What is termination for default in construction?

Termination for default (or termination for cause) ends the contractor's right to keep working because it failed to perform, such as falling far behind, abandoning the job, or not fixing defective work, and leaves it liable for the owner's extra cost to finish.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

Termination for default is the most serious remedy an owner (or a GC, against a sub) has under a construction contract. It says: you breached, you are off the job, and you will pay the difference to finish. It is different from termination for convenience, where nobody is at fault and the contractor gets paid its costs.

Because the consequences are severe (lost contract, back charges, a hit to bonding, sometimes debarment on public work), contracts usually require warnings and a chance to fix the problem first. A cure notice is the typical first step.

How a default termination plays out on a real job

Say a GC has a $620,000 drywall subcontract on a hotel. The sub is four weeks behind, keeps showing up with three hangers instead of ten, and has ignored two written requests to man up. The GC sends a cure notice giving the sub a set number of days (per the subcontract) to submit a recovery plan and staff the job. Nothing changes. The GC terminates for default, notifies the sub's surety if the sub was bonded, takes over the stored board on site as the contract allows, and brings in a replacement crew at $95,000 more than the remaining subcontract balance.

That $95,000, plus the GC's added supervision and any delay damages, becomes a back charge against the sub's unpaid balance and retainage. If the balance does not cover it, the GC pursues the sub or its performance bond.

The federal construction default clause

On federal fixed-price construction, FAR 52.249-10, Default (Fixed-Price Construction), applies. If the contractor refuses or fails to prosecute the work with the diligence that will ensure completion on time, or fails to complete on time, the government may terminate the right to proceed, take over the work, and use materials and equipment on site. The contractor and its sureties are liable for resulting damages, including increased completion cost.

The clause protects contractors from default for excusable delays. The right to proceed is not terminated if the delay arises from unforeseeable causes beyond the contractor's control and without its fault, such as acts of the government, fires, floods, epidemics, strikes, or unusually severe weather, and the contractor notifies the contracting officer in writing of the causes within 10 days from the beginning of the delay (unless extended). If a default termination is later found improper, the clause treats it as a termination for convenience.

Common mistakes and disputes

  1. Skipping the cure process. Terminating without following the notice steps in the contract can turn the owner's default termination into the owner's own breach.
  2. Waiving the deadline. An owner who lets a contractor keep working long after a missed date, without reserving rights, may have trouble defaulting it later for that same date.
  3. Not giving delay notices. Contractors who fail to send timely written notice of excusable delays lose their best defense.
  4. Poor documentation. Manpower counts, schedule updates, and daily logs decide these cases.
  5. Forgetting the surety. Bonded contractors' sureties usually have notice and takeover rights. Cutting them out can weaken a bond claim.

Related terms

See excusable delay, performance bond, back charge, and subcontractor default insurance. Smart Business Automator keeps daily logs, notices, and schedule updates tied to each subcontract, which is the record a default decision rests on.

Frequently asked questions

What is the difference between termination for default and termination for cause?

They mean the same thing in most construction contracts. Federal contracts say default; many private forms say cause.

Does a contractor get a chance to fix problems before termination for default?

Usually. Most contracts require a written cure notice and a period to correct the failure before termination. The exact steps and number of days come from the contract, so read the termination article before sending or answering a notice.

What happens to the surety after a default termination?

The surety on the performance bond is typically notified and may finance the contractor, arrange completion, or pay the owner's excess costs up to the bond amount, under the bond's terms.

Can a default termination be converted to a convenience termination?

Yes. Under FAR 52.249-10, if the contractor was not in default or the delay was excusable, the rights of the parties are the same as if the termination had been for the government's convenience. Many private contracts have similar language.

Sources

  1. Acquisition.gov: FAR 52.249-10, Default (Fixed-Price Construction)
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment