How to send a preliminary notice

Find out whether your state and role require a preliminary notice, collect the owner, contractor, and lender details at the start of the job, fill out the state's form, serve it on every required party by the deadline using a delivery method with proof, and file the proof with the job.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A preliminary notice is a short document that tells the owner (and often the general contractor and construction lender) that you are working on their project and may have lien rights. To send one, confirm your state and your role require it, gather the property and party details at the start of the job, complete the notice in the format your state requires, serve it on every required party within the deadline by a method that gives proof of delivery, and keep that proof. In some states, missing it can cost you lien rights for part or all of your work, so treat it as part of starting every job.

Who needs to send a preliminary notice

It depends on the state, your tier, and whether the job is private or public. Subcontractors and suppliers who do not contract directly with the owner are the most common senders. Names differ too: California calls it a preliminary notice, and Florida calls it a notice to owner. Two examples show how much the rules can vary.

Two state examples (private work)
RuleCaliforniaFlorida
NamePreliminary noticeNotice to owner
Who sends itClaimants before recording a lien, giving a stop payment notice, or claiming against a payment bond; laborers are exemptAll lienors under the section except laborers; aimed at those not in privity with the owner
Who receives itOwner, the direct contractor, and the construction lender if any; a party in direct contract with the owner notifies only the lenderOwner; sub-subs and suppliers to subs also serve a copy on the contractor
DeadlineNo later than 20 days after first furnishing workBefore starting, or no later than 45 days after starting, and before the owner's final payment
If lateCan still be sent, but rights reach only work done within 20 days before service and afterFailure to serve is a complete defense to enforcement of the lien
StatuteCivil Code sections 8200 and 8204Florida Statutes section 713.06

Federal jobs work differently. There is no lien on federal property, so the protection is the Miller Act payment bond. A sub-sub or supplier with a contract with a subcontractor, but not with the prime, must give written notice to the prime within 90 days after its last labor or material, by a method that provides written third-party verification of delivery, under 40 U.S.C. 3133. Check your state's rules on the mechanics lien law by state pages.

Step by step: sending a preliminary notice

  1. Decide at bid or award whether a notice is needed. Check the state, your tier, and whether the job is private, public, or federal. When in doubt, sending one costs little.
  2. Collect the job information on day one. Property address and legal description or parcel number, the owner's legal name and address, the GC's name and address, the construction lender if any, and the bonding company on bonded work. A notice of commencement, the building permit, or county property records are good sources. Ask the GC for the job information sheet.
  3. Calendar the deadline from your first day on site or first delivery. For a supplier, that is the first delivery, not the order date.
  4. Use the state's form or required content. Where the state prescribes a form or specific content, follow it exactly. Do not adapt a form from another state.
  5. Describe your work and estimated value as the form requires, for example "interior framing and drywall, estimated $185,000."
  6. Serve every required party using a delivery method the statute accepts that gives you proof of delivery. Keep receipts and tracking.
  7. File the notice and proof with the job and link it to your lien deadline calendar.
  8. Update if things change, such as a new owner, a lender added later, or work far beyond the original estimate, if your state allows or requires an amended notice.

Worked example: a drywall sub in California

As an illustration, a drywall sub starts framing on a private medical office in California on March 3. The sub contracts with the GC, not the owner, and the job has a construction loan.

  • Deadline: Civil Code section 8204 sets 20 days after first furnishing work, so the notice should go out by March 23. The sub's office sends it March 6.
  • Recipients: under section 8200, the owner, the GC (direct contractor), and the construction lender.
  • What happens if it were late: if the sub only served it on May 1, section 8204 still allows a later notice, but lien, stop payment notice, and bond rights would cover only work done within 20 days before May 1 and after. Six weeks of framing would be exposed.

Same job in Florida: the sub would serve a notice to owner before starting or within 45 days of starting, and before final payment. A sub-sub or supplier to a sub would also serve a copy on the contractor.

Running notices across many jobs

A trade contractor with 30 active jobs cannot rely on memory. Make the notice part of job setup, the same as the subcontract and the certificate of insurance. The person who opens the job in your system checks the state rule, requests the owner and lender information from the GC, and does not mark setup complete until the notice is served and the proof is filed. Suppliers can tie it to the first delivery ticket on a new job address. Review the open list weekly: any job with work started and no notice on file is a problem to fix that day, while the deadline may still be open.

Mistakes to avoid

  • Waiting for a payment problem before sending it. By then the deadline has usually passed. Send it on every job where it applies.
  • Assuming it insults the GC or owner. It is a routine statutory notice, and in California the lender is one of the parties the law says should receive it.
  • Wrong owner name. Use the legal owner from property records, not the tenant or the brand on the sign.
  • Missing the lender. In California the construction lender is a required recipient when there is one.
  • No proof of service. Without receipts, you may not be able to prove you sent it.
  • Counting from the wrong date. The clock usually starts with your first work or delivery, not your contract date.

Tools and next steps

After the notice, the next protections are lien waivers and the lien deadline itself. See how to protect lien rights as a subcontractor and when to file a mechanics lien. Related term: notice of intent to lien. Smart Business Automator stores each job's owner, GC, and lender details at setup and tracks notice and lien deadlines next to the job's billing, through subcontractor compliance automation.

Frequently asked questions

Is a preliminary notice the same as a lien?

No. A preliminary notice is an early notice that preserves the right to file a lien later. A lien is a claim recorded against the property after nonpayment. In states that require notices, you usually need the notice before you can file the lien.

Do general contractors need to send a preliminary notice?

It depends on the state. In California, a claimant in direct contract with the owner only needs to give notice to the construction lender, if there is one.

What if I missed the preliminary notice deadline?

Send it anyway if your state allows late notices. In California, a late notice still protects work done within 20 days before it was served and after. In Florida, failure to serve on time is a complete defense to the lien, so talk to an attorney about other remedies.

How do I send a preliminary notice on a federal job?

Federal property cannot be liened. Instead, a party with no contract with the prime must give written notice to the prime within 90 days after its last work or delivery to keep a Miller Act payment bond claim, using a method with third-party proof of delivery.

Sources

  1. California Civil Code section 8200, preliminary notice (public.law)
  2. California Civil Code section 8204, preliminary notice timing (statute text via FindLaw)
  3. Florida Legislature: Florida Statutes 713.06, Liens of persons not in privity
  4. Cornell LII: 40 U.S.C. 3133, Miller Act rights of persons furnishing labor or material
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.