Billing

What is a requisition in construction?

A requisition is a formal request. In construction it means one of two things: a contractor's request for payment on work completed, or an internal request from the field to buy materials, equipment, or services.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

Requisition is one of those words that changes meaning depending on who says it. When a project manager or an owner's rep talks about "the req," they usually mean a payment requisition: the contractor's periodic bill for work completed, the same thing many people call a pay application. When a superintendent or buyer says it, they often mean a material requisition: an internal request to order something, which then turns into a purchase order.

Both are requests, both need an approval, and both create a paper trail that ties money to a job and a cost code. Knowing which one is meant saves a lot of confused emails.

Payment requisitions

Public agencies, lenders, and contractors in parts of the Northeast often use "requisition" for the monthly bill. It lists work completed to date against the schedule of values, subtracts retainage and earlier payments, and states the amount now due. Supporting paperwork usually rides along: lien waivers, certified payroll on public jobs, stored material invoices, and sometimes an updated schedule. A monthly requisition is simply the regular cycle of these requests.

Example: a masonry sub on a school addition has a $260,000 subcontract. By the end of March it has completed $104,000 of work, and $62,000 was requisitioned in earlier months. The March requisition bills $42,000 of new work. With 5 percent retainage written into this subcontract, $2,100 is held and $39,900 is requested. If the backup is late or wrong, the GC kicks the whole requisition back and the sub misses the owner's cycle.

Material and purchase requisitions

Inside a contracting company, a requisition is the step before buying. A foreman needs 40 sheets of 5/8 Type X and a pallet of corner bead. The foreman submits a requisition with quantities, the job, the cost code, and the date needed on site. The PM or purchasing checks it against the budget and the bill of materials, then a buyer issues a PO to a supplier.

  • Why it matters: requisitions stop field crews from buying on a whim and charging it to whatever job is handy.
  • What it captures: who asked, for what job, against what budget line, and by when.
  • When to skip it: small companies often let the PM create the PO directly. The step pays off once several people can spend money.

Common mistakes

  1. Billing a payment requisition on a percentage that the superintendent would not sign off on. Overstated progress leads to overbilling and pushback.
  2. Sending a requisition without the backup the contract lists. Missing waivers or payroll reports are the most common reason for a returned req.
  3. Letting material requisitions bypass the budget check, so the job runs over before anyone sees it in the job cost report.
  4. Using the word without context in a contract. Define it, or reference the specific form.

Related terms

See progress billing, AIA G702, billing cycle, and procurement. Smart Business Automator builds payment requisitions from the schedule of values and tracks purchase orders against job budgets; see construction accounts receivable automation.

Frequently asked questions

Is a requisition the same as a pay application?

When people mean a payment requisition, yes. It is a regional and agency term for the same periodic request for payment based on work completed.

What is the difference between a requisition and a purchase order?

A material requisition is an internal request to buy something. A purchase order is the document sent to the supplier that commits the company to the purchase.

What usually goes with a payment requisition?

The continuation sheet or schedule of values, lien waivers, and whatever else the contract lists, such as certified payroll on public work or invoices for stored materials.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment