Prompt payment

Missouri prompt payment act and retainage rules

Missouri has two separate sets of rules: RSMo 8.960 for public works (30 day owner payment, 15 day flow-down, 5 percent retainage cap) and RSMo 436.300 to 436.336 plus 431.180 for private commercial work.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

On a Missouri public works job, the public owner must pay the contractor within 30 days, retainage cannot exceed 5 percent, and the prime must pay its subs within 15 days of getting paid or owe 1.5 percent per month interest. Those rules sit in RSMo 8.960, which was moved from the old section 34.057 in 2022. Private commercial work has its own statute: retainage is capped at 10 percent, it is held in trust, it must come out within 30 days of substantial completion, and a contractor can swap it for a bond or letter of credit.

Missouri payment and retainage rules at a glance
RulePublic work (RSMo 8.960)Private work (RSMo 436.300 to 436.336, 431.180)
Owner to primeMonthly progress payments, paid within 30 days after the later of delivery, invoice receipt, or approval of the owner's estimateAs scheduled in the contract (431.180)
Prime to subWithin 15 days after the prime receives paymentRetainage share within 7 days after the prime receives it; progress timing set by the subcontract
Late payment interest1.5 percent per month after day 30 (owner) or day 15 (prime to sub)Court may award up to 1.5 percent per month plus attorney fees
Retainage cap5 percent; up to 10 percent where no bond is required because the job is not estimated over $50,00010 percent of each payment, owner to contractor
Retainage releaseAt least 98 percent within 30 days after substantial completion and acceptance; final payment within 30 days of the due dateWithin 30 days of substantial completion, less 150 percent of the cost of remaining items
Substitute securityNot addressed in 8.960Certificate of deposit, retainage bond, or letter of credit
ExcludedFederal funding or late state grant conflictsSingle-family and residential of four or fewer units

Public works payment under RSMo 8.960

Missouri's prompt payment act for public works covers the state and its political subdivisions, including counties, cities, and districts. Owners pay progress payments at least monthly, based on monthly estimates of work performed and material delivered, or by the terms of a lump sum contract. The 30 day clock starts at the latest of three events: delivery of the materials or services, delivery of the invoice to the place the owner designates, or delivery of the contractor's approval of the owner's estimate.

Miss day 30 and the agency owes interest of 1.5 percent per month on top of the payment, running until it is paid. The same rate applies to architects, engineers, landscape architects, and surveyors on their invoices. Payment counts as made when it is posted with the U.S. Postal Service or the agreed delivery service, or hand delivered.

Flow-down to subs and suppliers

When the prime gets paid, it pays each sub and supplier in proportion to the work each completed, less retention of no more than 5 percent. A short pay from the owner gets split pro rata across everyone, unless the owner rejected specific work in writing, in which case only that trade waits. A prime that fails to pay within 15 days without reasonable cause owes 1.5 percent per month from day 16. The rule runs down every tier.

Good faith withholding is allowed. The statute lists reasons such as defective work not remedied, disputed work, third party claims, and a sub's failure to pay its own labor and material bills. Amounts held back from a sub must be identified in writing and pulled from the next application to the owner. No late interest is owed on payments withheld in good faith for reasonable cause, but a court that finds bad faith can impose 1.5 percent per month from the invoice date and award attorney fees.

Public retainage and release

  • Cap: 5 percent of the contract or subcontract value. If no bond is required under section 107.170 because the job is not estimated to exceed $50,000, the owner may hold up to 10 percent.
  • Reduction: the owner may reduce or eliminate retainage on any payment if, in its opinion, the work is going well.
  • Early release for subs: if the owner, design professional, and prime agree a sub's work is done, the prime asks for a retainage adjustment so that sub can be paid in full.
  • Release: at least 98 percent of retainage, less authorized offsets, within 30 days after substantial completion and acceptance. If the owner says the work is not substantially complete, it must explain why in writing within 14 calendar days, or pay at least 98 percent within 30 calendar days.
  • Punch items: 150 percent of the value of each remaining item may be held until it is done.

