How progress billing works in construction

Progress billing means the contractor invoices for the share of work completed each period, usually monthly, measured against an approved schedule of values, with retainage held back until the job is finished.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Progress billing is how most construction contracts get paid: instead of one invoice at the end, the contractor bills each period (almost always monthly) for the work completed since the last bill. The amount is measured against a schedule of values, reviewed by the owner or architect, reduced by retainage, and paid within a deadline set by the contract or a prompt payment law. The money then flows down to subs and suppliers, who bill the same way one tier below.

It exists because contractors cannot finance a $2 million building for a year and wait. Owners accept it because they only pay for work they can see, and they keep retainage as security.

The monthly progress billing cycle, step by step

  1. Before the first bill: get the schedule of values approved. Every later billing is measured against it. See how to build a schedule of values.
  2. Collect sub pay apps by the cutoff. A general contractor typically sets a date for subs to submit their own pay apps so they can be rolled into the owner billing.
  3. Walk the job and agree on percent complete. The PM and superintendent check each line against the field. On many jobs the owner's rep or architect walks it too, often with a "pencil draft" before the formal submission.
  4. Prepare the pay application. On AIA jobs that is the G702 and G703. Bill work in place plus approved stored materials, add approved change orders, and apply retainage.
  5. Attach the backup. Lien waivers, updated schedule, certified payroll on public work, stored material invoices, and anything else the contract lists.
  6. Owner or architect review and certification. On AIA contracts the architect certifies the amount due and may certify less than requested with an explanation.
  7. Payment, then payment down the chain. Once paid, the GC pays subs under the subcontract terms and any statute.

Ways to measure progress

Common progress billing methods
MethodHow the amount is setWhere it is common
Percent completeEach SOV line billed at its percent complete times scheduled valueCommercial lump sum work, AIA contracts
MilestoneFixed amounts when defined stages are reachedResidential, design-build, lender draw schedules
Unit priceMeasured quantities times the bid unit priceCivil, paving, utilities, DOT work
Cost plus or T&MActual costs incurred plus fee or markup, with backupService work, fast-track, owner-managed jobs

Residential remodelers often use milestone billing because homeowners understand "cabinets set" better than "62 percent on line 14." See how to set residential payment schedules for that version.

What the law says about progress payments

On federal fixed-price construction, FAR 52.232-5 has the government make progress payments monthly as the work proceeds, based on estimates of work completed and approved by the contracting officer. Each request must include an itemized breakdown by work element, the amount for each sub's work, and a signed certification that subs and suppliers have been paid from prior payments. FAR 52.232-27 then makes progress payments due 14 days after the designated billing office receives a proper payment request, with interest on late payment.

States have their own prompt payment rules, and they differ for public and private work. California's Civil Code section 8800, for example, requires a private owner to pay an undisputed progress payment within 30 days after a demand made under the contract unless the parties agreed otherwise in writing, with a penalty of 2 percent per month on amounts wrongfully withheld. Check your state on the prompt payment and retainage laws by state pages.

Worked example: three months on a $480,000 job

As an illustration, take a $480,000 tenant improvement with 10 percent retainage and no change orders yet.

Example progress billing over three months
MonthWork completed this periodTotal completed to dateRetainage held to datePayment due this month
1$60,000$60,000$6,000$54,000
2$110,000$170,000$17,000$99,000
3$95,000$265,000$26,500$85,500

After three months the contractor has earned $265,000, received or is due $238,500, and has $26,500 in retainage waiting for closeout. The payment due each month is total earned to date less retainage, minus everything certified before. Calculating it cumulatively, rather than month by month, means a correction in month two automatically carries into month three.

How progress billing works for subcontractors

Subs bill the general contractor the same way, one step earlier. The GC's cutoff is the sub's real deadline, and the sub's percent complete has to fit inside what the GC is billing the owner for that trade line. If the GC bills the owner 40 percent on drywall and the drywall sub bills 55 percent, one of them is getting cut.

Payment timing for subs depends on the subcontract and the law. On federal construction, 31 U.S.C. 3905 and FAR 52.232-27 require the prime to pay subs for satisfactory performance within 7 days after receiving payment from the government, to give written notice of any amount withheld with the reason, and to flow the same clause down to lower tiers. Private subcontracts often tie payment to the GC being paid, which is a different question. See pay-if-paid vs pay-when-paid clauses explained.

Overbilling and underbilling

Progress billing is an estimate, so it rarely matches cost exactly. Bill ahead of the work and you are overbilling: the cash is nice, but you owe the work and your WIP schedule shows a liability. Bill behind and you are underbilling, financing the owner's job with your own money. Bonding companies read both closely. Compare billed to earned on every job every month. See overbilling and underbilling explained with examples.

Mistakes to avoid

  • Missing the cutoff. On most jobs, a pay app that misses the owner's date waits a full month.
  • Billing unsigned change orders. It gets the whole application returned.
  • Percent complete that the field does not support. It erodes trust and invites line-by-line review every month after.
  • Forgetting backup. Lien waivers and certified payroll are the most common reasons a correct pay app still sits.
  • Not billing stored material. If the contract allows it and you have the documents, a switchgear delivery in month four is cash in month four.
  • Treating retainage as gone. Track it and bill the release. See how to bill retainage correctly.

Templates and tools

Use the schedule of values template and construction invoice template, and follow how to fill out AIA G702 and G703 for the forms. Smart Business Automator builds each period's pay app from the schedule of values and approved change orders, tracks retainage, and shows billed versus earned next to job cost, through construction accounts receivable automation.

Frequently asked questions

How often is progress billing done?

Usually monthly, on a cutoff date set by the contract. Some residential and small commercial jobs bill at milestones instead, and federal fixed-price jobs pay monthly or more often if the contracting officer allows.

Is progress billing the same as a progress payment?

They are two sides of one transaction. The contractor sends a progress billing (pay application), and the owner makes a progress payment once it is approved.

What happens if the owner disputes part of a pay app?

The owner or architect typically certifies the undisputed amount and explains the rest. Some state laws limit how much can be withheld for a dispute. California, for example, caps it at 150 percent of the disputed amount on private work.

Can I bill for materials not yet installed?

Often yes, as stored materials, if the contract allows it and you provide the required documentation. On federal work, off-site materials count only if the contract specifically authorizes them and the contractor shows title.

Sources

  1. Acquisition.gov: FAR 52.232-5, Payments under Fixed-Price Construction Contracts
  2. Acquisition.gov: FAR 52.232-27, Prompt Payment for Construction Contracts
  3. AIA Contract Documents: Summary of G702-1992, Application and Certificate for Payment
  4. California Civil Code section 8800, private progress payments (public.law)
  5. Cornell LII: 31 U.S.C. 3905, Payment provisions relating to construction contracts
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.