Prompt payment

Washington, D.C. prompt payment act and retainage rules

On private D.C. jobs, owners pay undisputed amounts within 7 days after the contract's payment date, contractors pay subs within 7 days of being paid, and late money earns 1.5 percent a month. District agency contracts follow the Quick Payment provisions, with a 7-day flow-down to subs.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Washington, D.C. has a private prompt payment act and a public one. Title 27A, Chapter 1 of the D.C. Code (§§ 27A-101 to 27A-106) covers private construction contracts entered into on or after October 1, 2013. It gives owners 7 days after the contract's payment date to pay undisputed amounts (or 15 days after a payment request if the contract sets no date), gives contractors 7 days to pay subs after they are paid, and charges 1.5 percent interest per month on late undisputed amounts. Public contracts with District agencies follow the Quick Payment provisions in §§ 2-221.01 to 2-221.06, which also require a 7-day flow-down to subs. Notably, the private law counts withheld retainage as part of an undisputed amount.

D.C. payment rules at a glance
RulePrivate work (§ 27A-101 et seq.)District agency contracts (§ 2-221.01 et seq.)
Owner pays prime7 days after the contract payment date; if none, earliest of 15 days after occupancy permit, possession, or payment request (§ 27A-102)Contract due date, or 30 calendar days (excluding legal holidays) after a proper invoice (§ 2-221.02(a))
Prime pays sub7 days after receiving payment for the sub's work (§ 27A-104(a))Within 7 days of being paid: pay the sub's share or give written notice of withholding with reasons (§ 2-221.02(d)(1))
Late interest1.5% per month or part of a month (§§ 27A-103, 27A-105)Set by Mayor's regulation, at least 1%; no penalty if paid within 15 days after the due date (§ 2-221.02(b))
RetainageCounted in undisputed amounts (§ 27A-101(5)); no statutory capNo cap in these sections; check the contract and solicitation
Pay-if-paidCannot waive lien or bond rights; such terms void (§ 27A-104(b), (c))Flow-down tied to the District's payment
FeesPrevailing contractor or sub recovers costs and attorney's fees in an interest actionInterest claims go to the contracting officer, then the Contract Appeals Board

Private jobs: owner payment deadlines

Under § 27A-102, the owner's deadline depends on whether the contract sets payment dates. If it does, undisputed amounts are due within 7 days after the date in the contract. If it does not, the owner must pay within the earliest of 15 days after the occupancy permit is granted, 15 days after the owner or its agent takes possession, or 15 days after receiving the contractor's payment request. An "owner" includes a tenant that hires the contractor, which matters a lot in D.C. office fit-outs, but excludes District agencies.

Miss the deadline and § 27A-103 adds interest of 1.5 percent per month, or any part of a month, on the undisputed amount. A contractor that wins a suit to collect that interest gets its costs and reasonable attorney's fees.

Private jobs: flow-down to subs and the 2023 offset rule

Section 27A-104 requires the contractor, and each sub paying a lower tier, to pay undisputed amounts within 7 days after receiving each payment for that sub's work or materials. Late payment carries the same 1.5 percent per month and fee recovery (§ 27A-105). The definition of subcontractor is broad: it includes anyone who performs work on the site for a contractor or sub, and fabricators who build project-specific items off-site from the plans.

  • No cross-contract offsets: a contractor or sub may not withhold a lower tier's payment to offset another contractual obligation or work still to be completed (§ 27A-104(d)(1)).
  • Void clauses: in contracts executed after March 31, 2023, a provision letting a party withhold funds on one contract for claims on a different contract is void as against public policy (§ 27A-104(d)(2)).
  • Lien and bond rights survive: a condition that ties sub payment to the contractor receiving the owner's payment cannot waive the sub's right to claim a mechanics' lien or sue on the contractor's bond (§ 27A-104(b)).

That last point is how D.C. handles the pay-if-paid clause. The statute does not ban conditional payment terms outright, but any such term that tries to waive lien or bond rights is void (§ 27A-104(c)). A sub that is not paid because the owner did not pay keeps its security. See the D.C. mechanics lien rules for those deadlines.

District agency contracts: the Quick Payment provisions

When a District agency is the owner, § 2-221.02 sets the required payment date as the date in the contract, or 30 calendar days (excluding legal holidays) after the agency receives a proper invoice. The agency must flag defects in an invoice in writing within 15 days of receipt. Interest is set by the Mayor's regulations at a rate of at least 1 percent, but no penalty is owed if payment is made within 15 days after the required date. Unpaid penalties are added to principal every 30 days. Claims for interest go to the contracting officer, who must decide within 30 days, and can be appealed to the Contract Appeals Board within 90 days (§ 2-221.04).

Every District agency contract must include a clause requiring the prime to act within 7 days of being paid: either pay the sub its proportionate share or notify the agency and the sub in writing that it is withholding, with the reason. The prime owes the sub interest on late payments, must flow these clauses down to lower tiers, and cannot pass that interest cost back to the District. A dispute between a prime and a sub is not a dispute with the District.

Retainage in D.C.

Neither Title 27A nor the Quick Payment sections set a retainage percentage, a reduction point, or an escrow option. On private work, the amount held and the release trigger come from the contract, but retainage that is not subject to a good-faith dispute counts as an undisputed amount, so the 7-day clocks and 1.5 percent interest can apply once it is due. On District agency work, read the solicitation and contract terms, and ask the contracting officer about the agency's release process.

Seven days is a short window. Smart Business Automator tracks when each owner payment lands and what share belongs to each sub, so the flow-down goes out on time. See construction accounts receivable automation. If you bid District work, check the D.C. prevailing wage requirements as well.

Frequently asked questions

How fast must a D.C. general contractor pay subcontractors?

On private jobs, within 7 days after receiving payment for the sub's work. On District agency contracts, within 7 days the prime must either pay the sub's share or give written notice of withholding with the reason.

What interest applies to late private construction payments in D.C.?

1.5 percent per month, or any part of a month, on undisputed amounts, plus costs and attorney's fees if the contractor or sub wins a suit to collect it.

Does D.C. cap retainage?

The D.C. Code sections on prompt payment do not set a retainage percentage. On private jobs, retainage not in good-faith dispute counts as an undisputed amount subject to the prompt payment deadlines.

Are pay-if-paid clauses allowed in D.C.?

A clause tying sub payment to the owner's payment cannot waive the sub's mechanics' lien or bond rights. Any provision that tries to is void under § 27A-104(c).

Does the private law apply to tenant fit-outs?

Yes. The definition of owner includes a tenant that contracts directly with a contractor.

Sources

  1. D.C. Code § 27A-101: Definitions (Private Contractors and Subcontractors Prompt Payment)
  2. D.C. Code § 27A-102: Prompt payments to contractors
  3. D.C. Code § 27A-104: Prompt payments to subcontractors
  4. D.C. Code § 27A-105: Failure to make prompt payments to a subcontractor
  5. D.C. Code § 2-221.02: Interest penalty payments by District agencies
  6. D.C. Code § 2-221.04: Filing of claims; disputed payments

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.