Prompt payment

Florida prompt payment act and retainage rules

Florida public owners can hold no more than 5 percent retainage on contracts over $200,000, local governments pay in 20 or 25 business days, and GCs must pay subs within 10 days of being paid. Private jobs fall under the Construction Contract Prompt Payment Law, s. 715.12.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Florida splits prompt payment three ways. Local governments follow the Local Government Prompt Payment Act, s. 218.735, Florida Statutes: payment is due 20 business days after a pay request is stamped received, or 25 if an agent must approve it first, and late money earns 2 percent per month. State agencies follow ss. 255.073 to 255.078. On both, the GC must pay subs within 10 days of being paid, and retainage is capped at 5 percent on contracts above $200,000. Private jobs fall under s. 715.12, the Construction Contract Prompt Payment Law, which sets interest at the s. 55.03 judgment rate plus 12 percent a year and requires retainage release within 14 days after substantial completion and punch list.

Florida payment and retainage rules at a glance
RuleLocal government (s. 218.735)State agencies (ss. 255.073 to 255.078)Private (s. 715.12)
Owner pays prime20 business days after stamped receipt; 25 if an agent must approveGoverned by s. 215.422; undisputed portion by contract date or 20 business days, whichever is earlierPer contract, once the request and required waivers are in
Prime pays sub10 days after GC is paid; subs pay their tiers in 7 days10 days; subs pay their tiers in 7 daysPer contract, after the payer is paid by the tier above
Late interest2% per month or the contract rate, whichever is greater2% per months. 55.03 rate plus 12% per year, from day 14 after due
Retainage cap5% of each progress payment (contracts over $200,000)5% of each progress payment (contracts over $200,000)No statutory cap
Retainage releaseWithin 20 business days after the punch list, less 150% of cost to completeWithin 20 business days after the punch list, less 150% of cost to complete14 days after substantial completion and punch list
Securities instead of retainageNot addressed in s. 218.735Not addressed in s. 255.078Treasury or Florida bonds, or insured CDs (s. 715.12(7)(c))

Local government jobs: s. 218.735

The clock starts when the pay request is stamped as received at the office the local government named in the contract or in a notice sent within 10 days of award or notice to proceed. If an agent such as the architect has to approve the request first, payment is due 25 business days after stamping, and the contractor may send an overdue notice. If the local government does not reject the request within 4 business days of that notice, it is deemed accepted (except any fraudulent or misleading portion). Without agent approval, payment is due in 20 business days. A rejection must be written within 20 business days and say what to fix. A corrected request must be paid or rejected within 10 business days, or after the next regular board meeting if a vote is required. Undisputed portions must be paid on time either way.

Retainage on local government work is capped at 5 percent of each progress payment (s. 218.735(8)). Owners may hold less, reduce it on a contract schedule, or release a sub's share early, and the GC must pass released retainage through to the subs it belongs to. The cap does not apply to contracts of $200,000 or less, or to federally funded work where federal rules conflict.

State agency jobs: ss. 255.073 to 255.078

For state public entities, s. 255.073 points to s. 215.422 for the basic payment timing, and requires the undisputed part of a disputed request to be paid by the contract date or 20 business days after receipt, whichever is earlier. The agency must forward a pay request to the Chief Financial Officer within 14 days of receiving it (s. 255.074). Late payments bear 2 percent per month. The same 5 percent cap and $200,000 threshold apply under s. 255.078, and the payment deadlines apply equally to retainage requests.

Punch list and retainage release on public jobs

Both public statutes force a single punch list with a cost to complete each item. It must be developed within 30 calendar days after substantial completion on projects under $10 million, or within 30 days (extendable by contract to 45) on projects of $10 million or more. Within 20 business days after the list is done, the owner pays the remaining contract balance, including retainage, minus 150 percent of the estimated cost to complete the listed items. Warranty items cannot hold up retainage, and retainage cannot be held to secure owner-controlled insurance premiums or a pending insurance audit. If the owner fails to develop the list on time, the contractor can bill all remaining retainage.

Private jobs: the Construction Contract Prompt Payment Law

Section 715.12 applies to written contracts to improve real property entered after December 31, 1992, where a construction lien is available under chapter 713. It does not set its own number of days to pay. A payer owes its payee when three things are true: the payee is entitled to payment under the contract and has sent a written request, the payer (other than the owner) has been paid by the tier above for that work, and the payee has provided any affidavits or lien waivers the owner needs under s. 713.06. Interest at the s. 55.03 rate plus 12 percent per year starts on the 14th day after payment is due. A payer that wants to reject an incomplete or wrong request has 14 days to return it with written reasons.

  • Retainage release: an owner may hold back part of each progress payment until substantial completion, then must pay the balance including retainage within 14 days after completion is certified (or a certificate of occupancy issues, or the owner takes possession) and the punch list is substantially done. If the contract sets no punch list deadline, the owner has 15 days.
  • Lower tiers: retainage held from subs bears interest 14 days after it comes due under the subcontract.
  • Securities: a payee may withdraw retainage by depositing Treasury securities, Florida bonds or notes, or insured certificates of deposit.
  • No early waiver: the right to interest cannot be waived before payment is due, and a dispute does not justify holding money for work not affected by it.

Pay-if-paid in Florida

Section 715.12 builds a condition into the payment duty: a payer other than the owner owes the payee once it has been paid for that work by the tier above. That works much like a pay-when-paid clause written into the statute. The public statutes tie the 10-day and 7-day flow-down to receipt of payment as well. Whether a true pay-if-paid clause shifts the owner's credit risk to a sub depends on contract wording and case law, so get legal review. Lien and bond deadlines keep running regardless; see Florida construction lien law.

Florida's public deadlines run in business days and its private rules turn on waivers and punch lists, which is a lot of dates to watch. Smart Business Automator logs pay request stamps, retainage held, and punch list status per job. See construction accounts receivable automation.

Frequently asked questions

What is the maximum retainage in Florida?

On public contracts over $200,000, both local governments and state entities may hold no more than 5 percent of each progress payment. Private contracts have no statutory cap; the percentage is whatever the contract says.

How long does a Florida local government have to pay a contractor?

20 business days after the pay request is stamped received, or 25 business days if an agent must approve it first. Late payments bear interest at 2 percent per month or the contract rate, whichever is greater.

How fast must a Florida GC pay subs on public work?

Within 10 days after the contractor receives payment for the sub's work. A sub must pay its own subs and suppliers within 7 days after it is paid.

When must a private Florida owner release retainage?

Within 14 days after substantial completion is certified, a certificate of occupancy issues, or the owner takes possession, once the punch list is substantially done. The contract can set a shorter time.

Does the 5 percent cap apply to federally funded local work?

Not where federal grant rules conflict with the Florida statute. The cap also does not apply to contracts of $200,000 or less.

Sources

  1. Florida Senate: s. 218.735, Timely payment for purchases of construction services (Local Government Prompt Payment Act)
  2. Florida Senate: s. 255.073, Timely payment for purchases of construction services
  3. Florida Senate: s. 255.074, Procedures for calculation of payment due dates
  4. Florida Senate: s. 255.077, Project closeout and payment of retainage
  5. Florida Senate: s. 255.078, Public construction retainage
  6. Florida Senate: s. 715.12, Construction Contract Prompt Payment Law

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment