Prompt payment

Michigan prompt payment act and retainage rules

Michigan's public works retainage law (MCL 125.1561 and following) lets a public agency hold up to 10 percent until the work is 50 percent in place, requires retained funds to sit in an interest-bearing account, and sets progress payments at 30 days after certification. Michigan has no broad private prompt pay statute in the sections reviewed here.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Michigan's main prompt payment act style rules for construction sit in MCL 125.1561 to 125.1564, which apply to public agency contracts for publicly funded facilities. A progress payment is due 30 days after the architect or engineer certifies the work is in place, or 15 days after the agency receives state or federal funds, whichever is later. Retainage is capped at 10 percent of work in place until the job is 50 percent complete, and the agency must deposit retained funds in an interest-bearing account. Private work runs on the contract: the statutes reviewed here set no private owner payment deadline or retainage cap.

Michigan public contract payment and retainage rules at a glance (MCL 125.1561 to 125.1564)
RulePublic agency contractsPrivate work
Owner pays prime (progress)30 days after architect or engineer certification, or 15 days after agency receives state or federal funds, whichever is later (125.1562(3))No general statute found; contract controls
Interest on late paymentContractor may add reasonable interest to the next payment request; no rate set (125.1562(4))Contract controls
Retainage cap10% of work in place until 50% in place; after that, more only for cause, up to 10% of work beyond 50% (125.1563(2))No statutory cap found
Where retainage is heldInterest-bearing account at a regulated in-state institution, tracked per contract (125.1563(3))Contract controls
Early release optionAt 94% in place, release of retainage plus interest against an irrevocable letter of credit (125.1563(5))Contract controls
Contracts covered$30,000 or more with more than three payments; MDOT, school districts, colleges, MSHDA and municipal electric utilities excluded (125.1561)Not applicable

Which public jobs the act covers

MCL 125.1561 defines a public agency as the state or a county, city, township, village, or other political subdivision, commission, or authority created by law. Several big owners are carved out: the state transportation department, school districts, junior and community colleges, the Michigan State Housing Development Authority, and municipal electric utilities. A covered contract involves a facility paid for with public funds or a special assessment, such as buildings, utilities, roads, bridges, sewers, or parks. Contracts under $30,000, or with three or fewer payments, are excluded. So a $2.1 million township water plant upgrade is in; a school district gym addition is not, and its bid documents control instead.

Progress payments on Michigan public work

Under MCL 125.1562(3), payment is due the later of 30 days after the architect or professional engineer certifies to the agency that the work is in place, or 15 days after the agency receives the state or federal funds that pay for it. The agency can defer processing until work earlier in the sequence is in place and approved. If it pays late, subsection (4) lets the contractor add reasonable interest on the past-due amount to its next payment request. The statute does not state a rate, which leaves the number open to argument. Keep the certification date for every pay app; it starts the clock.

Retainage, escrow, and release

  • First half of the job: no more than 10 percent of the dollar value of all work in place until the work is 50 percent in place.
  • Second half: no additional retainage unless the agency finds unsatisfactory progress or another specific performance cause; then it may hold up to 10 percent of the value of work beyond 50 percent.
  • Escrow: retained funds go into an interest-bearing account at a regulated financial institution in Michigan, not commingled with agency money, with retainage and interest accounted for separately on each contract. Funds from a state or federal grant not yet paid to the agency are excepted.
  • Letter of credit: once 94 percent of the work is in place, the contractor may ask for retainage plus interest in exchange for an irrevocable letter of credit for the full amount.
  • Delay disputes: at the agency's option, delay disputes go to an agent, who rules in writing within 14 days after an informal meeting; if unacceptable delay on the last 6 percent is found, interest on retained funds can go to the agency (125.1564).

Example: a paving contractor has $1,000,000 of a $1.8 million city street job in place. That is past the 50 percent mark, so retainage stays at the $90,000 held on the first $900,000 (10 percent) unless the city documents a performance cause. Interest on that $90,000 accrues in the escrow account and comes back with the retainage unless a delay finding shifts it to the city.

Private work and subcontractors

The sections reviewed here do not set a private owner payment deadline, a private retainage cap, or a prime to sub flow-down deadline, and MCL 125.1564 does not mention subcontractors. On private Michigan jobs, payment timing, retainage, and any pay-if-paid clause come from the contract. That makes the subcontract the whole ballgame: negotiate the payment days and the retainage rate before signing, and protect lien rights in parallel through the Michigan mechanics lien guide.

Smart Business Automator tracks retainage held, interest, and certification dates by job so the 30-day window and the 50 percent switch are visible. See construction accounts receivable automation.

Frequently asked questions

What is the retainage limit on Michigan public projects?

Under MCL 125.1563(2), no more than 10 percent of work in place until the work is 50 percent in place. After that, more can be held only for a specific performance cause, up to 10 percent of the value beyond 50 percent.

Does Michigan have a private prompt payment act?

The statutes reviewed for this page set no general private owner payment deadline or private retainage cap. Payment terms on private jobs come from the contract.

Do Michigan school district projects follow this retainage law?

No. MCL 125.1561 excludes school districts, junior and community colleges, MDOT, MSHDA, and municipal electric utilities from the definition of public agency.

Where does a Michigan public agency keep retainage?

In an interest-bearing account at a regulated financial institution in Michigan, not commingled with agency funds, with retainage and interest tracked per contract (MCL 125.1563(3)).

Sources

  1. MCL 125.1561, definitions (FindLaw copy, current as of January 1, 2025)
  2. MCL 125.1562, progress payments (FindLaw copy, current as of January 1, 2025)
  3. MCL 125.1563, retainage (FindLaw copy, current as of January 1, 2025)
  4. MCL 125.1564, delay disputes and retained funds (FindLaw copy, current as of January 1, 2025)
  5. Michigan Legislature: Michigan Compiled Laws

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment