Job costing and finance

Percentage of completion vs completed contract accounting

Percentage of completion recognizes a job's revenue and profit as the work progresses. Completed contract waits until the job is finished. For federal taxes, long-term contracts generally must use percentage of completion unless an exception, such as the small contractor or home construction exception, applies.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

The percentage of completion method records revenue and profit on a job a little at a time, in proportion to how much of the work is done, usually measured by cost to date divided by estimated total cost. The completed contract method records nothing until the job is finished, then books all the revenue and profit at once. Percentage of completion gives a truer picture of how the business is performing each month, which is why banks and sureties expect it. Completed contract can defer taxable income, which is why some smaller contractors prefer it for tax purposes. Federal tax law limits who can use completed contract, so the choice depends on contract length, company size, and the type of work.

How each method works

Percentage of completion

  1. Estimate total contract cost and keep it updated.
  2. Each period, divide cost to date by estimated total cost to get percent complete.
  3. Multiply contract value by percent complete to get earned revenue to date.
  4. Subtract revenue recognized in prior periods to get this period's revenue.
  5. Compare earned revenue with billings and record the overbilling or underbilling.

If the estimate shows a loss on the whole contract, ask your CPA how and when to recognize it. Waiting until the job closes usually hides the problem from everyone, including you.

Completed contract

Costs and billings accumulate on the balance sheet while the job is open. When the contract is complete, all the revenue and all the costs move to the income statement in that period. Nothing about the job appears as profit before then.

Worked example: the same job, two methods

Say a contractor signs a $900,000 contract in July with an estimated cost of $765,000 and $135,000 of expected profit. By December 31, it has spent $459,000. The job finishes in May of the next year at the estimated cost. The figures are illustrative.

Example: income recognized by year
LinePercentage of completionCompleted contract
Percent complete at Dec. 31 (459,000 / 765,000)60%Not used
Year 1 revenue$540,000$0
Year 1 gross profit$81,000$0
Year 2 revenue$360,000$900,000
Year 2 gross profit$54,000$135,000
Total gross profit$135,000$135,000

Total profit is identical. Timing is what changes. Under percentage of completion, the year 1 financial statements show that the company did real work and earned $81,000 on it. Under completed contract, year 1 shows $459,000 of cost sitting on the balance sheet and no profit at all, which can make a growing contractor look weak to a lender while deferring the tax on that $81,000 to the following year.

Which method can you use for taxes?

Under Internal Revenue Code section 460, taxable income from a long-term contract (one for building, installing, or constructing property that is not completed in the tax year it is entered into) is generally computed using the percentage of completion method, with completion measured by comparing costs incurred against estimated total contract costs. When the contract is finished, the taxpayer may also owe or receive look-back interest that recalculates the earlier years using actual figures.

Section 460(e) carves out two main exceptions for construction:

  • Home construction contracts: contracts where 80 percent or more of the estimated total contract costs relate to dwelling units in buildings with four or fewer units, plus improvements directly related to them.
  • Small construction contracts: contracts the contractor expects to complete within two years of the contract commencement date, if the contractor meets the gross receipts test of section 448(c) for the year the contract is entered into.

The section 448(c) test looks at average annual gross receipts over the prior three tax years. The statute sets the base amount at $25 million and adjusts it for inflation each year, rounded to the nearest million, so check the current figure with the IRS or your CPA. Contractors that qualify for an exception can often use completed contract or another permitted method for those contracts. Rules for tax shelters, related entities, and method changes add detail, and changing methods usually requires IRS consent, so this is a decision to make with a tax advisor.

Book accounting versus tax accounting

Many contractors keep their books one way and file taxes another. A company might prepare financial statements for its bank and surety under GAAP, which your CPA applies to your contracts, while using completed contract on its tax return for jobs that qualify for an exception. That is common and legitimate, but it means the WIP schedule, the financial statements, and the tax return will show different revenue for the same year. Keep a reconciliation so nobody is surprised.

Also keep completed contract separate from cash basis in your head. Cash basis records income when payment arrives and expenses when they are paid. Completed contract is an accrual method that holds a contract's revenue and costs on the balance sheet until the job is done. A contractor can be on the accrual method overall and still use completed contract for qualifying jobs, or use cash basis for small service work. Your tax advisor sets the combination; the operations team just needs clean job costs and billings so any method can be calculated.

Side-by-side comparison
FactorPercentage of completionCompleted contract
When profit is recognizedAs work progressesWhen the contract is complete
Depends on cost forecastsYes, heavilyMostly at completion
Smooths income across yearsYesNo, income can be lumpy
What banks and sureties preferUsually this methodLess informative
Can defer taxNoYes, where allowed
Who can use it for taxEveryoneContracts meeting a section 460(e) exception

Mistakes to avoid

  1. Running percentage of completion on stale cost estimates. The method is only as good as the cost to complete.
  2. Assuming the small contractor exception applies forever. Growth past the gross receipts threshold changes the rules for new contracts.
  3. Using completed contract on the books when a surety wants to see current performance.
  4. Ignoring a known loss on a job until it closes.
  5. Switching methods without the required IRS process.

Templates and related reading

The WIP report template runs the percentage of completion math for every open job. See also how to read a construction WIP report, overbilling and underbilling explained with examples, and construction accounting basics for small contractors. Related terms: revenue recognition, accrual accounting, and cash basis accounting.

Smart Business Automator calculates percent complete, earned revenue, and over and under billing from live job costs, which gives your CPA clean WIP data whichever tax method you file under. See job costing and WIP automation.

Frequently asked questions

Can any contractor use the completed contract method?

Not for federal taxes. Long-term contracts generally must use percentage of completion under section 460 unless an exception applies, such as home construction contracts or small construction contracts that meet the two-year and gross receipts tests.

What is the gross receipts limit for the small contractor exception?

The statute uses the section 448(c) test: average annual gross receipts for the prior three years at or below $25 million, adjusted for inflation each year. Check the current year's figure with the IRS or your CPA.

Why do sureties prefer percentage of completion?

It shows earned profit and over or under billing on open jobs as they progress, so underwriters can see whether jobs are performing before they close.

Is percentage of completion the same as progress billing?

No. Progress billing is how you invoice the customer. Percentage of completion is how you recognize revenue. The difference between the two is the over or under billing.

What is the look-back method?

When a long-term contract taxed under percentage of completion is finished, section 460 requires recalculating prior years' income using actual costs and contract price, with interest paid or received on the difference. Contracts that qualify for a section 460(e) exception fall outside those rules. Ask a tax advisor how it applies to you.

Sources

  1. Legal Information Institute (Cornell Law School): 26 U.S. Code section 460, Special rules for long-term contracts
  2. Legal Information Institute (Cornell Law School): 26 U.S. Code section 448, Limitation on use of cash method of accounting
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment