What is a draw schedule in construction?

A draw schedule is the agreed plan for releasing construction funds in stages, each tied to a milestone or a percentage of work completed.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A draw schedule lists each payment a contractor or builder can request over the life of a job, what has to be finished to earn it, and how much it is. It is most common on jobs financed with a construction loan, where the lender releases money in draws after an inspector confirms progress. Residential remodelers and custom builders also use draw schedules directly with homeowners.

Commercial jobs often do not use a fixed draw schedule. They bill monthly against a schedule of values instead. The two ideas are related, but a draw schedule is milestone-based and agreed up front.

How a draw schedule works on a real job

Say a builder signs a $520,000 custom home. The bank's loan agreement sets a draw schedule like the one below. Before each draw, the bank sends an inspector, and the builder submits an invoice, updated budget, and lien waivers for work already paid.

Example: milestone draw schedule for a $520,000 home
DrawMilestonePercentAmount
1Foundation complete10%$52,000
2Framing and roof dried in20%$104,000
3Rough mechanical, electrical, plumbing inspected20%$104,000
4Drywall and exterior finishes20%$104,000
5Cabinets, trim, flooring20%$104,000
6Final inspection and certificate of occupancy10%$52,000

The builder has to fund labor and material between draws. If framing takes six weeks, that is six weeks of payroll and lumber before draw 2 arrives. That gap is why the draw schedule belongs in the builder's cash flow projection.

Subs feel it too. A framing sub on this house may finish in week ten and wait until the bank funds draw 2 before the builder can pay. Smart subs ask to see the draw schedule before they sign, so they know which draw their invoice rides on.

Common problems

  1. Draws that lag the cost curve. Front-heavy work like foundations and framing costs more than its percentage of the price, so the builder finances the difference.
  2. Inspection timing. A draw request sent Friday may not be inspected for a week, and funding follows after.
  3. Missing paperwork. Lenders often hold a draw for one missing sub lien waiver or a title update.
  4. Change orders outside the loan. If the owner adds a $30,000 deck but the loan was not increased, the money has to come from somewhere else.
  5. Retainage on each draw, which some lenders hold until the end.

Related terms

A draw schedule connects to progress billing, retainage, and front loading. For residential deposits and payment terms, see how to set up deposit and payment schedules for residential jobs. Smart Business Automator's construction accounts receivable automation tracks each draw, its paperwork, and its due date.

Frequently asked questions

Who sets the draw schedule?

On financed jobs, the lender usually proposes it based on the budget, and the borrower and builder negotiate. On cash jobs, the contractor and owner agree on it in the contract.

Is a draw schedule the same as a schedule of values?

No. A schedule of values breaks the contract into line items for monthly percent-complete billing. A draw schedule sets fixed milestone payments. Some lenders use both.

What happens if a draw inspection fails?

The lender may fund part of the draw or none of it until the work is complete. The builder keeps carrying the cost until it passes.

Can a contractor stop work if a draw is late?

That depends on the contract and state law. Many contracts and prompt payment statutes give rights to suspend work after notice for nonpayment, but read the terms first.