Billing and cash flow

How to fill out AIA G702 and G703

Fill out the G703 continuation sheet first, one schedule of values line at a time, then carry its totals to the G702 summary page, apply retainage, subtract what you were already certified, and sign.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

To fill out an AIA pay application, start with the G703 continuation sheet. List every line of your approved schedule of values, enter what was billed before, what you installed this period, and what material is stored, then total the columns. Those totals go onto the AIA G702 summary page, where you add change orders, take out retainage, subtract prior certificates, and arrive at the current payment due. The contractor signs (and notarizes if the contract asks for it), and the architect certifies the amount.

The order matters. AIA's own instructions say the summary information from the G703 is transferred to the G702 after the G703 is complete. People who start on the G702 and back into the detail are the ones who end up with a line 4 that does not match anything.

What the G702 and G703 are

The G702 is the Application and Certificate for Payment. It is one page: the contractor's request on the left, the architect's certificate on the right. The AIA G703 is the Continuation Sheet, the detail behind the request. AIA describes the pair as made for projects where the contractor has a direct agreement with the owner, with the procedures set out in the A201 general conditions. AIA does not publish a separate schedule of values form, so the G703 usually carries the SOV itself.

Step by step: filling out the G703

  1. Columns A, B, and C. Enter the item number, description, and scheduled value for each line, straight from the schedule of values approved at the start of the job (or as adjusted). Keep the same breakdown every month. Column C should start out equal to the original contract sum.
  2. Column D, from previous application. Copy what the last pay app showed in its columns D and E for each line. Do not carry over last month's stored materials here.
  3. Column E, this period. Enter the value of work put in place since the last application. If material that was stored last month got installed this month, its value moves into E now.
  4. Column F, materials presently stored. Enter the value of material stored and not yet installed, both new deliveries and older stored material still sitting on site or in an approved warehouse. Recalculate this total every period.
  5. Column G, total completed and stored. Add D, E, and F. Divide G by C for percent complete.
  6. Column H, balance to finish. Subtract G from C.
  7. Column I, retainage. Use it only if your contract allows retainage to vary by line. If one flat rate applies to the whole contract, leave it blank and calculate retainage on the G702.
  8. Subtotal and total. Subtotal column C at the bottom of each page except the last, and total it on the last page. Add up D through I the same way.

Step by step: filling out the G702

With the G703 totaled, the G702 is mostly arithmetic. The line labels below are the ones printed on the form.

The nine lines of the G702 contractor's application
LineLabelWhere the number comes from
1Original contract sumThe signed contract. It never changes.
2Net change by change ordersThe change order summary box (approved changes only)
3Contract sum to dateLine 1 plus line 2
4Total completed and stored to dateColumn G total from the G703
5RetainageRetainage on completed work plus retainage on stored material
6Total earned less retainageLine 4 minus line 5
7Less previous certificates for paymentLine 6 from last month's certified application
8Current payment dueLine 6 minus line 7
9Balance to finish, including retainageLine 3 minus line 6

The change order summary

The box at the lower left splits approved change orders into those approved in previous months and those approved this month, additions and deductions in separate columns. The net of that box is line 2. Pending change order requests do not go here. Bill them only after they are signed.

Signature, notary, and the architect's certificate

AIA's instructions say the contractor signs the G702, has it notarized, and submits it with the G703 to the architect. Sign in your actual capacity (president, partner, and so on). The architect reviews both pages and, if acceptable, completes the certificate. The architect can certify a different amount than you asked for, and when that happens AIA says the architect initials every changed figure on both forms and attaches an explanation. The owner then pays the certified amount.

Worked example: month three on a tenant improvement

Here is an illustration. Say a general contractor has a $480,000 tenant improvement with 10 percent retainage, plus one approved change order last month for $12,000 of added data cabling. Prior certified payments total $153,000 (line 6 of the month two pay app).

Example G703 totals and the resulting G702, month three
ItemAmount
Line 1, original contract sum$480,000
Line 2, net change by change orders$12,000
Line 3, contract sum to date$492,000
G703 column D (previous applications)$170,000
G703 column E (this period)$95,000
G703 column F (stored: light fixtures in the space)$18,000
Line 4, total completed and stored (column G)$283,000
Line 5, retainage at 10 percent$28,300
Line 6, total earned less retainage$254,700
Line 7, less previous certificates$153,000
Line 8, current payment due$101,700
Line 9, balance to finish including retainage$237,300

Check the math the way the reviewer will. Line 4 must equal the G703 column G total. Line 9 must equal line 3 minus line 6. Line 7 must match last month's line 6 as certified, not as you submitted it. If the architect cut month two by $4,000, your line 7 is the lower number.

Mistakes that get pay apps sent back

  • Line 4 does not tie to column G. Usually caused by a hand-typed G702 or a hidden spreadsheet row.
  • Billing unapproved changes. Pending pricing slips into line 2 or into a base line. Reviewers catch it and hold the whole application.
  • Stored material without backup. Many contracts require invoices, photos, insurance, or a bill of sale before stored material is paid. See how to bill stored materials.
  • Front-loading. Percent complete on early lines that runs well ahead of the field. Superintendents and lenders walk the job, and an obvious mismatch costs trust on every later pay app.
  • Using last month's submitted numbers instead of certified numbers for column D and line 7.
  • Missing attachments. Lien waivers, certified payroll on public jobs, and updated schedules are often required with each application. A perfect G702 still sits if the package is incomplete.

Templates, terms, and tools that help

Build your line items once with the schedule of values template and see how to build a schedule of values before the first billing. Track what is held back with the retainage tracking template, and read how to bill retainage correctly for the release invoice. Related terms: pay application, progress billing, and stored materials.

Smart Business Automator builds the continuation sheet from your schedule of values and approved change orders, carries certified amounts forward each month, and calculates retainage, so the G702 lines tie out before anyone signs. See construction accounts receivable automation.

Frequently asked questions

Does the AIA G702 have to be notarized?

AIA's instructions say the contractor should sign the G702 and have it notarized. Some owners waive the notary in the contract, and some require it. Follow the contract and the owner's billing instructions for your job.

What goes in column I on the G703?

Column I is for retainage when the contract allows different rates on different lines. If one flat percentage applies to the whole contract, AIA says the column does not need to be filled in, and retainage is calculated on line 5 of the G702.

Can a subcontractor use the G702 and G703?

Many general contractors ask subs to bill on G702 and G703 or a look-alike form so they can roll the numbers into their own pay app. AIA designed the pair for contractors with a direct agreement with the owner, so read your subcontract for the required format.

What if the architect changes my numbers?

The architect may certify a different amount and must initial the changed figures and attach an explanation. Use the certified figures as your starting point next month, and resolve the difference through the contract's dispute or change process.

Where do pending change orders go?

Nowhere on the pay app until they are approved. The change order summary and line 2 include approved changes only. Track pending requests separately and push for signatures before the billing cutoff.

Sources

  1. AIA Contract Documents: Summary of G702-1992, Application and Certificate for Payment
  2. AIA Contract Documents: Instructions for G702-1992, Application and Certificate for Payment
  3. AIA Contract Documents: Instructions for G703-1992, Continuation Sheet
  4. Mastt: AIA G702 guide (line labels and calculations)