Prompt payment

Massachusetts prompt payment act and retainage rules

Public owners in Massachusetts pay periodic estimates within 15 days (30 for the Commonwealth), hold no more than 5 percent retainage, and owe the balance on a 65-day clock after substantial completion. Private jobs of $3 million or more fall under c. 149, §§ 29E and 29F, which void most pay-if-paid clauses and cap retainage at 5 percent.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Massachusetts has four payment statutes that matter to contractors. On public building work, M.G.L. c. 30, § 39K requires the awarding authority to pay a periodic estimate within 15 days (30 days for the Commonwealth), caps retainage at 5 percent of each approved payment, and requires the balance within 65 days after substantial completion. Section 39G sets parallel rules for public works such as roads, bridges, sewers, and water mains. On private work, the prompt payment act in c. 149, § 29E covers contracts of $3,000,000 or more, sets approval and payment deadlines for every tier, and voids most pay-if-paid clauses. Its companion, § 29F, caps private retainage on those same jobs at 5 percent of any progress payment and sets a release process after substantial completion.

Massachusetts payment and retainage rules at a glance
RulePublic buildings (c. 30 § 39K)Public works (c. 30 § 39G)Private $3M+ (c. 149 §§ 29E, 29F)
Owner pays periodic estimate15 days after receipt; 30 days for the Commonwealth15 days after receipt; 30 days for the CommonwealthApprove or reject in 15 days; pay 45 days after approval
Retainage cap5% of the approved periodic payment5% of the approved periodic payment5% of any progress payment (§ 29F(b))
Substantial completion paymentBalance within 65 days, less claims and cost to finishEstimate sent within 65 days of the declaration, releasing all retainage except 1%; paid within 35 days after the contractor accepts itRetainage application after 60 days from substantial completion, paid within 30 days (plus 7 days per lower tier) (§ 29F(f))
Late payment interest3 points above the Federal Reserve Bank of Boston rediscount rate3 points above the Federal Reserve Bank of Boston rediscount rateNot set in § 29E
Pay to subsForthwith after GC is paid (§ 39F); direct payment demand after 70 daysSame, under § 39FEach lower tier gets 7 more days to approve
Pay-if-paidNot addressedNot addressedVoid, with two narrow exceptions

Public building contracts under c. 30, § 39K

Section 39K covers building, altering, remodeling, repairing, or demolishing public buildings: Commonwealth contracts over $5,000 and local public contracts over $2,000. The awarding authority pays within 15 days after receiving a periodic estimate, or 30 days for the Commonwealth, local housing authorities included. It may hold a retention of no more than 5 percent of the approved amount, plus amounts for its own claims and for subcontractor direct-payment demands.

The balance is due within 65 days after the earliest of full completion, substantial completion (remaining work under 1 percent of the original contract price), or substantial completion with owner occupancy. The owner may still hold amounts for its claims and for incomplete work. Overdue payments carry daily interest at 3 percentage points above the rediscount rate charged by the Federal Reserve Bank of Boston, starting the day after the payment was due. On a final estimate, interest does not start until 15 days after receipt (24 days for the Commonwealth).

Public works contracts under c. 30, § 39G

  • Periodic payments: within 15 days of the contractor's estimate, or 30 days for the Commonwealth, with interest from the due date if late.
  • Retainage: no more than 5 percent of each approved periodic payment, plus 5 percent of planted-in-ground items until final acceptance.
  • Substantial completion: the owner has 21 days to respond to the contractor's certification with a declaration or an itemized deficiency list, or the certification takes effect.
  • Release: the substantial completion estimate is due within 65 days after the declaration and releases all retainage except 1 percent.
  • Final estimate: sent within 30 days after the contractor's notice that all work is complete, and paid within 35 days after the owner receives the contractor's written acceptance.

Subcontractors on public jobs: c. 30, § 39F

Section 39F requires the GC to pay each sub forthwith after it receives a periodic payment. The statute gives no number of days for that. It does give subs a real remedy at the end of the job: the sub's balance is due no later than the 65th day after substantial completion of the sub's work. If it has not been paid within 70 days, the sub may send a sworn demand for direct payment by certified mail, with a copy to the GC. The GC has 10 days to file a sworn reply, and the awarding authority pays within 15 days after receiving the demand, but not before day 70. Disputed sums go into an interest-bearing joint account.

Private work: c. 149, § 29E

Section 29E applies to private contracts with lien rights under chapter 254 where the original contract with the owner is $3,000,000 or more. Projects with 1 to 4 dwelling units are excluded. Payment applications go in every 30 days. The owner has 15 days to approve or reject, each lower tier gets 7 extra days, and approved amounts are paid within 45 days. An application not rejected in time is deemed approved. A rejection must be in writing, explain the factual and contractual basis, and be certified as made in good faith.

Conditioning payment on receipt from a third party is void, except for money lost because the claimant failed to perform and did not cure, or because the third party became insolvent within 90 days after the requisition and the claimant protected its lien rights and pursued its remedies. A clause forcing a party to keep working when an approved payment is more than 30 days late is also void, with limited exceptions, and any attempt to waive § 29E is void. Section 29E does not set an interest rate, so the contract governs that, and a sub waiting on a $3.4 million office fit-out should read it closely.

Retainage on those private jobs is covered by § 29F. No contract may hold more than 5 percent of any progress payment. Within 14 days after substantial completion, the prime sends the owner a notice of substantial completion, and the owner has 14 days to accept or reject it in writing, or it is deemed accepted. The owner then lists incomplete or defective work and missing close-out deliverables, and the prime passes a list down to each sub it holds retainage from. Starting 60 days after substantial completion (or sooner if the contract allows), a party may apply for its retainage, and the application must be paid within 30 days, plus 7 days for each tier below the owner. Withholding from that payment is limited to the value of missing deliverables (capped at 2.5 percent of the adjusted contract price if no value was agreed), 150 percent of the reasonable cost to finish or fix listed items, and the value of properly made claims.

Smart Business Automator tracks each pay application's submission, approval, and payment dates by tier, so deemed approvals and the day-70 window do not slip by. See construction accounts receivable automation.

Frequently asked questions

What is the retainage limit on Massachusetts public projects?

Sections 39G and 39K of chapter 30 cap retention at 5 percent of the approved amount of each periodic payment.

When must a Massachusetts public owner pay after substantial completion?

Under § 39K, the balance is due within 65 days after the earliest completion trigger. Under § 39G, the substantial completion estimate is due within 65 days of the declaration and releases all retainage except 1 percent.

Are pay-if-paid clauses enforceable in Massachusetts?

On private contracts covered by c. 149, § 29E ($3,000,000 or more, excluding 1 to 4 unit residential), they are void except for narrow exceptions tied to the claimant's uncured default or the payer's insolvency. The same jobs are subject to the 5 percent retainage cap in § 29F.

What interest applies to late public payments in Massachusetts?

Three percentage points above the rediscount rate charged by the Federal Reserve Bank of Boston, under §§ 39G and 39K.

Can a Massachusetts subcontractor get paid directly by a public owner?

Yes. Under c. 30, § 39F, a sub not paid within 70 days after substantial completion of its work can send a sworn demand for direct payment by certified mail.

Sources

  1. Massachusetts General Laws: c. 30, § 39K
  2. Massachusetts General Laws: c. 30, § 39G
  3. Massachusetts General Laws: c. 30, § 39F
  4. Massachusetts General Laws: c. 149, § 29E
  5. Massachusetts General Laws: c. 149, § 29F, Payment of retainage in private construction projects

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.