Private construction payment in Missouri

Missouri does have private prompt pay rules, but they work differently. RSMo 431.180 says every party to a private design or construction contract must make scheduled payments under the contract terms, and a court or arbitrator may award up to 1.5 percent per month interest from the due date plus attorney fees. It does not apply to owner occupied residential property of four units or less. So the contract sets the payment dates, and the statute puts teeth behind them.

RSMo 436.300 to 436.336 handles private retainage on contracts formed after August 28, 2002, on all private projects except single-family and residential work of four or fewer units. Any contract term that conflicts with these sections is unenforceable.

  • Cap: up to 10 percent of each payment, owner to contractor, with more allowed if the contractor is not performing.
  • Trust: retainage is held in trust for the contractor and every sub and supplier not in default.
  • No over-withholding: a prime cannot hold more from a sub than the owner holds from the prime for that sub's work, unless the sub is not performing.
  • Substitute security: a certificate of deposit, a retainage bond, or an irrevocable letter of credit. If tendered after retainage was withheld, the owner pays out that amount within 5 working days.
  • Release: within 30 days of substantial completion, less 150 percent of the cost to complete remaining items. The prime pays each sub its share within 7 days of receipt.
  • Interest: wrongful retainage withholding can draw up to 1.5 percent per month, plus attorney fees to the prevailing party.

Substantial completion means the earlier of the architect or engineer issuing a certificate of substantial completion or the owner accepting the full contract. Picture a $900,000 office remodel with 10 percent retainage, so $90,000 held at the end. If the architect signs the certificate on June 1 and $8,000 of punch work remains, the owner can keep $12,000 (150 percent) and owes the rest by July 1. The drywall sub's share then has to move within 7 days of the GC's deposit.

Pay-if-paid and practical tips

None of the sections cited here expressly bans a pay-if-paid clause. On public work, though, the 15 day clock runs from the prime's receipt of payment, and on private work the retainage rules override inconsistent contract terms. Have counsel read any contingent payment language against those sections before you sign.

If payment stalls anyway, check the deadlines in the Missouri mechanics lien guide before they run. Public jobs often carry Missouri prevailing wage requirements too, and your license status is covered in the Missouri contractor license guide. Smart Business Automator tracks invoice dates, retainage held, and amounts due by job, which is what construction accounts receivable automation is built for.

Frequently asked questions

What is the maximum retainage on Missouri public works?

RSMo 8.960 caps retainage at 5 percent of the contract or subcontract value. If the contractor is not required to obtain a bond under section 107.170 because the job is not estimated to exceed $50,000, the public owner may hold up to 10 percent.

How fast must a Missouri prime contractor pay subs on a public job?

Within 15 days after receiving payment. Without reasonable cause for a delay, the prime owes interest of 1.5 percent per month from the end of that 15 day period until paid.

Does Missouri cap retainage on private projects?

Yes. RSMo 436.303 allows up to 10 percent of each owner payment, with extra withholding allowed if the contractor is not performing. The cap does not apply to single-family homes or residential buildings of four or fewer units.

Can a Missouri contractor replace retainage with a bond?

On private work, yes. RSMo 436.312 accepts a certificate of deposit, a retainage bond, or an irrevocable letter of credit. Subs can tender substitute security through the prime as well.

Where did RSMo 34.057 go?

It was transferred in 2022 and is now RSMo 8.960. Contracts and specs that still cite 34.057 are pointing to the same public works prompt payment rules.

Sources

  1. Missouri Revisor of Statutes: RSMo 8.960, prompt payments on public works
  2. Missouri Revisor of Statutes: RSMo 431.180, private design or construction payments
  3. Missouri Revisor of Statutes: RSMo 436.303, private retainage
  4. Missouri Revisor of Statutes: RSMo 436.312, substitute security
  5. Missouri Revisor of Statutes: RSMo 436.324, release of retainage
  6. Missouri Revisor of Statutes: RSMo 436.333, unenforceable terms and interest

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.