Mechanics liens

Minnesota mechanics lien law and deadlines

Minnesota requires a prelien notice on most smaller jobs (in the contract for prime contractors, within 45 days for subs and suppliers), a recorded lien statement within 120 days after last work, and a court action within one year.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Minnesota's mechanics lien law (Minnesota Statutes chapter 514) puts a notice duty on almost everyone working on smaller projects, including the prime contractor. Miss the prelien notice and the lien may be gone before the work is done. Once unpaid, a claimant has 120 days after its last work to record a lien statement and serve the owner, and one year to start a court action.

Minnesota mechanics lien deadlines at a glance (Minn. Stat. 514.011, 514.08, 514.12)
StepWhoDeadline
Prelien notice in contractContractor dealing directly with ownerIn the written contract; if none, within 10 days after work is agreed on
Prelien noticeSubcontractors and suppliersWithin 45 days after first furnishing labor, skill, or materials
Lien statement recorded and servedAll claimantsWithin 120 days after last work or materials
Action to enforceAll claimantsWithin 1 year after the last item in the recorded lien statement
Public bond noticeClaimants on public workWithin 120 days after last labor or materials

Who has lien rights in Minnesota

Section 514.01 gives a lien to anyone who performs engineering or land surveying services, or who contributes to improving real estate by labor, skill, material, or machinery, whether hired by the owner or by the owner's agent, contractor, or subcontractor. The covered work is broad: building, altering, repairing, or removing structures; grading, filling, excavating, and clearing; sod, trees, and landscaping; wells, drains, and sewers; and sidewalks, curbs, and paving. The statute names engineers and surveyors; it does not name architects.

The prelien notice

Section 514.011 is Minnesota's preliminary notice rule, and it reaches both tiers.

  • Prime contractors who will use subs or suppliers must include the statutory notice in the written contract with the owner, or deliver it within 10 days after the work is agreed on if there is no written contract. A contractor that fails to give it does not have a lien.
  • Subcontractors and suppliers must deliver their own notice to the owner or the owner's agent within 45 days after first furnishing, personally or by certified mail. Notice is a prerequisite to the lien, though a good-faith effort to comply preserves it unless someone proves damage caused by the failure.
  • Format: at least 10-point bold type if printed, or capital letters if typed.
  • Owner's name and address: a contractor must give a requesting sub or supplier the owner's name and address within 10 days of the request, or face liability for actual damages and fees.

There are big exemptions. No prelien notice is needed for wholly residential improvements with more than four family units. For nonagricultural, nonresidential work, no notice is needed if the project adds more than 5,000 total usable square feet, if the existing property already has more than 5,000 total usable square feet, or if the property exceeds 5,000 square feet and the work is site work with no new building or addition (grading, paving, striping). In practice, notice matters most on homes, duplexes, fourplexes, and small commercial jobs.

Recording and serving the lien statement

Under section 514.08, the lien ends 120 days after the last work or materials unless, within that window, the claimant records a lien statement with the county recorder (or the registrar of titles for registered land) and serves a copy on the owner, the owner's agent, or the person who hired the contractor, personally or by certified mail. The statement must be verified under oath and include the amount, the improvement, the parties, the dates of first and last work, a property description, the owner's name, and whether any required prelien notice was given.

Example: a siding sub finishes a $185,000 remodel on a single-family home in Rochester on August 1. It sent its prelien notice within 45 days of starting and is owed $14,800. The statement must be recorded and served by November 29. If the sub skipped the prelien notice and cannot show a good-faith effort, recording a statement may not help.

Enforcing the lien

Section 514.12, subdivision 3, requires a complaint or answer filed with the court administrator within one year after the date of the last item of the claim in the recorded lien statement. Record a notice of lis pendens at the start of the action. Under section 514.07, if the owner demands a verified itemized account within 15 days after completion, you cannot start suit until 10 days after providing it.

Lien waivers and owner withholding

Section 514.07 lets the owner hold back enough from the contractor to cover other claimants' liens and says the owner need not pay the contractor until 120 days after completion, except to the extent the contractor provides lien waivers from those who furnished work and gave prelien notice. That is why Minnesota GCs collect waivers from every noticed sub with each draw. The statute does not prescribe a waiver form, so the document's wording controls. Use a conditional lien waiver until the check clears.

Public projects use payment bonds

Public work is protected by a payment bond under Minn. Stat. 574.26, required on public contracts above the amount set in section 471.345, subdivision 3. Under 574.31, a claimant must serve notice on the surety and the contractor within 120 days after its last labor or materials, and sue within one year of that last item.

Other Minnesota guides: contractor licensing, prevailing wage, and prompt payment. Smart Business Automator's accounts receivable automation can track 45-day notice and 120-day lien dates on each job.

Frequently asked questions

How long do I have to file a mechanics lien in Minnesota?

Record the lien statement and serve the owner within 120 days after your last labor or materials. Then start a court action within one year after the last item in the statement.

Who must send a prelien notice in Minnesota?

Prime contractors who use subs or suppliers put it in the owner contract (or deliver it within 10 days if there is no written contract). Subs and suppliers deliver their own notice within 45 days after first furnishing. Larger residential and commercial projects are exempt.

Do architects have lien rights in Minnesota?

Section 514.01 names engineering and land surveying services but not architects. Check with counsel before relying on a lien for design work.

Does Minnesota have a statutory lien waiver form?

No form is prescribed in section 514.07. Waivers tie into the owner's right to withhold payment until 120 days after completion unless waivers from noticed claimants are provided.

What is the bond claim deadline on Minnesota public projects?

Serve notice on the surety and contractor within 120 days after your last labor or materials, and sue within one year.

Sources

  1. Minnesota Revisor of Statutes: 514.01, liens for labor and materials
  2. Minnesota Revisor of Statutes: 514.011, prelien notice
  3. Minnesota Revisor of Statutes: 514.07, payments withheld and lien waivers
  4. Minnesota Revisor of Statutes: 514.08, lien statement
  5. Minnesota Revisor of Statutes: 514.12, enforcement
  6. Minnesota Revisor of Statutes: 574.26, public contractor bonds
  7. Minnesota Revisor of Statutes: 574.31, bond claim notice and suit

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.