Arizona mechanics lien law and deadlines

Arizona lien claimants other than wage laborers must serve a preliminary twenty day notice, record a notice and claim of lien within 120 days after completion (or 60 days after a recorded notice of completion), and sue within six months of recording.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Arizona's mechanics lien rules are in Arizona Revised Statutes 33-981 and following, and they are strict on paper. Almost everyone except a wage laborer must serve a preliminary twenty day notice within 20 days of first furnishing to the jobsite. The lien itself must be recorded with the county recorder within 120 days after completion, or within 60 days if the owner records a notice of completion. Then the lien dies six months after recording unless you sue and record a notice of pendency of action. Arizona also uses mandatory statutory lien waiver forms.

Arizona mechanics lien deadlines at a glance
StepDeadline or ruleStatute
Preliminary twenty day noticeWithin 20 days after first furnishing to the jobsite; late notice covers only work within 20 days before service and afterARS 33-992.01
Who must give itEveryone with lien rights except people performing actual labor for wagesARS 33-992.01(B)
Record notice and claim of lienWithin 120 days after completionARS 33-993(A)
If owner records notice of completionWithin 60 days after it is recordedARS 33-993(A)
Where to recordCounty recorder where the property is; serve a copy on the ownerARS 33-993(A)
Suit to forecloseWithin 6 months after recording, plus a recorded notice of pendency of actionARS 33-998
Owner-occupied homesOnly a claimant with a written contract directly with the owner-occupant can lienARS 33-1002
Public projectsNo lien; payment bond for the full contract amountARS 34-222, 34-223

Who has lien rights in Arizona

ARS 33-981 gives a lien to every person who labors or furnishes professional services, materials, machinery, fixtures, or tools in the construction, alteration, or repair of a building or improvement. That includes general contractors, subs at every tier, suppliers, equipment providers, and design professionals. Every contractor, sub, or architect in charge of the work is treated as the owner's agent, which is what lets lower tiers reach the owner's property.

  • Licensing. Anyone required to hold an Arizona contractor license who does not hold a valid one has no lien rights. See Arizona contractor license requirements.
  • Design professionals. Architects, engineers, and similar professionals need a valid certificate of registration, and they must have an agreement with the owner or with an architect, engineer, or contractor who has one.
  • Notice is a condition. If you were required to serve the 20-day notice and did not, with proof of service, you cannot enforce the lien.

The preliminary twenty day notice

This is Arizona's preliminary notice, and it is not optional. Serve it on the owner or reputed owner, the original contractor, the construction lender if any, and the person who hired you, no later than 20 days after you first furnish labor, professional services, materials, machinery, fixtures, or tools to the jobsite.

It must include a general description of what you are furnishing with an estimated total price, your name and address, the name of the party who hired you, a description of the jobsite, and a bold-faced statement that begins "In accordance with Arizona Revised Statutes section 33-992.01, this is not a lien..." followed by the notice to property owner language. Keep the proof of mailing: a copy of the notice and the proof must be attached to your lien.

Late is better than never, but it costs you. A notice served late covers only work furnished within 20 days before service and everything after. Picture an electrical sub that starts rough-in on June 1 and serves notice on July 15. Anything installed before June 25 is outside the lien. Raise the estimate later with an amended notice if the scope grows.

Recording the lien and what counts as completion

Record the notice and claim of lien with the county recorder within 120 days after completion, or within 60 days after the owner records a notice of completion. It must be made under oath and include the legal description, owner's name, who hired you, contract terms (or a copy of a written contract), your demand after credits, the completion date, and the date the 20-day notice was given. Serve the second copy on the owner within a reasonable time.

Completion is the earliest of 30 days after final inspection and written final acceptance by the permitting agency, or 60 consecutive days with no labor (strikes, material shortages, and acts of God excepted). With no permit or no final inspection, completion is the last date anyone furnished work to the property. In multi-building residential projects, each building has its own completion date.

Foreclosing the lien

Under ARS 33-998, the lien lasts no longer than six months after recording unless you file suit within that period and record a notice of pendency of action with the county recorder. If another claimant sues and names you, filing an answer or cross-claim asserting your lien within the six months counts. The court may award reasonable attorney fees to the successful party, which cuts both ways.

Owner-occupied homes

ARS 33-1002 is a major limit for residential subs and suppliers. On a one- or two-family dwelling (including a condominium unit) owned by an owner-occupant who held title before the work started and intends to live there, no lien is allowed except by a person who signed a written contract directly with the owner-occupant. A drywall sub working for the remodeler has no lien on that house, and the owner-occupant cannot waive the protection. Subs on those jobs should lean on credit checks, joint checks, and fast collections.

Statutory lien waiver forms

ARS 33-1008 says a waiver and release is enforceable only if it follows substantially one of the four statutory forms: conditional and unconditional waivers on progress payment and on final payment. A conditional waiver releases rights only when there is evidence of payment, such as your endorsement on a check the bank has paid. Contract clauses that waive lower-tier lien rights without their written consent are void. Use conditional waivers until funds clear.

Public projects use payment bonds

Public property is not lienable. ARS 34-222 requires contractors on public buildings and works of counties, cities, towns, and many districts to post a performance bond and a payment bond, each equal to the full contract amount. Under ARS 34-223, a claimant unpaid 90 days after its last work can sue on the bond. A claimant hired by a sub, with no contract with the prime, must also give the prime the preliminary twenty day notice and a written notice within 90 days after its last work stating the amount claimed.

See also Arizona prompt payment rules. Smart Business Automator tracks 20-day notice dates, waivers, and open balances per job; see construction accounts receivable automation.

Frequently asked questions

Is a preliminary notice required in Arizona?

Yes. Everyone claiming a lien except people performing actual labor for wages must serve a preliminary twenty day notice within 20 days after first furnishing to the jobsite (ARS 33-992.01). A late notice only protects work from 20 days before service onward.

How long do I have to record a mechanics lien in Arizona?

Within 120 days after completion of the improvement, or within 60 days after the owner records a notice of completion (ARS 33-993).

How long does an Arizona mechanics lien last?

Six months after recording, unless suit is filed and a notice of pendency of action is recorded in that time (ARS 33-998).

Can a subcontractor lien an owner-occupied home in Arizona?

Generally no. ARS 33-1002 allows a lien on an owner-occupant's dwelling only by a person with a written contract directly with the owner-occupant.

Does Arizona have statutory lien waiver forms?

Yes. ARS 33-1008 sets out conditional and unconditional waiver forms for progress and final payments, and a waiver is unenforceable unless it substantially follows one of them.

Sources

  1. Arizona Legislature, ARS 33-981: Lien for labor, professional services or materials
  2. Arizona Legislature, ARS 33-992.01: Preliminary twenty day notice
  3. Arizona Legislature, ARS 33-993: Procedure to perfect lien
  4. Arizona Legislature, ARS 33-998: Limitation of action to foreclose lien
  5. Arizona Legislature, ARS 33-1002: Owner-occupied dwelling
  6. Arizona Legislature, ARS 33-1008: Waiver of lien
  7. Arizona Legislature, ARS 34-222: Surety bond required
  8. Arizona Legislature, ARS 34-223: Payment bond provisions

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.