Change orders and contracts

How to handle verbal change requests from owners

Treat every verbal request as the start of a change order, not the change itself. Confirm it in writing the same day, price it, and get a signature before your crew touches the new work.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

When an owner asks for extra work out loud, write it down the same day, send it back as a change order request, and hold the new work until someone with authority signs a priced change order. If the owner needs it done right now, get a signed time and materials authorization or a written directive first, then settle the price. A handshake on the slab is not a contract change, and most contracts say so in plain language.

Verbal requests are where good margins quietly go to die. The owner remembers asking for "a couple more outlets." The foreman remembers an extra circuit, a new panel space, and two days of labor. Three months later, the invoice line shows up and nobody agrees on what was said. The fix is a habit, not a lawsuit.

Why verbal changes cause so many fights

Most prime contracts and subcontracts require changes to be in writing and signed by a named representative. Many also require written notice within a set number of days if you believe you were directed to do extra work. Federal construction is a good example. Under the FAR Changes clause (52.243-4), an oral order or direction counts as a change only if the contractor gives written notice stating the date, circumstances, and source of the order and that it regards the order as a change. Costs incurred more than 20 days before that written notice are not recoverable, and the contractor must assert its right to an adjustment within 30 days of the notice unless the government extends the period.

Residential work can be stricter still. In California, the Contractors State License Board tells homeowners that any change to the contract price must be made with a written change order that becomes part of the contract. Other states have their own home improvement rules. Read your contract and your state's rules before assuming a verbal yes will get you paid.

Step-by-step: handling a verbal change request

1. Acknowledge it, do not agree to it

Train foremen and supers to use one sentence: "Got it, I will get that priced and back to you today." That is polite, it keeps the relationship warm, and it commits to nothing. The worst answer is "No problem, we will take care of it," because the owner hears "free."

2. Write it down within hours

Log the request in the daily log with who asked, when, where on site, and what exactly they described. Take photos of the area as it sits now. If the request came by phone, note the call time. This record is your evidence later if the owner says the request never happened.

3. Send a written confirmation the same day

Email the owner or owner's rep a short note: what you heard, that it is outside the current scope, and that pricing will follow. Ask them to reply if anything is wrong. A two-line email sent at 4 p.m. is worth more than a perfect change order sent three weeks later.

4. Check the contract for who can approve changes

The person asking is not always the person who can sign. A tenant, a property manager, or the owner's spouse may have no authority under the contract. Find the clause that names the authorized representative and send the change order request to that person, with the requester copied.

5. Price it with time and cost impact

Build the price from labor hours, burdened rates, material, equipment, subcontractor quotes, and your contract markup. Always state the schedule effect, even when it is zero days. A change order that is silent on time can be read later as a waiver of any delay. The guide on how to price a change order covers the math.

6. Get a signature before the work, or a written directive if it cannot wait

If the owner signs, proceed. If the work truly cannot wait (an inspector is coming, or the wall closes tomorrow), ask for a signed change directive or a time and materials ticket that authorizes the work with price to follow. Track the hours and material daily on that ticket and have the owner's rep initial it.

7. Log it and bill it

Add the approved change to your change order log and your schedule of values so it shows up on the next pay application. Unbilled approved changes are just as costly as unapproved ones.

Worked example: the extra outlets

Here is an illustration. An electrical contractor is wiring a $480,000 tenant improvement. On a Tuesday walk, the tenant's office manager asks the foreman for six more floor outlets in the open office. The foreman answers, "I will get that priced today," logs it with photos, and calls the PM.

Example change order request for six floor outlets
ItemAmount
Labor: 18 hours at $92 burdened$1,656
Material: floor boxes, wire, conduit$1,140
Core drilling sub$900
Subtotal$3,696
Markup at 15% per contract$554
Total change order request$4,250
Schedule impact1 working day

The PM checks the subcontract: only the GC's project manager can approve changes, and the GC needs owner approval. The PM sends the request to the GC that afternoon, copying the office manager. The GC gets owner sign-off two days later, and the work proceeds. Without that paper, the same outlets would have been installed, argued about at closeout, and probably written off.

Mistakes to avoid with verbal change requests

  • Doing the work to be nice. Goodwill does not pay for labor, and it sets an expectation that the next request is free too.
  • Letting the foreman negotiate price. Field staff should capture the request, not quote it. Price comes from the office.
  • Missing a notice deadline. Some contracts give you a short window to give written notice of a claimed change. Put those days on a calendar the day the contract is signed.
  • Getting approval from the wrong person. A yes from someone without authority is often worth nothing.
  • Leaving out the time impact. Every change order should state the days added, or state zero.
  • Treating email threads as change orders. An email is a good record, but most contracts still want a signed change order form.

Templates, terms, and tools that help

Start with a construction change order template that includes scope, price, time, and signature lines, and keep every request on a change order log so nothing waits in someone's inbox. For the bigger picture, read how to get change orders signed before doing the work and the related terms field order and scope creep.

Smart Business Automator lets a super log a verbal request from the field, turns it into a priced change order request, and routes it to the right approver with a timestamp. See change order approval automation for how that flow works.

Frequently asked questions

Is a verbal change order legally binding?

Sometimes, but it is risky to rely on. Many contracts require written, signed changes, and some state home improvement rules do too. Courts may look at conduct, but proving a verbal agreement is hard and expensive. Get it in writing.

What if the owner refuses to sign but insists the work be done?

Send written notice that you consider the direction a change and that you are proceeding under protest, following the notice clause in your contract. Track costs separately on a time and materials basis so you can support a claim later.

Can I just add verbal changes to the final invoice?

You can try, but unapproved extras on a final invoice are one of the most common causes of payment disputes and short pays. Price and approve changes as they happen.

Who should handle verbal requests on site?

The super or foreman should capture and log the request, then pass it to the project manager, who prices it and gets approval. Keep pricing and approval in the office.

Sources

  1. Acquisition.gov: FAR 52.243-4 Changes
  2. California Contractors State License Board: Home Improvement Contracts consumer guide (PDF)
  3. California Contractors State License Board: Contracts and binding agreements
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.