Prompt payment

Ohio prompt payment act and retainage rules

Ohio requires contractors on both private and public jobs to pay subs within 10 calendar days of being paid, with 18 percent annual interest on late payments. State and local public improvement contracts add partial payment minimums, 30-day payment of approved estimates, no new retainage after 50 percent complete, and escrow of the money held.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

Ohio's main prompt payment rule for subs is Revised Code § 4113.61, and it reaches private and public work alike because its definition of owner covers public bodies and any person with an interest in the property. A contractor must pay a sub within 10 calendar days after receiving payment from the owner, and pass along the sub's share of final retainage within 10 calendar days after receiving it. Late payments earn 18 percent per year. For public improvements let by the state and by local public owners, Chapter 153 sets how much of each estimate must be paid, a 30-day payment window for approved estimates, an end to new retainage at 50 percent complete, and escrow of the money held. Single, two, and three family detached houses are excluded from § 4113.61, and the statute does not set a deadline for a private owner to pay the GC.

Ohio payment and retainage rules at a glance
RulePrivate workPublic work (state and local, Chapter 153)
Owner pays primeNot set by § 4113.61; contract terms governApproved estimates paid within 30 days (§ 153.14)
Prime pays sub10 calendar days after receiving payment from the owner (§ 4113.61)Same 10-day rule under § 4113.61
Late interest18 percent per year on the late sub payment (§ 4113.61)Owner: average prime rate at commercial banks in the nearest city over 100,000 (§ 153.14). Sub: 18 percent per year (§ 4113.61)
Amount paid each estimateContract termsLabor: at least 96 percent of approved estimates (§ 153.12). Delivered materials: 92 percent of invoice cost until incorporated (§ 153.14). No further retainage once the contract is 50 percent complete (§ 153.13)
Retainage releaseSub's share within 10 days after the GC receives it (§ 4113.61)Released from escrow when the major portion is substantially complete and occupied, in use, or accepted, less an amount to assure completion; the rest, with interest, 30 days from completion, acceptance, or occupancy (§ 153.13)
EscrowNot addressedRetained funds go into escrow once the job is 50 percent complete (§ 153.13). Money due from the public owner paid on the due date or deposited in escrow at an Ohio bank; 8 percent annual interest, compounded daily, if not (§ 153.63)
Pay-if-paidCannot stop a sub from making lien or bond claims (§ 4113.62(E))Same

The 10-day flow-down and 18 percent interest

Section 4113.61 applies to payments for improvements to property. When the contractor receives payment from the owner, it has 10 calendar days to pay each sub and supplier the amount due for the work covered by that payment. The contractor may hold back what is needed to resolve disputed liens or claims involving the work, but undisputed money has to move. Late payments earn interest of 18 percent per year on the amount due. The same 10-day rule applies when final retainage comes in: the GC passes each sub's share along within 10 calendar days of receiving it, or sooner if the subcontract says so.

Here is what that looks like. A painting sub has $36,500 due on a private medical office in Columbus. The GC gets paid on the 1st and pays the painter on the 41st, 30 days late. Eighteen percent a year over 30 days is about $540. That is not huge on one invoice, but it adds up fast across a dozen subs on the same job.

Clauses Ohio voids, and pay-if-paid

  • Surety bond waivers: a clause that waives rights under a surety bond is void (§ 4113.62(A)).
  • Final payment waivers: a clause that waives a pending or asserted claim because final payment was made is void once the other party has notice of the claim (§ 4113.62(B)).
  • No damages for delay: waivers of liability for delay caused by the owner's act or failure to act are void, and the same applies in subcontracts where the GC caused the delay (§ 4113.62(C)).
  • Out-of-state law or forum: a clause requiring another state's law, or dispute resolution outside Ohio, is void for Ohio real estate improvements (§ 4113.62(D)).

Ohio does not void pay-if-paid clauses outright. What § 4113.62(E) does say is that a contract making a sub's payment contingent on the GC's receipt of payment from someone else cannot stop the sub from filing a claim to protect its rights under the listed lien and bond statutes. So the clause may delay the check, but it cannot be used to waive the sub's lien or bond claim. Pair that with the Ohio mechanics lien deadlines and do not let them lapse while waiting.

Public improvements: estimates, retainage, and escrow

Chapter 153 governs the amount and timing of payments on public improvement contracts let by the state and by counties, townships, cities, school districts, and other political subdivisions, with a carve-out for certain Department of Transportation work (§ 153.12). Under § 153.12, partial payments for labor on unit or lump sum contracts must be at least 96 percent of the estimates prepared by the contractor and approved by the architect or engineer. Under § 153.14, owners may pay 92 percent of the invoice cost of approved materials delivered to the site or an approved storage location, with the balance paid once they are built in, and approved estimates must be paid within 30 days. Miss that and interest runs at the average prime rate of commercial banks in the city of over 100,000 nearest the project. The same interest applies to an unauthorized withholding of retainage.

Retainage is set by § 153.13. Once the contract is 50 percent complete, shown by payments of at least half the contract price, everything retained for faithful performance goes into the escrow account described in § 153.63 and no further funds are retained (contracts under $15,000 are excepted). When the major portion of the project is substantially complete and occupied, in use, or otherwise accepted, and there is no other reason to hold it, the retained percentages for that portion are released from escrow and paid to the prime, less only what is needed to assure completion. Whatever remains in escrow, with accumulated interest, is paid 30 days from completion, acceptance, or occupancy. Section 153.63 adds that money due from the public owner must be paid to the contractor on the day it is due or deposited in an escrow account at an Ohio bank or building and loan picked by mutual agreement, with 8 percent annual interest, compounded daily, owed if neither happens.

Public jobs in Ohio also bring prevailing wage and licensing requirements. Smart Business Automator tracks when each owner payment lands and starts the 10-day sub clock automatically, along with retainage held by job and by sub. See construction accounts receivable automation.

Frequently asked questions

How fast must an Ohio contractor pay subcontractors?

Within 10 calendar days after receiving payment from the owner, under Ohio Revised Code § 4113.61. Late payments earn 18 percent interest per year.

Does Ohio's prompt payment law apply to private projects?

Yes. Section 4113.61 defines owner to include any person with an interest in the property as well as public bodies. It does not apply to single, two, or three family detached dwelling houses.

Are pay-if-paid clauses enforceable in Ohio?

Ohio does not void them outright, but § 4113.62(E) says a contingent payment clause cannot stop a sub or supplier from filing a claim to protect its lien and bond rights.

When must retainage be released on Ohio public projects?

When the major portion of the project is substantially complete and occupied, in use, or accepted, the retained percentages for that portion are released from escrow, less what is needed to assure completion. The rest, with interest, is paid 30 days from completion, acceptance, or occupancy (§ 153.13). No new retainage is taken once the contract is 50 percent complete.

How quickly must a GC release retainage to subs in Ohio?

Within 10 calendar days after receiving the retainage from the owner, or a shorter period if the subcontract says so (§ 4113.61).

Sources

  1. Ohio Laws and Administrative Rules: Ohio Rev. Code § 4113.61, payment to subcontractors
  2. Ohio Laws and Administrative Rules: Ohio Rev. Code § 4113.62, void contract provisions
  3. Ohio Laws and Administrative Rules: Ohio Rev. Code § 153.12, partial payments
  4. Ohio Laws and Administrative Rules: Ohio Rev. Code § 153.13, estimates and retainage release
  5. Ohio Laws and Administrative Rules: Ohio Rev. Code § 153.14, payment of estimates and interest
  6. Ohio Laws and Administrative Rules: Ohio Rev. Code § 153.63, escrow of money due

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.