What construction financial statements do bonding companies want?
Bonding companies want year-end financial statements prepared by a CPA who knows construction, at the level of assurance your bond program requires, with full notes and supporting schedules: contracts in progress (WIP), completed contracts, contract revenue, and general and administrative expenses. Sureties also look at mid-year numbers.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.
Bonding companies want a complete set of CPA-prepared year-end statements (balance sheet, income statement, statement of retained earnings, and cash flow statement), the notes and disclosures that go with them, and construction-specific schedules, chiefly a schedule of contracts in progress (the WIP schedule) and a schedule of completed contracts. A Construction Executive article on surety underwriting also lists a schedule of contract revenue and a schedule of general and administrative expenses, and says sureties analyze both mid-year and year-end balance sheets. The level of CPA work (compilation, review, or audit) depends on the size of the bond program you want.
The statements are how a surety decides whether to back you and for how much. Weak or late statements cap your bonding capacity no matter how good your field work is.
Compilation, review, or audit: which level you need
CPA engagement levels, as described by Old Republic Surety
Level
What the CPA does
How sureties tend to view it
Compilation
Puts your numbers in financial statement form; no assurance on accuracy
Little weight, similar to internal statements or tax returns
Review
Inquiries and analytical procedures; limited assurance
With full notes and schedules from a construction CPA, may cover many mid-sized contractors
Audit
Tests evidence, confirms with third parties; reasonable assurance
Highest confidence; more often needed for complex companies, larger jobs, and large backlogs
Old Republic Surety's article gives no dollar thresholds. It says the decision depends on job sizes, how many open jobs you carry, organizational complexity, growth plans, revenue, and aggregate backlog. EisnerAmper's guide adds that audited or reviewed statements are an important tool for obtaining higher bonding limits. Ask your surety agent before you engage the CPA, not after.
What the package should include
The four core statements
Balance sheet, income statement, statement of retained earnings, and statement of cash flows, prepared under GAAP with notes. The notes explain revenue recognition, contract receivables and retainage, debt, leases, related-party transactions, and anything else that affects risk.
Schedule of contracts in progress (WIP)
For every open job: contract value with approved change orders, estimated total cost, cost to date, estimated cost to complete, percent complete, revenue earned, billed to date, and the over or under billing. EisnerAmper calls cost to complete "the foundation of the entire WIP schedule" and recommends tying the WIP to job costing so the two never diverge. See how to read a construction WIP report.
Schedule of completed contracts
Jobs finished during the year, with final contract value, final cost, and gross profit. Underwriters compare final margins with what the prior year's WIP projected. If jobs finished well below projections, that margin fade undermines trust in the current WIP.
Contract revenue and G&A schedules
Revenue broken out by contract or type of work, and a detailed schedule of general and administrative expenses. Old Republic Surety also lists schedules of cash flow and a debt breakout among the items a reviewed statement should include.
Interim statements
The Construction Executive article notes that sureties analyze mid-year balance sheets as well as year-end ones. Interim statements are often prepared internally, so ask your surety what it expects. Whatever the format, prepare them on the same basis as year-end, with a current WIP, so the numbers compare.
How to prepare your statements for the surety, step by step
Ask your surety agent what level and schedules your program requires, and when they want the package after year end.
Hire a CPA with construction experience. The Old Republic article stresses a CPA experienced in construction accounting.
Close every month during the year so year-end is not a reconstruction project.
Update cost to complete on every job at year end with the PMs, not from budget minus spent.
Reconcile the WIP to the general ledger before the CPA starts fieldwork.
Clean up the balance sheet: collect or write off old receivables, document related-party balances, and confirm retainage by job.
Review the draft with your agent before it goes to the underwriter, so surprises get explained up front.
Worked example: a WIP schedule a surety would read
Say a general contractor has three open jobs at year end. Figures are illustrative.
Example schedule of contracts in progress
Job
Contract
Est. total cost
Cost to date
% complete
Earned
Billed
Over (under)
Medical office
$2,400,000
$2,112,000
$1,267,200
60%
$1,440,000
$1,500,000
$60,000
Retail fit-out
$850,000
$765,000
$612,000
80%
$680,000
$640,000
($40,000)
School addition
$1,600,000
$1,408,000
$352,000
25%
$400,000
$430,000
$30,000
An underwriter will notice that the retail fit-out is 80 percent complete and underbilled by $40,000. That raises a question: is the work unbilled because of a pending change order, or is the job losing money and costs are running ahead of what can be billed? EisnerAmper flags underbillings as a red flag for exactly this reason. Answer it before the underwriter asks, with a note explaining the change order and its status.
What underwriters check first
Underwriters do not read the package front to back. EisnerAmper's guide says sureties often check working capital before they open the WIP schedule, and the Construction Executive article lists the ratios many look at: working capital against revenue, debt to equity, underbillings against working capital, backlog against a year of revenue, and fade on completed jobs. Run those numbers yourself before the package goes out. If one of them looks weak, say why in the cover letter: a one-time equipment purchase, a loss job that has since closed, a large change order still being negotiated. An explained number gets a conversation. An unexplained one gets a lower limit.
Underwriters also compare this year's package with last year's. Consistent formats, the same CPA, and the same accounting methods make that comparison easy and the trend easy to trust. Changing all three in one year forces the underwriter to start over.
Mistakes that hurt you with a surety
A WIP that does not tie to the income statement.
Cost to complete based on budget minus spent, which hides losses until the job closes.
Large year-end distributions that drain working capital just before the statement date.
Unexplained related-party receivables or loans to owners.
Switching CPAs or accounting methods every year, which makes trends hard to read.
Smart Business Automator keeps job costs, change orders, and billing on each project and shows them in job costing and WIP views, so the schedule your CPA and surety need comes from data that already ties out. See job costing and WIP automation.
Frequently asked questions
Do bonding companies accept tax returns instead of financial statements?+
For very small bonds, some sureties may. For an ongoing bond program, sureties generally want GAAP financial statements with a WIP schedule, because tax returns do not show earned revenue, over and under billings, or projected profit on open jobs.
What is the difference between a reviewed and an audited statement?+
A review gives limited assurance based mainly on inquiries and analytical procedures. An audit gives reasonable assurance and includes testing evidence, such as confirming balances with third parties. Audits cost more and are more often required for larger programs.
What is a schedule of contracts in progress?+
It is the WIP schedule: a list of every open job with contract value, estimated cost, cost to date, percent complete, revenue earned, billings, and over or under billing. It is one of the first schedules a surety reads.
How soon after year end do sureties want statements?+
It varies by surety and program. Ask your surety agent for the deadline when you set up the program, and plan your year-end close and CPA schedule around it.
Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.
Related listening · Scaling Legends
The Megaproject Blueprint 2026: What Turner Construction's 10 Straight $1 Billion Wins Teach Every Contractor About Competing for the Biggest Contracts in America
Turner Construction has won 10 projects valued at $1 billion or more in the first five months of 2026 - more megaprojects than it captured in all of 2025. This episode dissects what separates megaproject winners from the field: team structure, prequalification positioning, bonding capacity, JV strategy, specialty subcontract pathways, and how small and mid-size contractors can win work on programs that industry giants are capturing.
Starts muted when the player comes into view.
Read the full episode transcript
Published transcript from Scaling Legends. It may contain transcription errors. View the source transcript.
Disclaimer, this podcast is for informational and educational purposes only, and is not legal, financial, or professional advice. We're accepting beta testers for new Smart Business Automator features. Sign up at smartbusinessautomator .com. Beta testers get first access to new features and updates before public rollout. Welcome to today's deep dive, everyone. Really excited for this one. Yeah, it's a huge topic. So I want you to imagine putting together a jigsaw puzzle. But this puzzle has 10 ,000 pieces. Oh, and those pieces are currently scattered across like three different continents. Right, exactly. And if you happen to snap just one of them into the wrong place, it costs your company $50 million. Yeah, it's a completely unyielding environment. Which is the reality of a modern construction
megaproject. Exact blueprint to scale a construction firm to billion dollar project wins. The big leagues. The absolute biggest. We're looking at how the largest players dominate. And more importantly, the specific roadmap a midsize firm has to execute to get a seat at that table. Because it's. It's a highly capital -intensive ecosystem. It literally operates on a completely different set of physical and financial laws than your standard commercial real estate. Exactly. And to understand the gravity here, we have to look at the staggering concentration of capital happening right now. Like, I read this stat and my jaw dropped. Oh, the Turner stat. Yes. As of this month, May 2026, Turner Construction, who, by
the way, is already the industry's largest contractor, by revenue. They have won 10 different projects valued at a billion dollars or more. It's wild. In just the first five months of the year. 10 billion dollar projects. That is more than they won in all of 2025 combined. It's an unprecedented run, honestly. And, you know, to ground those numbers for everyone listening, just look at one of those Turner projects, the IAD06 data center in Frederick, Maryland. Oh, right. That one just topped out at steel structure in March, right? And when you actually examine a site like IAD06, you realize pretty quickly that you are not just building a structure. It is essentially a mission -critical fortress. Like beyond normal building specs. Way beyond. You're integrating dedicated power substations, industrial -scale liquid cooling infrastructure, and security perimeters
that honestly rival defense installations. So Turner securing 10 of these programs in five months. It tells something really crucial about where this market is heading. Which raises an immediate question for me. I mean, we all know these projects are incredibly complex. Right. But knowing that doesn't really explain the current monopoly. Like, even if it's hard, why are only the top three or four firms winning all of them? Why aren't highly capable midsize firms scaling up to meet the demand? Well, it fundamentally comes down to risk absorption. It's not just about technical capability anymore. OK, unpack that a bit. So the market is aggressively bifurcating. And it's because owners are changing how they distribute risk. When a major tech company or a developer is throwing $3 billion at a semiconductor
plant. Their main concern isn't finding the lowest bidder. Exactly. They don't care about a flight discount. Their singular focus is certainty of execution. I mean, I have to push back on that a little bit, though, on behalf of anyone listening. Sure. Do these massive firms really guarantee certainty? We've all seen corporate behemoths get bogged down in, you know, endless red tape and bureaucracy. That's true, yeah. So wouldn't a private owner prefer a highly agile midsize firm, one that can pivot quickly, make fast decisions and not get paralyzed by corporate overhead? In a conventional build, absolutely. Agility is a huge selling point there. But on a mega project, financial risk absorption always trumps operational agility. Because the numbers are just too big. Right. The owner needs a general
contractor with a balance sheet vast enough to absorb a catastrophic supply chain failure without going bankrupt. Oh, I see. Think about it. If a critical piece of switchgear is delayed by eight months, the holding costs alone could bankrupt a midsize firm. Wow. Yeah, that makes sense. But giants like Turner. They have the capital reserves, the global procurement leverage, the sheer financial mass to guarantee it crosses the finish line, no matter what macroeconomic shocks hit. So the owners just push all the liability onto the mega price. Exactly. The big gets exponentially bigger and the mid -sized firms are left competing for the standard. you know, commercial work. So for you listening, that makes the barrier to entry pretty clear. If you're a midsize contractor, you can't just show up on bid day with a sharp pencil and a glossy proposal. Not a chance. You
have to prove you belong in the room by passing the prequalification wall. And from what I understand, that wall is practically a fortress. Oh, it's intentionally designed to be almost insurmountable. It's this rigorous multi -year auditing process just to get on the approved bidder list. Because they're using financial requirements as a brutal filter. Yes. First, you have the portfolio requirements, proving you actually delivered similar complexity. But then you face the bonding capacity threshold. Which is where most firms fail, right? Oh, absolutely. So let's actually dive into the mechanics of that bonding capacity. Because, you know, it's not just calling your insurance broker and asking for a larger policy. I wish it were that easy. Right. How does a surety company actually underwrite a contractor for a billion -dollar bond? It is
a deeply invasive financial colonoscopy. Yikes. Seriously. A surety bond is a guarantee to the client that the contractor will finish the job. If the contractor defaults, the surety company is on the hook to pay for the completion. Millions of dollars on the line. Hundreds of millions. So they aren't just looking at your credit score. They are forensically analyzing your working capital, your debt -to -equity ratios. And your WIP schedule, right? Yes, exactly. Your work -in -progress schedule is the holy grail. What are they looking for in that specifically? Cash flow management across all your current projects. They look at overbillings versus underbillings. Like if a midsize contractor is consistently underbilled on their current jobs. That means they're financing the construction out of their
own pocket. Exactly. Instead of staying ahead of the client's cash. And to a surety company, that demonstrates really poor cash flow management. Right. If you can't manage cash tightly on a $50 million job, they're definitely not trusting you with a billion dollar job. Never. Moving from a 50 million limit to a 200 million limit requires an entirely different tier of corporate financial governance. And even if your financials are spotless, there's another metric that acts as an absolute deal breaker, isn't there? Yes, the EMR. Right, the experience modification rate. For those who don't know, this is the metric insurance companies use to calculate your workers' comp premiums based on your safety record. And the industry baseline for that is exactly 1 .0. And it's vital to explain how that's calculated because it's not just a snapshot of today. It's
a trailing three -year average, correct? Spot on. It compares your actual claims against your total payroll over a rolling three -year period compared to other companies in your trade. So if your EMR is 1 .2, you're 20 % worse than average. Right. And if it's 0 .8, you're 20 % better. On a mega project, an EMR above 1 .0 is an instant disqualification. Because one accident on a job that size just carries way too much liability. Precisely. Think about the daily operational friction you need to maintain that score. If a worker trips on an improperly secured scaffold in 2023 and files a legitimate claim... That goes to the state rating bureau. Yep. It gets factored into your formula. Yeah. And that single lapse in safety in 2023 will actively prevent
you from bidding on a billion -dollar data center in 2026. The mega primes will just auto -reject your prequalification packet. Instantly. Okay, so you need flawless cash flow management, an immaculate three -year safety history to keep the EMR down, and a massive portfolio, which brings up a glaring paradox. The experience loop. Right. If you need mega project experience to get pre -qualified for a mega project, how does a mid -sized firm ever secure their first one? It's like you need experience to get the job, but you need the job to get experience. That is the core strategic challenge. And the reality is mid -sized firms almost never break in through the front door as the prime contractor. So they use side doors. Exactly. Systemic entry points. Right. And one of the most critical mechanisms is through federal set -aside pathways. Okay. How do those actually function on the ground?
Because, you know, a lot of contractors hear federal program and just assume it means endless paperwork without real opportunity. It's actually the exact opposite. It's a legally mandated wedge that forces the door open. Oh, really? Yeah. The federal government funds a vast portion of these mega projects, and they legally require that a specific percentage of the total contract value must go to designated business categories. Like the SDVOSB. Right. The Service Disabled Veteran -Owned Small Business Program or the 888 Business Development Program for Disadvantaged Businesses. So the mechanism here is that a giant like Turner literally cannot win the contract unless they partner with these smaller firms. Exactly. It artificially bridges that financial gap. A midsize firm with an SDVOSB designation
might not have the bonding capacity for the whole job. But the mega prime needs their designation to satisfy the mandate. So they bring them in. There's also the formal mentor -protege program where the government incentivizes a mega prime to actively train a smaller firm. Basically letting the smaller firm borrow the mega prime's balance sheet just to get on site and build their resume. Exactly. Okay, but what if your firm doesn't qualify for one of those set -asides? Like, you're just a standard mid -sized commercial contractor. What's your side door? Then you take the specialty subcontractor path. You don't try to manage the whole ecosystem. You just carve out a highly complex, but narrowly defined piece of the pie. Like positioning a unique capability. Right. Like pouring hundreds of thousands of yards of continuous concrete or erecting heavy structural
steel or executing the complete MEP package. Mechanical, electrical, and plumbing. Exactly. or custom curtain wall systems. So instead of trying to carry a billion -dollar bond, you just take down a $40 million mechanical scope. Right. You execute that specific package flawlessly as a sub to the Megaprime. By doing that, you officially have a piece of a megaproject on your resume. Proving to your surety company you can handle the logistics of a site with 2 ,000 workers. And proving your safety culture can maintain that sub -1 .0 EMR under intense pressure. But eventually, even that specialty path hits a ceiling, right? Because as these projects scale up, those specialty packages get massive, too. They do. If a data center needs a $200 million concrete package, your midsize firm probably doesn't have
the bonding capacity for that item. And that is the exact threshold where firms have to pivot to a joint venture strategy, a JV. When you want to step up in weight class. Yes. You find a mega project capable firm or another highly capable midsize firm and you form a JV. I think people often misunderstand what a JV actually is. It's less like joining a band to play a bigger gig and more like two people co -signing a massive commercial mortgage. That's a perfect analogy. One person brings the flawless credit score and the cash that's your out -of -state mega prime. The other brings the local real estate license and knows the zoning board that's your local midsize firm. Right. And the bank... or in this case the owner, requires both elements to underwrite the risk. But JD is not just a handshake. It's
a completely new, legally binding entity. Usually an LLC, created exclusively for that single project. And you have to negotiate the split of profits, capital contributions, equipment. It might be a 70 -30 split or 60 -40. And what about liability? Because co -signing is terrifying. Oh, that's the crucial mechanism. Joint and several liability. Meaning what exactly? Meaning if the 30 % partner defaults or goes bankrupt halfway through the build, the 70 % partner is legally obligated to finish 100 % of the project. They absorb all the excess costs. Everything. That's why forming a JV is so rigorous. The larger partner is going to deeply audit your financials, your safety culture, your leadership team before they assign anything. Which means you can't just scramble
to find a JV partner the week a massive project makes the local news. Not a chance. By the time it's in a business journal, the mega primes already have their JV agreements signed and their pre -qualification lists for subs are locked. And this is exactly why utilizing a tool like Smart Business Automator is non -negotiable for this strategy. According to their market intelligence report, tracking pre -qualification announcements is literally the key. It's the only way to know when and where to position yourself for those JV or specialty sub -roles. Right. Before the broader market even knows the project exists. It's like being the best bass player in the world. You might not headline the stadium tour alone, but if you join a supergroup JV or get hired as the session musician, suddenly you're playing the arena. I love that. And you need that data
early because the most counterintuitive reality of this market is the timeline. The client relationship timeline. Right. The decisions that determine who wins a billion dollar program are actually made two to five years before the reality. Request for proposal the RFP ever hits the street. Two to five years before a public bid, what is practically happening during that massive window? A tremendous amount of groundwork. The owner is quietly handling land acquisition, navigating zoning approvals. Environmental impact studies, probably. Exactly. And for a data center, they're spending years negotiating with utility companies for massive power grid allocations. During this invisible phase, they hire program managers to sketch out the master plan. So how does a mid -sized contractor infiltrate that invisible phase? This is where
you have to utilize Smart Business Automator to track award data and monitor program manager selections years in advance. Because it's the intelligence that drives your positioning. Exactly. If you see a specific program management firm was just retained by a major tech client to scout locations in your state, your business development team needs to engage them immediately. To do what, though? Pitch a proposal that doesn't exist yet? No, to act as an unpaid constructability consultant. You provide them with actionable intelligence. Like warning them about local supply chain bottlenecks. Right. Or offering insights into the current availability of union labor in that county. You establish trust and prove your competence years before they ask you for a price. That requires an incredible amount of
patience. So if we zoom out, what does the actual step -by -step roadmap look like for a mid -sized firm trying to climb this mountain? It is functionally a 10 -year positioning roadmap. In years one through three, your executive team is focused strictly on the specialty subcontract path. Taking down those $20 to $50 million scopes. Flawlessly, under mega primes. And establishing that your safety EMR is permanently locked below 1 .0. Building the resume. proving you aren't a liability. Correct. Then in years four through six, your financial focus shifts to bonding growth. You use the retained earnings from those subcontracts to build your working capital. Showing the surety underwriters your WIP schedules are disciplined. Exactly. Steadily raising your bonding ceiling
from $50 million to $100 million and beyond. Expanding your capacity to absorb risk. Yep. Then moving into year seven through nine, you leverage that expanded capacity and your pristine mega project resume to aggressively court a strategic JV partner for a prime contract. All while your compliance team is constantly updating your financials and safety data across all the proprietary portals. Letlessly. Which leads to a very real operational problem, right? Like if decisions are made five years out and the roadmap takes 10 years. How do these midsize contractors sustain morale, focus, and cash flow while basically chasing a ghost for half a decade? That is the ultimate test of executive leadership. You survive the wait by strictly enforcing a dual -track business model. So keeping one foot in the present. Yes.
Your operations team has to remain fiercely focused on executing the core business. the bread and butter $30 million conventional projects. Because that's what pays the overhead and keeps the lights on. And keeps field morale high through regular visible winds. Because if your field team loses focus and blows a budget, or has a major safety incident on a routine project... Your EMR spikes, your capital drains, and your 10 -year roadmap evaporates overnight. Exactly. You can't let the pursuit of tomorrow's billion -dollar whale distract from pouring today's concrete. Meanwhile, the executive team lives entirely in the future. Right. They're the ones utilizing the market intelligence tools, courting the program managers, structuring future JVs. The friction between present -day execution and a multi... year pursuit
is immense. It's an incredible balancing act. So to synthesize all of this for you listening, winning a piece of a billion dollar mega project is never an accident of just being the lowest bidder on the right day. Never. It is the culmination of a decade of strategic positioning, the financial discipline to scale bonding capacity. The rigor to maintain an EMR strictly below 1 .0 and brilliant partnering using JVs and federal set -asides as entry points. And leveraging deep market intelligence long before a bid goes public. Truly an endurance sport played at the highest financial stakes. It really is. And, you know, when we look at the sheer scale of the roadmap required just to compete, it raises a critical, honestly provocative question about the future of the industry. Oh,
what's that? Well... If the market continues this extreme trajectory of bifurcation, where only the absolute giants, the turners of the world, can secure the top spot. And smaller firms are permanently forced into specialty sub or JV roles. Right. Will we eventually see the complete extinction of the midsize prime contractor? Like, are we heading toward a future skyline built entirely by hyper -specialized subs on the bottom answering to a monopoly of mega primes at the top with absolutely nothing surviving in between? It really is an ecosystem where you either adapt to the scale or you disappear. We will leave you to chew on what that means for your firm and for the future of the industry at large. Food for thought. Thank you for joining us on this deep dive. If this conversation helped you map out your next decade of growth, please take
a second to like, share, comment, and subscribe from wherever you are listening today. Until next time.