What is a WIP report in construction?

A WIP (work in progress) report is a schedule of every open job that shows contract value, estimated cost, cost to date, percent complete, earned revenue, billings, and the resulting over or underbilling and projected profit.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

The WIP report is the single most important financial report in a contracting business. A profit and loss statement tells you what happened last month across the company. The WIP tells you, job by job, whether each project is on track to make the money it was bid to make, and whether billing is ahead of or behind the work. Sureties, banks, and CPAs all ask for it.

It is built on the percentage of completion method: costs to date divided by total estimated costs drives the percent complete for each job.

What is on a WIP report

Sample WIP schedule, end of quarter (example)
JobContractEst. total costCost to date% completeEarnedBilledOver (under)
Retail shell$1,800,000$1,530,000$918,00060%$1,080,000$1,150,000$70,000
Clinic TI$640,000$560,000$336,00060%$384,000$352,000($32,000)
Warehouse addition$2,400,000$2,232,000$446,40020%$480,000$500,000$20,000

Read across each line. The retail shell job is overbilled by $70,000, which is cash in the bank that has not yet been earned. The clinic is underbilled by $32,000, which needs an explanation. The warehouse addition is only projecting $168,000 of gross profit on $2.4 million, a 7 percent margin. If that job was bid at 12 percent, the margin has already faded.

Notice too that the totals tell a different story than any single job. Across all three, the company is net overbilled by $58,000. That money is sitting in the operating account, and it belongs to work not yet done. An owner who reads only the bank balance might think the business is doing better than it is.

How to read it like a surety

  • Margin fade: compare projected gross margin this period with last period and with the bid. Falling margin on the same job is the top warning sign.
  • Underbillings: large or growing ones may hide cost overruns. See underbilling.
  • Overbillings: healthy in moderation, but they are a liability. Spending them on overhead creates a cash hole later. See overbilling.
  • Estimate quality: if estimated total costs never change month to month, nobody is updating them.
  • Backlog: the unearned contract balance across jobs shows future work. See backlog.

Common WIP mistakes

  1. Not updating the estimate at completion each month, so percent complete is fiction.
  2. Including unapproved change orders in contract value without a consistent policy.
  3. Leaving committed but unbilled costs out of the cost picture. See committed cost.
  4. Running WIP only at year end for the CPA instead of monthly for management.
  5. Letting the accountant build it alone. PMs know the cost to complete; the WIP needs their input.

Related terms

The WIP draws from job costing, cost to complete, and progress billing. Start from the WIP report template and the guide how to read a construction WIP report. Smart Business Automator builds the WIP from live job cost and billing data instead of a month-end spreadsheet; see job costing and WIP automation.

Frequently asked questions

What does WIP stand for in construction?

Work in progress. The WIP report covers all contracts that are started but not finished.

How often should a WIP report be prepared?

Monthly for management is the common standard. Sureties and banks often require it quarterly or with year-end financial statements.

Who prepares the WIP report?

Usually the controller or accountant, using cost to complete estimates from project managers. Both are needed for the report to be accurate.

Why do bonding companies want a WIP report?

It shows whether jobs are making their expected margins, whether billing is ahead of or behind the work, and how much backlog remains, which drives how much bonding capacity a contractor gets.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.