Material handlingForklift days, distance from stockpileTight sites cut production

Mistakes that sink masonry bids

  1. Using one production rate for every wall regardless of height, openings, and pattern.
  2. Deducting every opening from the unit count but not adding labor for the cuts, lintels, and jambs around them.
  3. Pricing tuckpointing by the square foot without seeing how deep and how bad the joints are.
  4. Leaving out the footing, or assuming another trade provides it without writing that into the scope of work.
  5. Not tracking actual units per day, so bad rates repeat. Use job costing on every job.

Lay out your lines in the construction estimate template and bill from the construction invoice template. For tools that track production against the estimate, see masonry software. Smart Business Automator's estimate to project handoff automation carries estimated units and hours into the job budget so actuals can be compared.

Frequently asked questions

How many concrete blocks are in a square foot of wall?

For standard 8 by 16 inch block, 1.125 block per square foot, because each block with its joint covers 128 square inches of wall face. Add waste for cuts and breakage.

Should I price masonry per square foot or per unit?

Estimate by units and production rate, then convert to a square foot price if the customer wants one. A square foot price is only as good as the unit count and production rate behind it.

How do I find my crew's production rate?

Record units installed and hours worked by wall type on every job. After a few jobs you will have rates for straight walls, high walls, and detailed work that you can trust more than any published figure.

How should I price tuckpointing?

Inspect first. Joint depth, mortar hardness, and access drive the time. Many contractors price it per square foot after a test area, or as time and materials with a written rate when conditions are unclear.

Do silica controls belong in the job price?

Yes. Wet saws, shrouds, vacuums, and respirators are tied to specific tasks under OSHA's silica standard, so price them with the work that needs them.

Sources

  1. Bureau of Labor Statistics: Occupational Outlook Handbook, Masonry Workers
  2. eCFR via Cornell LII: 29 CFR 1926.1153, Respirable crystalline silica
  3. Smart Business Automator: pricing
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment