What is a monthly requisition in construction?

A monthly requisition is the contractor's formal request for payment for work completed and materials stored during the billing period, usually submitted on a set day each month.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

A monthly requisition (often shortened to "req") is the progress bill a contractor submits each month on commercial work. In much of the Northeast the word requisition is used where other regions say pay application or pay app. It means the same thing: a package that shows the value of work completed to date against the schedule of values, subtracts retainage and prior payments, and states the amount due this period. See also requisition.

Many commercial jobs use the AIA format: a summary sheet like the AIA G702 and a continuation sheet like the AIA G703. Public owners and lenders often have their own forms with the same structure.

What goes in a monthly requisition

  • Summary page with the contract sum, approved change orders, work completed to date, retainage, previous payments, and current amount due.
  • Continuation sheet listing each schedule of values line, percent complete, and stored materials.
  • Lien waivers: conditional for this period, unconditional for the last one, for the GC and often its subs.
  • Backup for stored materials, such as invoices, photos, and insurance.
  • Certified payroll on prevailing wage jobs.
  • Any owner-specific items, such as updated schedules or sub payment affidavits.

How the monthly cycle works

Say the contract requires requisitions by the 25th, covering work through month-end. On a $1,450,000 office renovation in month four:

Example: month four requisition
LineAmount
Contract sum plus approved changes$1,480,000
Work completed and stored to date$612,000
Retainage at 10%$61,200
Earned less retainage$550,800
Less previous payments$418,500
Current payment due$132,300

Before the 25th, the GC collects subs' requisitions (often due several days earlier), reviews them against field progress, rolls them into its own requisition, and sends the package to the architect. Many GCs submit a pencil draft first so the architect can agree on percentages before the final goes in. After certification, the owner pays on the timeline set by the contract and any applicable prompt payment law.

Common mistakes

  1. Missing the cutoff. Many contracts say a late requisition rolls into next month, which can delay payment by 30 days or more.
  2. Billing for change orders that are not executed yet. Most owners reject those lines.
  3. Missing lien waivers from subs, which stalls the whole package.
  4. Percent complete that does not match what the architect sees in the field, causing short pays.
  5. Math errors carried from last month's previous payments line.

Subcontractors should treat the GC's due date as their own deadline minus a few days. A sub's requisition that arrives after the GC has sent its package to the owner usually waits a full month for the next cycle.

For the forms, see how to fill out AIA G702 and G703 and how progress billing works. Smart Business Automator builds each requisition from schedule of values progress, attaches waivers, and tracks it through approval and payment; see construction accounts receivable automation.

Frequently asked questions

Is a requisition the same as a pay application?

Yes. Requisition is the common term in some regions, especially the Northeast, while others say pay application. Both are progress billing requests.

When is a monthly requisition due?

The contract sets the date, often a fixed day each month. Subcontractors are usually due several days earlier so the GC can compile them.

What is a pencil requisition?

A draft requisition shared with the owner or architect before the official one, so both sides can agree on percent complete first.

Can stored materials be included in a requisition?

Often yes, if the contract allows it and you provide invoices, proof of insurance, and storage details.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.