Prompt payment

Alabama prompt payment act and retainage rules

Alabama runs two separate systems: Section 39-2-12 for public awarding authorities and the Prompt Pay Act (Title 8, Chapter 29) for private commercial work. Each sets its own payment clock, interest rule, and retainage cap.

An office manager and contractor review invoices with a calculator and laptop in a construction office.
Review invoices, committed costs, and cash timing together before making project decisions. AI-generated illustration.

On Alabama public work, the awarding authority must pay an accepted partial payment estimate within 35 days, can hold no more than 5 percent retainage, and stops holding new retainage once the job hits 50 percent complete. On private work covered by the Alabama Prompt Pay Act, the owner pays on the contract terms or within 30 days if none are agreed, subs get paid within 7 days of the GC receiving funds, retainage is capped at 10 percent until 50 percent complete, and late money earns 1 percent per month.

Alabama payment and retainage rules at a glance
RulePublic work (Ala. Code 39-2-12)Private work (Ala. Code 8-29-1 to 8-29-8)
Owner to primeMonthly, no later than 35 days after the awarding authority accepts the estimatePer contract terms; 30 days after receipt of the pay request if no terms are agreed
Review of pay requestDesignated person reviews within 10 days (20 days for ALDOT)Owner must give written notice of a dispute within 15 days
Prime to subNot set by 39-2-12; follow the subcontractPer subcontract terms, or 7 days after receiving the owner's payment
Interest on late paymentRate assessed for underpayment of taxes under Section 40-1-44(a)1 percent per month (12 percent per year)
Retainage cap5 percent, and no further retainage after 50 percent completion; none on ALDOT road and bridge contracts10 percent, and no further retainage after 50 percent completion
Retainage releaseHeld until final completion and acceptance; final payment due 35 days after closeout items are deliveredNo later than 60 days after the contractor's work is complete or substantial completion, whichever is first
Escrow or securitiesYes, escrow account or deposit of securities if the contract provides for itNot addressed in the statute

Public projects: Section 39-2-12

Section 39-2-12 governs partial and final payments by awarding authorities such as cities, counties, school boards, and state agencies. Partial payments are made at the end of each calendar month as the work progresses, but in no case later than 35 days after the awarding authority accepts that the estimate and the contract's partial payment terms have been met. The contract has to name a person who reviews the pay request. That person has 10 days to accept it or flag an error in writing (20 days on Department of Transportation contracts).

If the undisputed amount is not paid inside the 35 days, the contractor is owed interest at the rate set for underpayment of taxes under Section 40-1-44(a). That rate is published by the state rather than fixed in the statute, so look it up for the period the money was late. An agreement signed after contract execution that stretches the 35 days is not enforceable. A few exceptions matter: interest is not due for fiscal year-end processing delays or announced closures, the timing rules do not apply to contracts administered by the Alabama Building Commission, and if the job is funded by a grant or reimbursement that arrives after award (and the bid documents say so), the clock starts when the authority receives the funds, after which it has 10 days to process payment.

Public retainage and the escrow option

The cap is low compared with most states. The awarding authority may hold not more than 5 percent of the work done and stored materials, and after 50 percent completion no further retainage is withheld. Run the math on a $2,000,000 school addition: the most retainage the owner can be sitting on is about $50,000, because holding stops at the halfway point. ALDOT highway, bridge, and road contracts carry no retainage at all.

Retainage is held until final completion and acceptance of all work, unless the contract allows one of two alternatives. Under subsection (f), the money can go into an escrow account at an Alabama bank or savings and loan, invested in deposits or government bonds, with interest paid to the contractor. Under subsection (g), the contractor can pull retainage out by depositing approved securities with the State Treasurer or the local official holding the funds. Final payment becomes due 35 days after the contractor delivers a certified voucher, any required release of claims, and proof of advertisement. A separately priced building or division of the work can be paid in full, including its retainage, when it is completed and accepted.

Private projects: the Alabama Prompt Pay Act

Title 8, Chapter 29 covers private construction. It does not apply to residential homebuilders, residential projects of 16 or fewer units, contracts of $10,000 or less, or contracts with state or local governments. Everything else (an office build-out, a warehouse, a medical clinic) falls under it.

  • Owner to GC: pay on the agreed terms, which must appear in the contract documents. With no agreed terms, payment is due within 30 days after the owner receives the pay request or invoice.
  • GC to sub, sub to sub-sub: pay on the subcontract terms, or within 7 days after receiving payment from the party above. Section 8-29-3(e) also requires the GC to pay each sub its share of an owner payment no later than the seventh day.
  • Disputes: the owner must give written notice of a disputed pay request within 15 days; contractors and subs have 5 days. A party may withhold up to 2 times the disputed amount for the reasons listed in Section 8-29-4.
  • Interest: 1 percent per month (12 percent per year) on late amounts. The right to interest cannot be waived before the payment is due.
  • Fees: the winning party in a suit under the chapter recovers reasonable attorneys' fees, court costs, and expenses.

Retainage on private work is capped at 10 percent of work properly done and stored materials, and after 50 percent completion no further retainage is withheld. The same cap applies GC to sub and sub to sub-sub, and a GC cannot hold a higher percentage from a sub than the owner holds from the GC. Over-withholding earns 1 percent per month interest. The owner must release retainage within 60 days after the contractor's own scope is complete or 60 days after substantial completion of the project, whichever comes first, with certificates of occupancy issued. Subsections (h) through (l) do not apply to projects for or by an electric utility regulated by the Public Service Commission.

What this means for pay-when-paid language

The private statute ties the sub's 7 day clock to the GC's receipt of payment, and it lets the parties set their own terms. That makes the subcontract the first place to look. A pay-if-paid clause or pay-when-paid clause will shape when money moves, and the statute does not say how courts treat those clauses. Read the subcontract with that in mind and see pay-if-paid vs pay-when-paid clauses.

Related Alabama guides

If payment stalls, your lien and bond rights run on their own deadlines: see Alabama mechanics lien law. For licensing see Alabama contractor license requirements, and for wage rules on public jobs see Alabama prevailing wage. The general concept is covered in the prompt payment act glossary entry. Smart Business Automator tracks retainage held, release dates, and aging pay apps by job, which is the core of construction accounts receivable automation.

Frequently asked questions

What is the retainage limit on Alabama public projects?

Section 39-2-12 allows the awarding authority to retain not more than 5 percent of work done and stored materials, and no further retainage after 50 percent completion. ALDOT road, highway, and bridge contracts have no retainage.

Does the Alabama Prompt Pay Act cover homebuilders?

No. Section 8-29-7 exempts residential homebuilders, residential projects of 16 or fewer units, contracts of $10,000 or less, and contracts with state or local governments.

How fast must an Alabama general contractor pay a subcontractor on a private job?

On the terms in the subcontract, or if none are agreed, within 7 days after the GC receives the owner's payment for that work. Late amounts earn 1 percent per month.

When must private retainage be released in Alabama?

No later than 60 days after the contractor's work is complete or 60 days after substantial completion of the project, whichever comes first, with certificates of occupancy issued.

Can I substitute securities for retainage on an Alabama public job?

Yes, if the specifications or contract provide for it. Section 39-2-12 allows an escrow account at an Alabama bank or a deposit of approved securities in lieu of retained amounts.

Sources

  1. Alabama Legislature (ALISON): Code of Alabama Section 39-2-12, Partial and Final Payments of Contractors by Awarding Authorities
  2. Alabama Legislature (ALISON): Code of Alabama Section 8-29-3, Timely Payments to Contractors and Subcontractors; Retainage
  3. Alabama Legislature (ALISON): Code of Alabama Section 8-29-4, Withholding Payment; Notice
  4. Alabama Legislature (ALISON): Code of Alabama Section 8-29-7, Exemptions from Chapter

Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment