What is overbilling in construction?

Overbilling is when the amount billed on a construction contract is more than the revenue earned based on percentage of completion. On the balance sheet it shows up as a liability called billings in excess of costs and estimated earnings.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Overbilling means you have billed the customer for more work than you have actually earned. It is not necessarily fraud or bad faith. It is an accounting measurement that comes from comparing billings to date with earned revenue to date on the WIP report. When billings are ahead, the job is overbilled. When they are behind, it is underbilled.

Under the percentage of completion method, earned revenue is the contract value times the percent complete. Overbilling is the difference when billings to date are higher than that number.

How to calculate overbilling

  1. Percent complete = cost to date divided by total estimated cost.
  2. Earned revenue = contract value times percent complete.
  3. Over or under billing = billings to date minus earned revenue. Positive is overbilled; negative is underbilled.
Example: overbilled job on a WIP report
LineAmount
Contract value$1,000,000
Total estimated cost$850,000
Cost to date$340,000
Percent complete40%
Earned revenue (40% of $1,000,000)$400,000
Billed to date$460,000
Overbilled$60,000

That $60,000 is cash the contractor has collected (or will) for work it has not done yet. It is recorded as a current liability, because the company owes the customer that much work.

Why overbilling happens

  • Front-loaded schedule of values. Early line items such as mobilization or general conditions are priced high, so the first pay apps bill faster than costs come in. See front-loading.
  • Deposits and stored materials. Billing for material ordered but not yet installed or not yet costed.
  • Optimistic progress. The PM bills 50 percent on a line that is really 35 percent done.
  • Estimate problems. If the estimated total cost is too low, percent complete looks high and the overbilling looks smaller than it is. Fix the cost to complete first.

Why it matters

A moderate overbilling position is often seen as healthy cash management, since the customer's money is funding the work. Sureties and lenders watch it closely, though. The danger is spending the overbilled cash on overhead, equipment, or another job's losses. When the job reaches the end, the remaining work still has to be paid for and there is no billing left to cover it. That is how a company that looked cash rich ends up short on its last three jobs at once.

Common mistakes

  1. Treating overbilled cash as profit and distributing it.
  2. Ignoring overbilling on a job whose estimate is out of date, which hides a loss.
  3. Netting overbilled and underbilled jobs into one number so neither problem is visible.
  4. Not reviewing the WIP monthly. Overbilling changes every billing cycle.

A quick gut check helps. If a job is overbilled, ask whether the cash it produced is still in the bank. Add up overbillings across all open jobs and compare that total with cash on hand. If cash is lower, the company has already spent money it will need to finish work, and the shortfall will show up later as a cash crunch on jobs that look fine on paper.

Related terms

Overbilling is half of the over/under analysis with underbilling. It depends on accurate estimate at completion numbers and ties to bond capacity and working capital. For worked examples, see overbilling and underbilling explained. Smart Business Automator shows over and under billings by job in its WIP views. See job costing and WIP automation.

Frequently asked questions

Is overbilling illegal?

No. In accounting terms it only means billings are ahead of earned revenue. Billing for work that was not performed in violation of the contract is a different issue.

Where does overbilling show on financial statements?

As a current liability, usually labeled billings in excess of costs and estimated earnings.

Is overbilling good or bad?

Some overbilling can help cash flow. Large or growing overbillings, especially if the cash has been spent, can signal trouble when the job winds down.

How do I fix an overbilled job?

Make sure the cost estimate is current, bill only for real progress going forward, and keep enough cash on hand to finish the work you have already been paid for.