What is estimate at completion in construction?

Estimate at completion (EAC) is the forecast of what a job will have cost in total when it is done: cost spent so far plus the cost still needed to finish.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

Estimate at completion (EAC) is the projected final cost of a project or cost line. The most practical way to get it is simple addition: actual cost to date plus a bottom-up cost to complete. Compare EAC to the revised budget and you know whether the job is heading over or under. Compare it to the contract value and you know the expected gross profit.

EAC drives the percentage of completion method: percent complete equals cost to date divided by EAC. That makes it the hinge of every WIP report.

Three ways to calculate EAC

Common EAC methods
MethodFormulaBest used when
Bottom-upActual cost plus a new cost to completeMost construction jobs; the PM re-forecasts each line
Performance-basedBudget at completion divided by CPIWork is repetitive and past efficiency is a fair guide
Budget-basedActual cost plus remaining budgetEarly in a job, or for lines with no variance yet

The budget-based method is the most common and the most dangerous, because it assumes the rest of the job will go exactly to plan. Use it only where that assumption is defensible, such as a sub line that is fully bought out with no open issues.

How EAC works on a real job

A general contractor is halfway through a $3.4 million restaurant build-out with a $3.06 million cost budget. Here is the month-end review on three lines:

Example: EAC on selected cost lines
LineBudgetCost to dateCost to completeEACVariance
Site concrete$180,000$171,000$22,000$193,000$13,000 over
Kitchen equipment (sub)$410,000$205,000$205,000$410,000On budget
General conditions$240,000$132,000$138,000$270,000$30,000 over

General conditions is running over because the job is three weeks late, and every extra week of supervision, trailer, and dumpsters adds cost. That $30,000 is real money, and it belongs in the EAC now, even if the GC hopes to recover it with a change order later. A pending recovery goes on the revenue side only when it is probable, not on the cost side as a credit.

Common EAC mistakes

  1. Holding EAC at budget until the job is over, then taking the whole fade in one month.
  2. Netting expected change order revenue against cost. Keep cost and revenue separate.
  3. Ignoring open commitments. A sub with $80,000 left on its contract and a pending $12,000 claim is a $92,000 cost to complete, not $80,000.
  4. One person forecasting every job. Have each PM own their EAC and walk through it in a monthly review.

Related terms

EAC pairs with earned value, budget variance, committed cost, overbilling, and underbilling. Smart Business Automator's job costing and WIP views show EAC by line and how it changed since last month.

Frequently asked questions

What is the difference between EAC and ETC?

ETC (estimate to complete) is the cost still to be spent. EAC is the total: actual cost to date plus ETC. In construction, ETC is usually called cost to complete.

How often should EAC be updated?

At least monthly at WIP close. Jobs with problems deserve a weekly look.

Can EAC go down?

Yes. If a buyout comes in under budget or a contingency is not needed, EAC drops and projected profit rises. Be as honest about good news as bad.

What is VAC?

Variance at completion: budget at completion minus EAC. A negative VAC means the job is forecast over budget.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.