Pricing and estimating

How to price framing jobs

Price framing from crew hours per square foot on similar plans, multiplied by your burdened crew cost, plus adders for the things that slow a crew down, then load overhead and profit. If you supply lumber, price it separately with an escalation clause.

A project engineer in a hardhat and safety vest uses a rugged tablet beside steel wall framing.
Capture field information where the work happens, then route it to the people who need it. AI-generated illustration.

To price a framing job, measure the framed floor area, estimate crew hours from your history on similar plans (hours per square foot by stories, wall height, and roof type), multiply by your burdened crew cost per hour, add adders for stairs, vaulted or complex roofs, shear walls, decks, and equipment like a lift or forklift, then add overhead and profit. Most builders compare framing bids per square foot, so turn your total into that unit, but build it from hours. A flat per-square-foot price for every house is how framers win simple plans and lose money on the complicated ones.

Pricing methods framers use

  • Per square foot of floor area. The most common labor price for residential framing. Define what counts (living area only, or garage and porches too) on the bid, because builders measure differently.
  • Per square foot with adders. A base rate plus line items for stairs, tray or vaulted ceilings, extra wall height, complex roofs, beams, shear walls, and decks. This is the fairest method for both sides.
  • Per board foot or per piece. Some markets and commercial jobs price by lumber quantity installed. It ties price to material quantity, not complexity, so watch heavily detailed plans.
  • Lump sum. Common on custom homes and commercial work, with a written scope and exclusions.
  • Time and materials. For remodel framing, repairs, and unknown conditions. See time and materials.

Step by step: building the price

  1. Measure the job. Floor area by level, garage, porches, wall height, roof type (trusses or stick framed), and openings. Note anything that slows a crew: tall walls, steep roof pitch, many corners, engineered beams, hold-downs.
  2. Estimate crew hours. Use your own hours per square foot on similar plans. If you are new, time your crews on the first few houses and adjust. See how to estimate labor hours.
  3. Cost the labor. Hours times the burdened cost of the crew: wages plus payroll taxes, workers' compensation, and benefits. See labor burden.
  4. Add equipment and job costs. Forklift or telehandler rental, crane time for trusses if you provide it, fall protection setup, fuel, and travel to distant jobs.
  5. Add materials if you furnish them. Lumber, sheathing, fasteners, hardware, and connectors, with a waste allowance and a quote date. Lumber prices move, so add an escalation clause.
  6. Load overhead. Office, insurance, trucks, tools, software, and your salary. See how to calculate construction overhead rate.
  7. Set profit. Decide on margin and apply it consistently. See markup vs margin in construction.

Worked example: labor-only framing on a two-story house

This is a made-up example to show the math. The hours, rates, and percentages are placeholders, not market figures; use your own crew history and costs.

Say a builder sends a two-story plan with 2,600 square feet of living area and a 500 square foot garage, roof trusses, and one interior stair. On similar plans your four-person crew has averaged 0.12 crew hours per square foot of floor area, so 3,100 square feet times 0.12 is 372 crew hours. Your burdened cost for the crew averages $42 per person hour.

Example: labor-only framing estimate
ItemQuantityRateCost
Base framing labor372 hours$42 per hour$15,624
Stair adder16 hours$42 per hour$672
Telehandler rental5 days$300 per day$1,500
Fall protection setup, fasteners, fuelLot$700
Direct cost$18,496
Overhead at 15% of direct cost$2,774
Cost including overhead$21,270
Sell price at 12% net margin ($21,270 / 0.88)$24,170

Divided by 3,100 square feet, that is about $7.80 per square foot. Now say the next plan has 10-foot walls, a vaulted great room, and a hip roof. Your crew history says that kind of house takes more hours per square foot, so either the base rate goes up or the adders do. If you had bid both houses at the same flat rate, the second one would eat the profit from the first.

Overhead, labor burden, and markup

Labor is most of the cost in labor-only framing, so the burden number matters. The Bureau of Labor Statistics reported a median wage of $29.12 per hour for carpenters in May 2025, but your real cost per hour includes payroll taxes, workers' compensation (expensive for framers), and any benefits. Use how to calculate labor burden to get your own figure. Overhead for a framing sub is mostly trucks, tools, insurance, and office time spent on draws and change orders; spread it over the houses you realistically frame in a year, not your best year.

Pricing extras and change orders

Framers lose a lot of money in small extras: added blocking for cabinets and grab bars, moved openings, beam changes after the engineer's revision, rework after an inspection comment that was not your fault. Keep a unit price list for common extras (per opening moved, per beam, per hour of rework) and put it in your subcontract or bid. Then price each extra as a change order and get it approved before the crew does the work. See how to price a change order.

Safety costs belong in the price

OSHA requires fall protection for workers doing residential construction 6 feet or more above a lower level, through guardrails, safety nets, or personal fall arrest, or a written fall protection plan where those are infeasible. Setting anchors, installing guardrails on stair openings and second floor edges, and moving them as the house goes up take crew hours on every house. Count them in your hours per square foot instead of treating them as free.

Keep pricing honest with job costing

After each house, compare actual crew hours per square foot with the estimate, split by plan type and builder. If one builder's plans always run long, that builder needs a higher rate. Smart Business Automator tracks estimated against actual cost on each job and keeps change orders tied to the house, so the comparison is quick. See the framing software guide for other tools to compare.

Frequently asked questions

How do framers price jobs?

Most residential framers quote labor per square foot of floor area, often with adders for stairs, tall walls, complex roofs, and decks. Commercial and custom work is often lump sum. Build any price from crew hours on similar plans.

What square footage should a framing bid use?

State it on the bid. Some framers price living area only, others include garage, porches, and decks at a different rate. Builders measure differently, so define it to avoid disputes.

Should framers include lumber in the price?

Labor-only bids leave lumber to the builder. If you furnish lumber, price it separately with a quote date and an escalation clause, because lumber prices can move quickly.

How do I price framing extras?

Keep a unit price list for common extras such as moved openings, added blocking, and beam changes, and price each one as a change order approved before the work.

Is markup the same as margin?

No. A markup on cost gives a smaller margin on the sell price. Pick which one you target and calculate it the same way on every bid.

Sources

  1. Bureau of Labor Statistics: Carpenters, Occupational Outlook Handbook
  2. 29 CFR 1926.501, Duty to have fall protection (Cornell LII)
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment