Mechanics liens

Massachusetts mechanics lien law and deadlines

A Massachusetts lien takes three filings: a notice of contract (60 or 90 days), a statement of account (90 or 120 days), and a lawsuit within 90 days after the statement. The earliest triggering event controls each deadline.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Massachusetts General Laws Chapter 254 builds a mechanics lien in three steps, each with its own clock. First, record a notice of contract at the registry of deeds. Second, record a statement of account showing what is owed. Third, file a civil action to enforce within 90 days after the statement. Each filing deadline is the earliest of several dates, and the owner can shorten your time by recording a notice of substantial completion or termination.

Massachusetts lien deadlines at a glance (M.G.L. c. 254, sections 2, 4, 8, 11)
StepDeadline (earliest of)Where
Notice of contract60 days after notice of substantial completion is recorded; 90 days after notice of termination; 90 days after your last labor or materialsRegistry of deeds where the land lies
Statement of account90 days after notice of substantial completion; 120 days after notice of termination; 120 days after your last labor or materialsRegistry of deeds where the land lies
Civil action to enforce90 days after filing the statement of accountCourt
Notice of identification (optional, lower tiers)Within 30 days of starting work, certified mail to the original contractorSent, not recorded

Who has lien rights in Massachusetts

Section 2 covers anyone with a written contract with the owner (or someone acting for or with the owner's consent) for labor, including construction management and general contractor services, or for materials, rental equipment, appliances, or tools. Section 4 extends rights to anyone working under a written contract with the contractor or with a subcontractor of the contractor, which reaches subs, sub-subs, and suppliers. Section 4 also covers people who perform professional services under those contracts.

The phrase written contract does real work here. A supplier selling on a phone order with no written terms has a weaker position. Get a signed credit application, PO acceptance, or subcontract on file before the first delivery.

Step one: the notice of contract

You can record a notice of contract any time after the written contract is signed, even before work starts. That is the smart move on large jobs, because the lien does not exist until the notice is recorded and, for subs, until the owner gets actual notice of the filing. The outside deadline is the earliest of 60 days after the owner records a notice of substantial completion, 90 days after a notice of termination, or 90 days after your last day of work or supply.

A sub's lien is capped at what is due or will become due under the original contract on the date the sub notifies the owner of its filing. A lower-tier claimant without a contract with the original contractor is generally capped at the balance under the subcontract that includes its work, as of when it files. That second cap falls away if the claimant sent the original contractor a written notice of identification by certified mail, return receipt requested, within 30 days of starting work. It is optional, but it is the closest thing Massachusetts has to a preliminary notice, and it is cheap insurance for a sub-sub or supplier.

Step two: the statement of account

Under section 8, the lien dissolves unless you record a statement of account by the earliest of 90 days after the notice of substantial completion, 120 days after the notice of termination, or 120 days after your last labor or materials. The statement must give a just and true account of the amount due or to become due, with all just credits, a brief property description, and the owners' names as set out in the notice of contract. It can be filed before the owner's notices.

Example: a mechanical sub on a $2.3 million Worcester lab fit-out last works on May 1. The owner records a notice of substantial completion on May 20. The notice of contract is due by July 19 (60 days after May 20, which beats 90 days after May 1). The statement of account is due by August 18 (90 days after May 20). Most subs assume 90 and 120 days from their last day and miss both.

Step three: suit within 90 days

Section 11 dissolves the lien unless a civil action to enforce it is commenced within 90 days after the statement of account is filed. That is a short window. Line up counsel when you record the statement, not after.

Lien waivers in Massachusetts

Section 32 voids contract terms that bar filing a notice of contract, bar enforcing a lien, or subordinate lien rights. The exceptions include a Partial Waiver and Subordination of Lien, which must be substantially in the statutory form with no material deviation. It waives rights for work through the payment period on receipt of the stated payment, excluding retainage, unpaid change orders, and disputed claims, and subordinates rights to the lender's advances through the 25th day after the period. It is signed under penalties of perjury. A GC handing subs a custom lien waiver that waives more than the statute allows is creating an unenforceable document.

Residential work

The Chapter 254 sections covered here apply the same notice of contract and statement of account steps to residential and commercial work, with no separate homeowner track in their text. The practical protection for homeowners is the cap tied to the amount still owed under the original contract when the sub gives notice. Check the full chapter and the owner's situation before filing against an owner-occupied home.

Public projects use payment bonds

Public property cannot be liened. Under M.G.L. c. 149, section 29, public construction contracts over $25,000 require a payment bond of at least 50 percent of the contract price. A claimant with no direct contract with the bond principal must send written notice by registered or certified mail within 65 days after last furnishing labor or materials, and must file suit within one year after its last work.

More Massachusetts guides: contractor licensing, prevailing wage, and prompt payment. Smart Business Automator's accounts receivable automation can hold each job's notice of contract, statement, and suit dates next to the open balance.

Frequently asked questions

How long do I have to file a mechanics lien in Massachusetts?

The notice of contract must be recorded by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after your last work. The statement of account follows by the earliest of 90, 120, or 120 days from those same events.

Does Massachusetts require a preliminary notice?

No preliminary notice is required to have a lien. Lower-tier claimants can send an optional notice of identification to the original contractor within 30 days of starting work, which removes a cap on their lien amount.

How long does a Massachusetts lien last?

The lien dissolves unless a civil action is filed within 90 days after the statement of account is recorded.

Can a subcontract waive my Massachusetts lien rights?

Generally no. Section 32 voids advance waivers and subordinations, except for listed items such as the statutory Partial Waiver and Subordination of Lien given with a payment.

What is the payment bond claim deadline on Massachusetts public jobs?

Claimants without a direct contract with the bond principal give written notice within 65 days after last furnishing labor or materials and sue within one year after their last work.

Sources

  1. Massachusetts Legislature: M.G.L. c. 254, section 2, notice of contract by contractors
  2. Massachusetts Legislature: M.G.L. c. 254, section 4, subcontractor notice of contract
  3. Massachusetts Legislature: M.G.L. c. 254, section 8, statement of account
  4. Massachusetts Legislature: M.G.L. c. 254, section 11, enforcement action
  5. Massachusetts Legislature: M.G.L. c. 254, section 32, waivers and statutory form
  6. Massachusetts Legislature: M.G.L. c. 149, section 29, public works payment bonds

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment