What is the percentage of completion method in construction?

The percentage of completion method recognizes revenue and profit on a construction contract as the work progresses, usually by comparing costs incurred to date with total estimated costs, instead of waiting until the job is finished.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

The percentage of completion method (POC) spreads a contract's revenue and profit across the periods when the work actually happens. If a job is 40 percent done at year end, 40 percent of the contract's revenue is recognized that year. That gives a much more accurate picture of a contractor's performance than recognizing everything at the end, which is what the completed contract method does.

POC is the basis of the WIP report and the over/under billing numbers that lenders and sureties study.

How the cost-to-cost method works

The most common way to measure progress is cost-to-cost: percent complete equals costs incurred to date divided by total estimated costs. Federal tax law uses the same idea. Under 26 U.S.C. 460, income from a long-term contract is generally determined under the percentage of completion method, with completion measured by comparing costs allocated to the contract and incurred before the end of the tax year with estimated total contract costs.

A worked example across two years

Say a GC signs a $1,000,000 contract with an estimated cost of $900,000 (expected gross profit $100,000). Year one costs are $360,000. In year two, after more costs come in, the GC revises the total estimated cost to $950,000 and cumulative costs reach $760,000.

Example: revenue and profit under POC
ItemYear 1Year 2 (cumulative)
Total estimated cost$900,000$950,000
Cost to date$360,000$760,000
Percent complete40%80%
Revenue earned to date$400,000$800,000
Gross profit to date$40,000$40,000
Gross profit recognized this year$40,000$0

The cost increase in year two wiped out all new profit for the year. Expected gross profit on the whole job fell from $100,000 to $50,000. POC shows that fade right away, which is the point. If the revised estimate showed an overall loss, standard accounting practice is to recognize the whole expected loss at once.

Tax rules and the small contractor exception

For taxes, section 460(e) exempts certain construction contracts from the required POC method. Home construction contracts are one category. Other construction contracts qualify if the contractor estimates when signing that the contract will be completed within two years and the contractor meets the gross receipts test in 26 U.S.C. 448(c). That test starts from a $25,000,000 average annual gross receipts figure over the prior three tax years and is adjusted for inflation each year. Ask your CPA for the current figure and which method fits your company.

Common mistakes

  1. Stale estimates. POC is only as good as the cost-to-complete. An old estimate makes percent complete wrong.
  2. Counting uninstalled material as progress. Material sitting in the yard raises cost to date without real progress.
  3. Mixing billing percent with cost percent. What you billed is not what you earned.
  4. Waiting until year end to update estimates, which turns a slow fade into a sudden write-down.

Owners and bankers also read POC numbers as a sign of how well a company estimates. A contractor whose projected margins drop at year end on job after job looks like it does not know its costs. One that revises estimates monthly and shows small, explained changes looks like it has control.

Related terms

POC ties into revenue recognition, overbilling, underbilling, cost to complete, and earned value. For the comparison, see percentage of completion vs. completed contract accounting. Smart Business Automator calculates percent complete and over/under billing by job in its WIP views. See job costing and WIP automation.

Frequently asked questions

What is the difference between percentage of completion and completed contract?

POC recognizes revenue as work progresses. Completed contract waits until the job is substantially finished to recognize revenue and profit.

Is percentage of completion required for taxes?

Long-term contracts generally use it under 26 U.S.C. 460, but section 460(e) exempts home construction contracts and some smaller contractors whose contracts are expected to finish within two years and who meet the section 448(c) gross receipts test.

What is cost-to-cost?

A way to measure percent complete by dividing costs incurred to date by total estimated costs.

Can percent complete be based on something other than cost?

Yes. Some contractors use units installed, labor hours, or engineering estimates. Cost-to-cost is the most common because the data already exists in job cost reports.

Sources

  1. Cornell LII: 26 U.S.C. 460, Special rules for long-term contracts
  2. Cornell LII: 26 U.S.C. 448, Limitation on use of cash method (gross receipts test)
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.