Legal

What are consequential damages in construction?

Consequential damages are indirect losses that flow from a breach, such as an owner's lost rent or a contractor's lost profit on other work, as opposed to the direct cost of fixing the problem.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

In construction, damages usually split into two kinds. Direct damages are the natural, immediate cost of a breach: the cost to tear out and replace a bad roof, or the extra cost of a replacement sub. Consequential damages are the ripple effects: the store that could not open on time, the tenant who walked, the financing that cost more, the profit a contractor lost on jobs it could not bid because its bonding was tied up. They can be far larger than the contract itself, which is why most construction contracts deal with them directly.

The mutual waiver of consequential damages

Many standard forms include a mutual waiver in which owner and contractor give up claims against each other for consequential damages. In AIA A201-2017, the general conditions used on a large share of U.S. commercial work, it appears at section 15.1.7. Commentary in STRUCTURE magazine summarizes the categories: the owner waives items such as rental expenses, loss of use, income, profit, financing, business and reputation, and loss of employee productivity; the contractor waives items such as principal office expenses, lost opportunities and profit, loss of bonding or increased bonding costs, and damage to reputation. The same article ties the clause's origin to an arbitration award against a construction manager for $14,500,000 in an owner's lost profits from project delay.

Under A201, the waiver does not block liquidated damages where the contract provides for them. That is a key interaction: an owner who gives up consequential damages often negotiates a liquidated damages rate to cover delay instead.

Worked example

A GC builds a $2.2 million restaurant. Completion slips six weeks because of the GC's own scheduling problems. The owner claims $180,000 in lost profit and $24,000 in extra rent on its old location. If the contract has a mutual waiver with no liquidated damages, the owner's lost profit and rent are likely waived, and recovery is limited to direct damages. If the contract has no waiver at all, the GC faces the full claim. If the contract has a waiver plus liquidated damages of $1,500 a day, the owner collects the agreed daily rate for the delay period instead.

Common mistakes and disputes

  1. Deleting the waiver without noticing. Owners' attorneys sometimes strike it, and contractors sign without catching the change.
  2. Mismatched subcontracts. A GC that has the waiver with the owner but not with its subs (or the reverse) can be caught in the middle.
  3. Direct or consequential? There is no universal definition, so the same loss can be argued either way. Listing the waived categories helps.
  4. Indemnity clauses that bring it back. A broad hold harmless clause can reopen exposure the waiver was supposed to close.

Related terms

See delay claim, no damages for delay clause, and force majeure. The guide how to negotiate liquidated damages covers the trade-off, and construction contract clauses that hurt subcontractors shows where waivers go missing.

Frequently asked questions

What is an example of consequential damages in construction?

An owner's lost rental income or lost profits because a building opened late, or a contractor's lost profits on other work because a dispute tied up its bonding capacity.

Is a mutual waiver of consequential damages enforceable?

Courts in most jurisdictions generally enforce clear, negotiated waivers between commercial parties. Enforceability depends on state law and the wording, so have counsel review it.

Does the waiver stop liquidated damages?

Not under AIA A201-2017, which says the waiver does not preclude liquidated damages when the contract provides for them. Other forms may differ.

Who benefits more from the waiver?

Usually the contractor, since an owner's lost profits and lost use can dwarf the contract price. Owners often ask for liquidated damages in exchange.

Sources

  1. STRUCTURE magazine: Waiver of Consequential Damages
  2. AIA Contract Documents: article on the A201-2017 mutual waiver of consequential damages
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment