Schedule of values template

A schedule of values breaks the contract sum into billable line items so every pay application shows what was done, what was stored, and what is left. Download this template as a CSV for Excel or Google Sheets, or print it.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A schedule of values template is the spreadsheet behind every progress bill. It splits the contract into line items, gives each one a dollar value, and then tracks how much of each line is complete and stored each month. The free template below follows the same column logic as the AIA G703 continuation sheet, so it works whether the owner wants AIA forms or just a clean backup page attached to your pay application.

Get the schedule of values right at the start and billing becomes a monthly percent-complete exercise. Get it wrong and every pay app turns into a negotiation with the architect over what 40 percent of drywall really means.

What the schedule of values is for

The owner, lender, or general contractor uses the schedule to check that each bill matches the work in place. The contractor uses it to bill consistently, hold the line on retainage, and see the balance to finish on every line. Lenders on a construction draw often send an inspector who walks the site with this exact sheet in hand.

Build the lines around how the work will actually be inspected. A $480,000 tenant improvement might have 15 to 30 lines: general conditions, demolition, framing and drywall, doors and hardware, electrical, HVAC, plumbing, flooring, paint, and so on. Big lines that run for months, like drywall or electrical, are easier to approve when split by floor, area, or phase.

How to fill in each column

  • Item no.: a fixed line number. Never renumber after the first pay app, or the history stops lining up.
  • Description of work: the scope on that line, in words the owner's rep will recognize on site. Match your cost codes where you can.
  • Scheduled value: the dollar value of the line. All lines together must equal the current contract sum.
  • From previous applications: the total billed on this line in all earlier pay apps. Copy it forward from last month's total, not from memory.
  • This period: work put in place since the last application.
  • Materials presently stored: material on site or in an approved off-site location that is not yet installed. Check the contract for what proof is required to bill stored materials.
  • Total completed and stored: previous plus this period plus stored.
  • Percent complete: total completed and stored divided by scheduled value.
  • Balance to finish: scheduled value minus total completed and stored.
  • Retainage: the held amount on that line at your contract rate. The sample uses 10 percent only as an example.

Common mistakes

  1. Front-loading. Inflating early lines like mobilization or demo to pull cash forward. Reviewers spot it, and it creates overbilling that shows up later on the WIP. See front-loading.
  2. Lines too big to measure. One $300,000 electrical line invites arguments every month. Split it.
  3. Scheduled values that do not add up. Run a total check before the first submission and after every change order.
  4. Billing stored material without backup. Invoices, bills of lading, photos, and insurance on off-site storage are often required.
  5. Forgetting retainage on change order lines. Unless the contract says otherwise, retainage usually applies to them too.

Related forms and guides

For the step-by-step build, see how to build a schedule of values, and for the cover sheet that goes on top, how to fill out AIA G702 and G703. Track held money with the retainage tracking template and signed changes with the change order log template. Once billing and costs are both in, the WIP report template shows whether billing is running ahead of the work.

Smart Business Automator keeps the schedule of values tied to each project, rolls approved change orders onto it, and builds the monthly invoice from the percent complete you enter. See construction accounts receivable automation.

Schedule of values (continuation sheet)

Download CSV
Item no.Description of workScheduled valueFrom previous applicationsThis periodMaterials presently storedTotal completed and storedPercent completeBalance to finishRetainage (10%)
1General conditions36,000.0012,000.006,000.000.0018,000.0050.0%18,000.001,800.00
2Selective demolition18,500.0018,500.000.000.0018,500.00100.0%0.001,850.00
3Metal studs and drywall92,000.0023,000.0027,600.004,600.0055,200.0060.0%36,800.005,520.00
4Electrical74,000.0014,800.0022,200.000.0037,000.0050.0%37,000.003,700.00
5HVAC61,500.006,150.0012,300.009,840.0028,290.0046.0%33,210.002,829.00
6Flooring28,000.000.000.007,000.007,000.0025.0%21,000.00700.00
7CO-002 Replace rotted sill plate, east wall1,989.500.001,989.500.001,989.50100.0%0.00198.95
  • Sample data only. Replace the example lines with your own contract.
  • Total completed and stored = from previous + this period + materials presently stored.
  • Percent complete = total completed and stored divided by scheduled value. Balance to finish = scheduled value minus total completed and stored.
  • Use the retainage rate in your contract. 10 percent is shown only as an example; some contracts and states set a different rate or reduce it partway through the job.
  • Add a total row and confirm the scheduled value column equals the current contract sum before every submission.

Frequently asked questions

What is a schedule of values in construction?

It is a breakdown of the contract sum into line items with a dollar value for each. It becomes the basis for progress billing and for checking percent complete each month.

Is a schedule of values the same as the AIA G703?

The G703 is the AIA's continuation sheet that presents the schedule of values on each pay application. This template uses the same column logic, so you can use it with or without AIA forms.

How many line items should a schedule of values have?

Enough that each line can be measured on site. Small jobs may need 10 or so; larger jobs often split big trades by floor, area, or phase. The owner or lender may also set requirements.

Can I change the schedule of values after it is approved?

Usually only by agreement, and most often by adding change order lines. Moving value between lines after billing starts tends to draw questions from the owner or lender.

Can I use this schedule of values template in Excel?

Yes. Download the CSV, open it in Excel or Google Sheets, and add formulas for the total, percent complete, balance, and retainage columns.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.