What is a stop work order in construction?

A stop work order is a written directive to halt all or part of the work on a construction project. It can come from the owner under the contract, or from a government agency such as a building department or safety regulator.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A stop work order tells a contractor to put down the tools. It might cover the whole job or a single area or trade. There are two main kinds. A contractual stop work order comes from the owner (or a GC to its sub) under a clause in the contract, often because of funding, design changes, or disputes. A regulatory stop work order comes from a government authority, usually the local building department for unpermitted work, failed inspections, or unsafe conditions. The paperwork, the reasons, and the path to restart are different for each.

Stop work orders on federal contracts

Federal contracts can include FAR 52.242-15, Stop-Work Order. Under that clause, the contracting officer may order the contractor to stop all or part of the work for up to 90 days after the order is delivered, plus any further period the parties agree to. The contractor must comply immediately and take reasonable steps to minimize the costs tied to the stopped work. Before the period ends, the contracting officer must either cancel the order or terminate the work.

If the order is canceled or expires, work resumes, and the contractor can request an equitable adjustment to the schedule, price, or both. The request must be made within 30 days after the end of the work stoppage, though the contracting officer may still consider a later request before final payment if the facts justify it.

How a stop work order plays out on a real job

Say an owner pauses a $2.6M office renovation because its tenant deal fell through. The GC gets a written order on a Tuesday to stop all work on floors 2 and 3, while floor 1 continues.

  1. Stop and secure. The super halts work on the affected floors, protects open work, and secures stored materials.
  2. Notify subs in writing. Every affected sub gets a copy of the order and instructions the same day.
  3. Document the state of the work. Photos, percent complete by line, materials on site and in transit, and crew counts.
  4. Track costs separately. Set up a cost code for standby, demobilization, extended general conditions, and remobilization.
  5. Give notice of cost and time impact. Follow the contract's notice requirements for a change or claim.
  6. Restart or close out. On restart, submit the request for adjustment. If the owner terminates, follow the termination clause.

Six weeks later the owner lifts the order. The GC's request covers remobilizing two trades, a supplier restocking fee, six weeks of extended general conditions, and a time extension. Because it documented every cost from day one, the negotiation is about amounts, not about whether the costs exist.

Common mistakes

  • Continuing work after the order. Costs incurred after receiving a stop order usually are not recoverable.
  • Not telling subs. Their costs become your costs if they keep working.
  • Missing notice deadlines. Contracts often require written notice of a claim within a set period.
  • Mixing standby costs into the job. If the costs are not separated, they are hard to prove.
  • Ignoring a regulatory order. Working through a building department stop order can lead to fines and more trouble with permits.

Related terms

Stop work orders connect to suspension of work, termination for convenience, delay claims, and extended general conditions. For documenting impacts, see how to document construction delays for claims. Smart Business Automator's change order tools help log stop work costs and route the adjustment request for approval.

Frequently asked questions

Who can issue a stop work order?

The owner or its representative under the contract, a general contractor to its subs under the subcontract, and government authorities such as building departments for permit or code violations.

How long can a federal stop work order last?

Under FAR 52.242-15, up to 90 days after delivery to the contractor, plus any extension the parties agree to. The contracting officer must then cancel it or terminate the work.

Can I get paid for time lost to a stop work order?

Often, if the stoppage is not your fault and you follow the contract's notice and claim rules. On federal work the request for an equitable adjustment is due within 30 days after the stoppage ends.

What should I do first after receiving a stop work order?

Stop the affected work, secure the site, notify subs and suppliers in writing, and start documenting the condition of the work and every related cost.

Sources

  1. Acquisition.gov: FAR 52.242-15 Stop-Work Order
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.