What is AIA billing in construction?

AIA billing is a progress billing method where the contractor bills each month on the AIA G702 Application and Certificate for Payment and the G703 Continuation Sheet, showing percent complete against a schedule of values.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

AIA billing means billing a construction job in monthly installments using the American Institute of Architects payment forms: the AIA G702 summary page and the AIA G703 continuation sheet. Instead of sending a single invoice for a lump amount, the contractor reports how much of each line of the schedule of values is complete, the architect or owner's rep checks it, and the owner pays what was earned minus retainage.

People say "AIA billing" even when no architect is involved. A lot of general contractors and lenders ask subs for an "AIA style" pay app on a homemade spreadsheet that copies the G702 and G703 layout. The format matters more than the logo, because everyone up the chain knows how to read it.

How AIA billing works month to month

The process starts before the first bill. At contract signing the contractor submits a schedule of values that splits the contract sum into lines such as mobilization, sitework, concrete, framing, MEP rough-in, and finishes. Once that is approved, it becomes the frame for every pay app on the job.

  1. Near the billing cutoff (often the 25th of the month), the PM walks the job and estimates percent complete for each line.
  2. The office enters those numbers on the G703, adds any approved change orders as new lines, and lists materials stored on site or off site.
  3. The G703 totals carry to the G702, which calculates retainage, subtracts what was paid before, and shows the current payment due.
  4. The contractor signs, the pay app goes out with backup (lien waivers, stored material invoices, certified payroll if required), and the architect certifies the amount or a revised one.
  5. The owner pays the certified amount, usually on a schedule set by the contract and any state prompt payment law.

A worked example

Say a GC holds an $850,000 contract to build out a medical office, with 10 percent retainage. Through month two, $210,000 was billed. In month three the PM marks framing at 100 percent, electrical rough-in at 60 percent, and drywall at 25 percent. Those percentages produce $140,000 of new work this period, plus $18,000 of light fixtures stored in a locked conex on site.

Month three AIA pay app, simplified
ItemAmount
Completed and stored to date$368,000
Retainage at 10 percent$36,800
Total earned less retainage$331,200
Less previous payments ($210,000 less retainage)$189,000
Current payment due$142,200

The math is simple. The arguments are about the percentages. If the architect thinks drywall is closer to 15 percent, the certified amount drops and the contractor waits another month for the difference.

Common AIA billing mistakes

  • Front-loading the schedule of values. Inflating early lines like mobilization gets cash in sooner, but reviewers spot it and may reject the whole SOV. See front-loading.
  • Billing unapproved change orders. Pending changes belong on a separate log until signed. Adding them to the G703 early is one of the fastest ways to get a pay app sent back.
  • Stored materials without proof. Most owners want invoices, photos, and sometimes insurance or a bill of sale before paying for material that is not installed.
  • Math that does not tie. Previous application columns must match what was certified last month, not what was requested.
  • Missing backup. A pay app without the required lien waivers can sit on a desk until the next cycle.

Related terms

AIA billing is one form of progress billing. It feeds the pay application, drives overbilling and underbilling on the WIP report, and ends with release of retainage at closeout. For a line-by-line walkthrough, read how to fill out AIA G702 and G703. Smart Business Automator builds the pay app from the job's schedule of values and change order log, so the G703 numbers tie to the books before anyone signs.

Frequently asked questions

Do I need to buy AIA forms to do AIA billing?

Official G702 and G703 documents are licensed from AIA Contract Documents. Many contractors bill on their own forms that follow the same layout, which owners often accept unless the contract requires the official documents. Check the contract.

Is AIA billing only for commercial work?

Mostly, but not only. Custom home builders working with a construction lender often bill in the same format because the lender's inspector reviews percent complete line by line.

How often does AIA billing happen?

Usually monthly, on a cutoff date set in the contract. Some contracts set a pencil draft date a week earlier so the architect can review numbers before the formal submission.

What is the difference between AIA billing and a regular invoice?

A regular invoice bills a fixed amount for work or a milestone. AIA billing reports cumulative progress on every line, applies retainage, and requires the architect or owner to certify the amount.

Sources

  1. AIA Contract Documents: Summary of G702-1992, Application and Certificate for Payment
  2. AIA Contract Documents: Instructions for G703-1992, Continuation Sheet